ISTQB CTAL-TM - Certified Tester Advanced Level Test Management (CTAL-TM) v3.0
Your defect opened trend is converging to the closed trend but there is still a gap. What does that gap represent?
You tend to be conservative in your project estimations because you know how many things can go wrong and extend the schedule. You manager is not happy with your estimates and thinks you are being too negative with your numbers and not trying hard enough Which estimation method should you use to provide your manager with a positive' number while still also providing the number you think is more realistic?
Which of the following defect statistics will provide input to be used for improvement in the defect reporting process?
In an Agile project, when Is it acceptable lo not write a formal defect report when a defect is found''
You are a new lest manager in an organization You have been asked to assess the defect process to determine if there are any efficiency improvements that could be made that would reduce the cost of quality You have started digging through the defect Information What information would be most helpful for this investigation?
In what environment are you most likely to see multiple defect management systems used in one project?
You are managing the test team that is testing a new mobile application that provides a "step-by-step' hiking guide Your risk assessment resulted in the following table:

Your team has clone the depth and breadth testing for the GPS accuracy and usability features but when the product was given to beta testers there were some issues Despite the users reporting the app was easy to use at least one user walked off the edge of a cliff and another one ended up in a river. Your team has confirmed that the functionality is working correctly. and the GPS information is accurate.
What other area of testing should you now prioritize?
Which test process improvement model consists of five maturity levels?
Which of the following best describes the appraisal costs in the cost of quality'
Which of the following is the proper order for the stages of a tool lifecycle?