A program is a container for the following except for:

A.

Program tasks

B.

Issues

C.

Cost plans

D.

Portfolios

Which statement defines the Project Workspace?

A.

A central location to view of all projects in a portfolio to prioritize work

B.

A central location for creating and managing projects

C.

A central location transform the navigation of lists and forms into an interactive graphical experience

D.

A central location for viewing and assessing business demands

Depending on the execution type selected for a particular project, one of these dashboards will also be available:

A.

Project Summary - Waterfall Dashboard

B.

Timecard Dashboard

C.

User Manager Dashboard

D.

PMO Dashboard

If a sub-project and parent project have different project currencies, this property should be set to true for cost roll-ups.

A.

com.snc.project.calculate_roi

B.

com.snc.project.rollup_project_start_date

C.

com.snc.project.copy.additional_attributes

D.

com.snc.project.multicurrency.rollup_if_different

Which property controls the changes in cost and resource plans with respect to the change in the start date of a demand or project?

A.

'Change Resource Plan, Cost Plan and Benefit Plan Start Date with Demand or Project Start Date Change'.

B.

'Enable altering of planned date for task in WIP/Closed'.

C.

'Rollup project start date from tasks'.

D.

'Calculate ROI percentage based on a project's estimated cost and its net value'.

Which of the following can be used to calculate planned cost when creating a resource plan?

Choose 2 answers

A.

Demand rate

B.

Rate card

C.

Default rate

D.

Project rate

The RIDAC workflow can be modified by using which recommended feature?

A.

Workflow Editor

B.

Project Form

C.

Flow Designer

D.

Service Catalog

What minimum role is required to assign a time sheet policy to a user?

A.

ppm_admin.

B.

timecard_admin.

C.

it_project_manager.

D.

It is not possible to assign a time sheet policy to a user.