USGBC LEED-AP-BD+C - LEED AP Building Design + Construction (LEED v5 AP BD+C)
In the context of Core and Shell projects, which of the following strategies effectively aligns tenant spaces with LEED goals for sustainability?
A hospital certified underLEED V5in 2018 is designing and constructing a 21,000 ft² (1,950.96 m²) vertical addition, plus vegetated terraces and a mechanical penthouse.
The original hospital achieved the Gold certification level and was built with the capacity to add three floors—levels six through eight—to the top of the structure. This addition requires partial demolition of the roof and the floor below.
The project is designed to be architecturally cohesive with the existing building façade and is targeting Platinum certification under LEED v5.
The campus is in a dense urban area adjacent to several bus stops, a light-rail transit station within a 2,500 ft. (762 m) walking distance, and a bicycle docking point at the main entrance to the property. An on-campus shuttle service connects patients, visitors, and staff from the parking areas to each medical building and the light-rail station.
The healthcare campus has existing infrastructure; therefore, no new roads, sidewalks, parking structures, or ground-level landscaping will be installed.
The new floors have separate mechanical systems in the penthouse, but piping for public and patient restrooms, janitor closets, and staff break rooms connects directly to the main hospital plumbing system.
The newly installed medical equipment uses gas, steam, and chilled water supplied by the campus central plant.
Based on the project design and the credit options that the project team may attempt, what is the highest LEED certification level that can be achieved?
A project team compares a life-cycle assessment (LCA) model to a baseline design to determine the reductions in six impact categories. One impact category exceeds the baseline by 7%. Which alternative analyses should the team run to check different impact measurements?
When the LEED AP is applying the Integrative Process to a Building Design and Construction project, which of the following information is required to be present in the Owner ' s Project Requirements (OPR)?
Which is a benefit of earning Regional Priority credits?
What LEED Building Design and Construction project type should exclude weekend transit service from the transit service level calculations for Location and Transportation Credit, Access to Quality Transit, if the project occupants do not commute to the building during weekends?
Which of the following strategies can be used to reduce the internal load of a building?
When the project occupancy is not known, which method is recommended?
For a new project with a $10 million construction cost, the weight of the total recycled content is 0.9 tons (816.5 kilograms) each for post-consumer and pre-consumer recycled content. The value of the total recycled content is one million each for post-consumer and pre-consumer recycled content. What is the percentage of recycled content that contributes toward Materials and Resources Credit: Building Product Disclosure and Optimization - Sourcing of Raw Materials, Option 2, Leadership Extraction Practices?
When preparing the Sustainable Sites Prerequisite, Construction Activity Pollution Prevention, the Construction General Permit must contain which of the following?