When planning a water-efficient landscape design, the designer should consider including

A.

potable water

B.

sprinkler system

C.

native vegetation

D.

permeable pavement

A design team is working on a new building project and is employing an integrated, whole-building approach. The architects want to increase the size of a glazed opening on the south facing wall. Which team members are first

affected by this change?

A.

Civil engineers

B.

Facility managers

C.

Landscape architects

D.

Mechanical engineers

Which of the following prerequisites or credits are affected by using plug-in devices when attempting to achieve Indoor Environmental Quality Credit. Thermal Comfort?

A.

Energy and Atmosphere Credit. Demand Response

B.

Energy and Atmosphere Credit. Advanced Energy Metering

C.

Energy and Atmosphere Prerequisite. Minimum Energy Performance

D.

Energy and Atmosphere Prerequisite. Building Level Energy Metering

Short-term bicycle storage in Location and Transportation Credit, Bicycle Facilities must be within 100 ft. (30 m) walking distance of any:

A.

Bicycle network

B.

Emergency access

C.

Main entrance

D.

Shower room

A project team is deciding on the impact of a proposed concrete walkway. Which of the following will be impacted as a result of adding the walkway?

A.

Site's impervious cover

B.

Project density calculations

C.

Erosion and sediment control plan during construction

D.

Air quality as a result of off gassing that occurs as concrete cures

Which of the following criteria must a Commissioning Authority (CxA) comply with in order to meet the requirements of the Energy and Atmosphere Prerequisite, Fundamental Commissioning and Verification of Building Energy Systems?

A.

Document commissioning authority experience for at least one building project

B.

Review the owner's project requirements (OPR) for project goals and expectations

C.

Be a part of the project's design and construction management team

D.

Report results, findings, and recommendations directly to the architect

Which of the following products must always be included in Materials and Resources credits?

A.

Faucets

B.

Furniture

C.

Interior Paint

D.

Fire suppression system

An existing vacant office building will be completely renovated and new mechanical, electrical and plumbing systems will be installed. 20% of the building's gross floor area will be complete at the time of certification. There will be a data center and some retail stores on the ground floor of the building at a future date. Which rating system is applicable for the building?

A.

LEED BD+C: Retail

B.

LEED BD+C: Data Centers

C.

LEED BD+C: Core & Shell Development

D.

LEED BD+C: New Construction & Major Renovation

The current facilities requirements (CFR) and operations and maintenance plan (OMP) required for Energy and Atmosphere Prerequisite, Fundamental Commissioning and Verification must include

A.

issue logs

B.

functional performance tests

C.

minimum outside air requirements

D.

installation verification (construction) checklists

A project will renovate a building with historic designation into new office space. The surface area of the existing building structure and envelope is 100,000 ft² (9,290 m²). How much of the existing building will need to be reused to earn 5 points for the Materials and Resource Credit, Building Life-Cycle Impact Reduction?

A.

90,000 ft² (8,361 m²)

B.

There is no minimum

C.

80,000 ft² (7,432 m²)

D.

At least 50% of the surface area