Weekend Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmas50

BCS ISEB-PM1 - BCS Foundation Certificate in IS Project Management

Page: 12 / 13
Total 625 questions

Control chart theory is based on the differentiation of the causes of variations in quality. Variations may be produced by assignable causes. All of the following are examples of assignable causes except:

A.

None of the other alternatives apply (all are examples)

B.

differences among materials.

C.

differences among machines.

D.

differences among workers.

E.

differences in each of these factors over time.

Which of the following is NOT included in a schedule change control system?

A.

Approval levels necessary for authorizing changes

B.

Tracking systems

C.

Paperwork necessary for making changes

D.

Limitations on the scope of changes

A work package has been scheduled to cost $1,000 to complete, and was to be finished today. As of today, the actual expenditure is $1,200 and approximately half of the work has been completed.

What is the cost variance?

A.

-$700

B.

-$200

C.

+$200

D.

+$500

In which of the following team development stages does the team begin to work together, develop trust, and adjust to the work habits and behavior?

A.

Norming

B.

Forming

C.

Storming

D.

Performing

Sally is a project manager working on a project that will require a specially engineered machine. Only three manufacturers can make the machine to the specifications Sally needs. The price of this machine is particularly critical to this project. The budget is limited, and there's no chance of securing additional funds if the bids for the machine come in higher than budgeted.

She's developing the evaluation criteria for the bidders' responses and knows all of the following are true except for which one?

A.

Sally will review the project management plan, including the risk register, as inputs to this process.

B.

Sally will base the evaluation criteria on price alone since the budget is a constraint.

C.

Sally will update the contract statement of work with any new information.

D.

Sally will use standard contract forms provided by her procurement department to write the contract for this machine.

The project budget is set at $150,000. The project duration is planned to be one year. At the completion of Week 16 of the project, the following information is collected:

Actual cost = $50,000 Plan cost = $45,000 Earned value = $40,000

What is the cost performance index?

A.

0.80

B.

0.89

C.

1.13

D.

1.25

The most common form of written project communication is

A.

Bulletin boards

B.

All of the other alternatives apply

C.

Publications

D.

Letters and memos

E.

Reports

What causes replanning of the project scope?

A.

Requested changes

B.

Project scope statement changes

C.

Variance analysis

D.

Approved change requests

Fast tracking is a schedule compression technique used to shorten the project schedule without changing project scope.

Which of the following can result from fast tracking?

A.

The risk of achieving the shortened project time is increased.

B.

The critical path will have positive total float.

C.

Contingency reserves are released for redeployment by the project manager.

D.

Duration buffers are added to maintain a focus on planned activity durations.

What process determines which risks might affect the project?

A.

Qualitative risk analysis

B.

Identify Risks

C.

Plan Risk Management

D.

Quantitative risk analysis

A work breakdown structure is most useful for:

A.

determining potential delays

B.

developing a cost estimate

C.

scheduling the start of tasks

D.

identifying individual tasks for a project

E.

A and C

The seller tells you that your activities have resulted in an increase in their costs. You should:

A.

Recommend a change to the project costs.

B.

Have a meeting with management to find out what to do.

C.

Ask the seller for supporting information.

D.

Deny any wrongdoing.

If a risk has a 20 percent chance of happening in a given month, and the project is expected to last five months, what is the probability that this risk event will occur during the fourth month of the project?

A.

Less than 1 percent

B.

20 percent

C.

60 percent

D.

80 percent

In the precedence diagramming method, which of the following is a logical relationship for the activities?

A.

Finish-to-start

B.

Applying leads and lags

C.

Activity-on-node

D.

Dependency determination

What risk technique is used to quantify the probability and impact of risks on project objectives?

A.

Expert judgment

B.

Risk registry

C.

Risk response planning

D.

Interviewing