Weekend Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmas50

Exin EX0-008 - Agile Scrum Foundation

Page: 1 / 2
Total 59 questions

What is meant by the velocity of the team?

A.

The rate a team puts in a normal work day.

B.

The rate at which features are released to the customer.

C.

The rate at which the team completes the work.

D.

The rate at which the team renews itself.

A story was estimated at eight ideal hours. A working day is eight hours. Developers can get about six hours of work done on a daily basis.

What is the elapsed time required to complete the story?

A.

1.25 days

B.

1.33 days

C.

2 days

D.

This cannot be determined without knowing the velocity.

Why is planning poker an effective estimation technique?

A.

It generates a lot of useful discussion and gets team buy-in.

B.

It results in lower estimates as team members will estimate individually.

C.

It triggers a more detailed and task oriented break-up of the story.

Which means of communication is the most preferable to clarify the interpretation of a requirement?

A.

E-mail

B.

Face-to-face

C.

Instant messaging

D.

Telephone

Who is responsible for implementing the actions agreed upon by the team during a Retrospective?

A.

The Product Owner

B.

The Scrum Master

C.

The team

For a Sprint, progress is monitored in a burn-up chart with bars.

What makes the bar become longer?

A.

The progression of time.

B.

Work is added to the Sprint Backlog.

C.

Work is deleted from the Sprint Backlog.

Which statement describes Release Planning?

A.

After looking at all the stories in the backlog, the team estimates their effort in detail.

B.

The team meets with the customer to negotiate the scope, cost and time of the release.

C.

The team and the Product Owner agree on an initial plan for the delivery of features.

What message can you give to a customer about a key benefit of using Scrum?

A.

Scrum will give customers more control over day-to-day activities.

B.

Scrum will help the team accept changes into the project at no additional cost.

C.

The team will show a demonstration of working software every few weeks.

Sprint planning should result in a commitment on what will be delivered at the end of the Sprint. Who makes this commitment?

A.

The Product Owner

B.

The Scrum Master

C.

The team

Who knows most about the progress towards a business objective or a release?

A.

The Product Owner

B.

The Scrum Master

C.

The team