Which of the following techniques incorporates a form of risk assessment?

A.

Arrow diagramming method

B.

Network diagramming

C.

Critical path method

D.

Three-point estimating

Plurality is a type of which of the following?

A.

Group creativity techniques

B.

Group decision making techniques

C.

Facilitated workshops

D.

Prototypes

Which of the following statements is in agreement with McGregor's concepts concerning Theory X and Theory Y managers?

A.

All of the other alternatives apply

B.

Theory X managers tend to be autocratic whereas Theory Y managers are more likely to delegate responsibility

C.

Both 1) Theory X managers view subordinates as being lazy, irresponsible, and resistant to change, and 2) Theory Y managers view subordinates as being imaginative, creative, and willing to accept responsibility

D.

Theory Y managers view subordinates as being imaginative, creative, and willing to accept responsibility

E.

Theory X managers view subordinates as being lazy, irresponsible, and resistant to change

Which of the following is closest to Juran's definition of Quality?

A.

conformance to requirements.

B.

fitness for use.

C.

customer focus.

D.

continuous improvement.

E.

All of the other alternatives apply.

Which of the following is an input to Develop Human Resource Plan?

A.

Team performance assessment

B.

Roles and responsibilities

C.

Staffing management plan

D.

Enterprise environmental factors

You are a project manager for the Swirling Seas Cruises food division. You're considering two different projects regarding food services on the cruise lines. The initial cost of Project Fish'n for Chips will be $800,000, with expected cash inflows of $300,000 per quarter. Project Picnic's payback period is six months.

Which project should you recommend?

A.

Project Fish'n for Chips, because the costs on Project Picnic are unknown.

B.

Project Picnic, because Project Fish'n for Chips' payback period is two months longer than Project Picnic's.

C.

Project Picnic, because Project Fish'n for Chips' payback period is four months longer than Project Picnic's.

D.

Project Fish'n for Chips, because its payback period is two months shorter than Project Picnic's.

What tool and technique includes all costs incurred over the life of a product by investment in preventing nonconformance to requirements?

A.

Cost of quality

B.

Measure of design

C.

Statistical control

D.

Systematic analysis