SAP C_S4PPM_2021 - SAP Certified Application Associate - SAP S/4HANA Portfolio and Project Management

Page: 3 / 3
Total 82 questions

Which of the following are consequence of releasing a phase?

NOTE: There are 2 correct answers to this question

A.

Predecessor phases are assigned the status locked

B.

Lower-level tasks and checklist are release

C.

Additional tasks cannot be added to the phase

D.

The phase type is set to read-only

You want to control the execution of subsequence phases in project management.

Which indicators must you activate in the phase type in customizing?

NOTE: There are 2 correct answers to this question

A.

The Release Success phase only after Approval indicator

B.

The approval phase indicator

C.

The completion required indicator

D.

The complete phase when Granting Approval indicator

Which information can be assigned to a business partner in project management?

NOTE: There are 3 correct answers to this question

A.

Work centers

B.

Areas and locations

C.

Personal numbers

D.

Production resources or tools (PRT)

E.

SAP users

What data influence the bottom-up scheduling of a project in portfolio management?

NOTE: There are 3 correct answers to this question.

A.

Duration of tasks

B.

Project type

C.

Role demands

D.

Relationships between phases

E.

Relationships between tasks