The project team has decided to substitute the flooring in the school gym with natural rubber flooring that has met the Sustainable Agriculture Standard. The cost of the substituted flooring is $80,000. The project will achieve

A.

Materials and Resources Credit, Building Product Disclosure and Optimization - Sourcing of Raw Materials,

Option 2. Leadership Extraction Practices

B.

Materials and Resources Credit, Building Product Disclosure and Optimization - Sourcing of Raw Materials,

Option 1. Raw Material Source and Extraction Reporting

C.

Materials and Resources Credit, Building Product Disclosure and Optimization Environmental Product

Declarations, Option 1. Environmental Product Declarations

D.

Materials and Resources Credit, Construction and Demolition Waste Management, Option 1. Diversion

If a commercial building is considered to have 100 peak visitors in a day, what is the minimum number of short-term

bicycle storage spaces that must be provided to earn one point under Location and Transportation Credit, Bicycle

Facilities?

A.

Three

B.

Four

C.

Five

D.

Ten

A design team pursuing LEED for a new office building project calculated that with the water fixtures specified for the project, a 24% water reduction can be achieved compared to the LEED baseline. What does this mean to the team in terms of pursuing LEED?

A.

The project cannot pursue LEED

B.

The project may pursue Water Efficiency Credit, Indoor Water Use Reduction

C.

The project does not meet Water Efficiency Prerequisite, Indoor Water Use Reduction, but can make up the points elsewhere in the rating system

D.

The project can meet the Water Efficiency Prerequisite, Indoor Water Use Reduction, but cannot earn any points under Water Efficiency Credit, Indoor Water Use Reduction

What supporting material is required for all LEED Building Design and Construction projects in order to document Location and Transportation Credit, Bicycle Facilities for the bicycle network?

A.

Photographs of bicycle network signage and directional signposts

B.

Photographs of the installed bicycle storage and shower facilities

C.

Vicinity map showing bicycle network, route and distance along network to eligible destination(s)

D.

Manufacturer specifications for the chosen bicycle storage facilities, including the number of bicycles supported by each bike rack

When the LEED AP is applying the Integrative Process to a Building Design and Construction project, when should the Owner’s Project Requirements (OPR) be created and updated?

A.

Prior to beginning design and are generally not updated

B.

Once the project design is completed and edited throughout the project

C.

During predesign and are edited throughout the project

D.

After the design is completed and are generally not updated

A school wants to incorporate natural daylighting in classrooms on all sides of the building. What can the project design team explain to the school district about how this strategy will affect the operational energy cost?

A.

Heat gain will reduce the air conditioning load

B.

Having the lights off reduces the electricity use

C.

Reduction in lighting fixture use reduces re-lamping

D.

There would be passive solar heating benefits to all of the classrooms

What building classification requires the energy model to determine the predicted power usage effectiveness (PUE) for Energy and Atmosphere Prerequisite, Minimum Energy Performance?

A.

Office

B.

Hospital

C.

Warehouse

D.

Data Center

For Energy and Atmosphere Credit, Advanced Energy Metering, what is the minimum amount of time that the metering system should store data?

A.

6 months

B.

12 months

C.

24 months

D.

36 months

A construction manager is looking for a project management tool that offers energy management strategies, benchmarking software tools for buildings, and product procurement guidelines. Which of the following is recognized by U.S. Green Building Council to assist them?

A.

Green Seal

B.

SCAQMD

C.

ENERGY STAR®

D.

SMACNA

Which of the following items must have safe collection, storage, and disposal for Materials and Resources Prerequisite, Storage and Collection of Recyclables?

A.

Food waste

B.

Medical waste

C.

Electronic waste