USGBC LEED-AP-BD+C - LEED AP Building Design + Construction (LEED AP BD+C)
Water Efficiency Prerequisite, Outdoor Water Use Reduction, Option 2. Reduced Irrigation, requires that a project's landscape water requirement be reduced by what percentage from the calculated baseline for the project site's peak watering month?
A LEED Building Design and Construction project includes an outdoor stage for theatrical performances. In pursuit of Sustainable Sites Credit, Light Pollution Reduction the engineer has specified an LED fixture to illuminate actors on the stage while limiting light pollution. Which of the following suggestions should the LEED AP give to the project owner?
The design team and project owner decided not to pursue Energy and Atmosphere Credit, Enhanced Commissioning, but would hire a Commissioning Authority (CxA) to oversee the requirements for Energy and Atmosphere Prerequisite, Fundamental Commissioning and Verification. What is a required responsibility for the CxA to achieve the stated objective?
What are the Storage and Collection of Recyclables requirements for only Retail projects under the Materials and Resources Prerequisite?
A LEED Building Design and Construction: New Construction office building's HVAC system includes hot water from a central utility plant. The central utility plant is owned and operated by a management company. The office pays a flat fee for hot water, included as part of the lease. The management company does not meter or invoice for actual hot water consumption. For the project to meet the requirements for Energy and Atmosphere Prerequisite, Building-Level
Energy Metering, an energy meter must be installed for
When the LEED AP is applying the Integrative Process to a Building Design and Construction project, which of the following information is required to be present in the Owner's Project Requirements (OPR)?
For minimum acoustic performance, peak-hour is defined as M
What type of project would benefit from showing compliance with Energy and Atmosphere Prerequisite, Minimum Energy Performance, Option 2. Prescriptive Compliance: ASHRAE 50% Advanced Energy Design Guide?
A Photovoltaic (PV) system was installed on a 35,000 ft2 (3 252 m2) project. What actions need to take place in order to meet compliance for Energy and Atmosphere Prerequisite, Fundamental Commissioning (Cx) and Verification?
A Healthcare Project is constructing a new building adjacent to an existing LEED Certified hospital facility. The new building's location is on the same hospital campus as the certified facility. The entire hospital campus was analyzed with an Environmental Site Assessment (ESA) as part of the certified facility's project scope. The new building project needs to complete a new Phase I ESA if
