Summer Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmas50

USGBC LEED-AP-BD+C - LEED AP Building Design + Construction (LEED AP BD+C)

Page: 4 / 13
Total 404 questions

Which of the following actions should be taken to ensure that project team members understand and prioritize the selection of materials compliant with the Materials and Resources Credit: Building Product Disclosure and Optimization?

A.

Select locally sourced and manufactured materials

B.

Procure materials directly from raw material suppliers

C.

Include all building materials in a whole-building life-cycle analysis

D.

Include the material requirements in the project specifications

Questions 1–5 are based on the same project scenario. Please use the scenario information when answering.

A hospital certified under LEED V5 in 2018 is designing and constructing a 21,000 ft² (1,950.96 m²) vertical addition, plus vegetated terraces and a mechanical penthouse.

The original hospital achieved the Gold certification level and was built with the capacity to add three floors—levels six through eight—to the top of the structure. This addition requires partial demolition of the roof and the floor below.

The project is designed to be architecturally cohesive with the existing building façade and is targeting Platinum certification under LEED v5.

The campus is in a dense urban area adjacent to several bus stops, a light-rail transit station within a 2,500 ft. (762 m) walking distance, and a bicycle docking point at the main entrance to the property. An on-campus shuttle service connects patients, visitors, and staff from the parking areas to each medical building and the light-rail station.

The healthcare campus has existing infrastructure; therefore, no new roads, sidewalks, parking structures, or ground-level landscaping will be installed.

The new floors have separate mechanical systems in the penthouse, but piping for public and patient restrooms, janitor closets, and staff break rooms connects directly to the main hospital plumbing system.

The newly installed medical equipment uses gas, steam, and chilled water supplied by the campus central plant.

Based on the project design and the credit options that the project team may attempt, what is the highest LEED certification level that can be achieved?

A.

Platinum

B.

Gold

C.

Silver

Which rating system is being used if all of the credits below have been submitted towards certification?

- Location and Transportation Credit, Reduced Parking Footprint

- Energy and Atmosphere Credit, Fundamental Refrigerant Management

- Indoor Environmental Quality Credit, Acoustic Performance

- Materials and Resources Credit, Persistent, Bio accumulative, and Toxic (PBT) Source Reduction - Lead, Cadmium, and Copper

A.

Building Design and Construction: Schools

B.

Building Design and Construction: Healthcare

C.

Building Design and Construction: Hospitality

D.

Building Design and Construction: Data Centers

LEED project boundaries that include multiple similar buildings which are all eligible for certification can be registered as which of the following?

A.

Batch project

B.

Group project

C.

Master Site project

D.

Neighborhood project

A project has a potable water source as well as two alternative water sources. Which of the following statements is applicable for a project using two alternative water sources?

A.

A project may not use two alternative water sources

B.

Target the uses that require the least treatment first

C.

Match uses by location: indoor sources to indoor uses, outdoor sources to outdoor uses

D.

All alternative water sources should be treated to potable water standards

A coastal mixed-use development pursuing LEED BD+C certification is evaluating flood-resilience strategies to protect against sea-level rise. Which of the following strategies most comprehensively addresses flood resilience for IPp1: Climate Resilience Assessment?

A.

Elevate all critical mechanical, electrical, and plumbing systems above the 500-year flood elevation and design ground-floor spaces with flood-tolerant materials, drainage infrastructure, and resilient finishes

B.

Design foundation walls with reinforced concrete, waterproof membranes, and active dewatering pumps to keep below-grade spaces dry and functional during flooding

C.

Specify native flood-tolerant vegetation with bioswales and rain gardens throughout the site to absorb stormwater runoff and reduce peak flow rates

Which of the following projects is eligible to pursue the Energy and Atmosphere Prerequisite, Minimum Energy Performance, Option 2. Prescriptive Compliance: ASHRAE 50% Advanced Energy Design Guide?

A.

50,000 ft2 (4 645 m2) office project

B.

80,000 ft2 (7 432 m2) hospital project

C.

110,000 ft2 (10 219 m2) school project

D.

140,000 ft2 (13 006 m2) retail project

Which of the following is required in determining the baseline for Water Efficiency Prerequisite, Indoor Water Use Reduction?

A.

Duration of use

B.

Building floor area

C.

Make and model of fixtures

D.

Proposed design fixture flow rates

Which of the following are the major factors determining the total irrigation requirement for a particular landscaping design?

A.

Planting density, soil conditions, irrigation efficiency and rainfall

B.

Relative humidity, site exposure, plant species and planting density

C.

Plant species, rainfall, evapotranspiration rate, site exposure and irrigation efficiency

D.

Plant species, rainwater tank size, evapotranspiration rate, site exposure and irrigation efficiency

Which of the following project types is required to consider the perimeter floor area instead of the regularly occupied floor area under the Indoor Environmental Quality Credit, Daylight calculations?

A.

Retail

B.

Schools

C.

Healthcare

D.

Core and Shell