Summer Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmas50

USGBC LEED-AP-BD+C - LEED AP Building Design + Construction (LEED AP BD+C)

Page: 9 / 13
Total 404 questions

Questions 1–5 are based on the same project scenario. Please use the scenario information when answering.

A hospital certified under LEED V5 in 2018 is designing and constructing a 21,000 ft² (1,950.96 m²) vertical addition, plus vegetated terraces and a mechanical penthouse.

The original hospital achieved the Gold certification level and was built with the capacity to add three floors—levels six through eight—to the top of the structure. This addition requires partial demolition of the roof and the floor below.

The project is designed to be architecturally cohesive with the existing building façade and is targeting Platinum certification under LEED v5.

The campus is in a dense urban area adjacent to several bus stops, a light-rail transit station within a 2,500 ft. (762 m) walking distance, and a bicycle docking point at the main entrance to the property. An on-campus shuttle service connects patients, visitors, and staff from the parking areas to each medical building and the light-rail station.

The healthcare campus has existing infrastructure; therefore, no new roads, sidewalks, parking structures, or ground-level landscaping will be installed.

The new floors have separate mechanical systems in the penthouse, but piping for public and patient restrooms, janitor closets, and staff break rooms connects directly to the main hospital plumbing system.

The newly installed medical equipment uses gas, steam, and chilled water supplied by the campus central plant.

The project team is designing the maternity ward to increase patient interaction with the vegetated terraces and green roof to promote healing and reduce recovery time. Which of the following credits or prerequisites can be achieved through this design approach?

A.

EQc2: Occupant Experience

B.

SSc1: Biodiverse Habitat

C.

IPp2: Human Impact Assessment

Which of the following buildings meets the Minimum Program Requirements for LEED certification?

A.

A 1,500 ft2 (139 m2) Tourism Center located on a previously undeveloped one-acre site

B.

A 20,000 ft2 (1 859 m2) Transit Parking Garage located on a previously developed five-acre site

C.

A 2,500 ft2 (232 m2) mobile Health Clinic located on a previously constructed above-water dock

D.

A 5,000 ft2 (465 m2) Science Education center on an above-water pier that is being built specifically for the Education center

What issue must be present on the project site to achieve Location and Transportation Credit, High-Priority Site, Option 3. Brownfield Remediation?

A.

Mercury containing lamps

B.

Contaminated soil or groundwater

C.

Asphalt construction waste

D.

Asbestos tile and glue

What LEED Building Design and Construction project type should exclude weekend transit service from the transit service level calculations for Location and Transportation Credit, Access to Quality Transit, if the project occupants do not commute to the building during weekends?

A.

Schools

B.

Data centers

C.

Hospitality

D.

Warehouses and distribution centers

Which of the following is true regarding LEED Pilot Credits?

A.

Pilot Credits are not specific to the rating systems

B.

Pilot Credits can be attempted in the design review stage only

C.

A registered Pilot Credit must be replaced on the LEED project's scorecard if that pilot credit is removed from the Pilot Credit Library

D.

Pilot Credit feedback surveys must be completed

IPp1: Climate Resilience Assessment identifies a high risk of extreme heat caused by the urban heat-island effect and flooding caused by an impervious site. Which combination identifies an appropriate strategy for heat and sea-level or flooding risks?

A.

Heat: High-albedo white roof

Sea level: Emergency backup generators

B.

Heat: High-efficiency variable refrigerant flow system

Sea level: Green roof

C.

Heat: Exterior window shading and operable windows

Sea level: Sump pumps with backup power

During a design charrette, community neighbors raise a concern about potential glare resulting from a project's highly reflective roof. Which option should the LEED AP recommend to best address these concerns?

A.

Install a vegetative roofing system

B.

Change the design to reduce the amount of roofing area

C.

Change the roofing material to a dark material to eliminate the issue

D.

Increase the parapet height

When measuring sound pressure levels in a classroom to determine compliance with the HVAC background noise requirements of LEED Building Design and Construction: Schools, Indoor Environmental Quality Prerequisite, Minimum Acoustic Performance, what testing conditions are appropriate for the classroom?

A.

Furnished, teacher speaking, HVAC operating at maximum flow rates

B.

Unfurnished, teacher speaking, HVAC operating at typical level

C.

Furnished, no occupants, HVAC operating at typical level

D.

Unfurnished, no occupants, HVAC operating at maximum flow rates

The design team and project owner decided not to pursue Energy and Atmosphere Credit, Enhanced Commissioning, but would hire a Commissioning Authority (CxA) to oversee the requirements for Energy and Atmosphere Prerequisite, Fundamental Commissioning and Verification. What is a required responsibility for the CxA to achieve the stated objective?

A.

Verify installation and performance of the commissioned systems

B.

Review the building 10 months after substantial completion

C.

Verify that training requirements are completed

D.

Develop a systems manual for the commissioned systems

When required to measure residential and non-residential densities, Location and Transportation Credit, Surrounding Density and Diverse Uses, Option 1. Surrounding Density requires project teams to measure the residential and non-residential densities in what way?

A.

Measure densities within a ¼ mile (0.40 km) radius of the project boundary

B.

Measure densities within a ¾ mile (1.20 km) radius of the project boundary

C.

Measure densities within a â…“ mile (0.53 km) radius of the project boundary

D.

Measure densities within a ½ mile (0.80 km) radius of the project boundary