What is meant by the velocity of the team?
A story was estimated at eight ideal hours. A working day is eight hours. Developers can get about six hours of work done on a daily basis.
What is the elapsed time required to complete the story?
Why is planning poker an effective estimation technique?
Which means of communication is the most preferable to clarify the interpretation of a requirement?
Who is responsible for implementing the actions agreed upon by the team during a Retrospective?
For a Sprint, progress is monitored in a burn-up chart with bars.
What makes the bar become longer?
Which statement describes Release Planning?
What message can you give to a customer about a key benefit of using Scrum?
Sprint planning should result in a commitment on what will be delivered at the end of the Sprint. Who makes this commitment?
Who knows most about the progress towards a business objective or a release?