Who has the responsibility for monitoring the progress of benefits realization against the plan?
The engineering department has been asked to produce a weekly report for the programme board. The report will include data on how many new water meters have been installed in the last seven days. The programme manager is writing the assurance approach. The engineering department report has been included as part of the first line of defence.
Is this an appropriate application of the assurance’ theme, and why?
Which of following is NOT part of delivering the capability?
Which of the following is a programme management principle?
Which of the following defines an Emergent programme?
POTI model is part of which governance theme?
The CFO has informed the programme board that the predicted increase in electricity and gas customer numbers is too optimistic. The BCM has produced new targets based on this new information. The programme manager has updated the target operating model to reflect this.
Is this an appropriate application of the ‘align with priorities' principle, and why?
The task of organizational realignment relies heavily on getting results from existing staff and enhancing skills. Here are items of information to be recorded in the stakeholder engagement and communications plan. Under which heading should they be recorded?

The programme is starting Tranche 1 and there is a lot of dissatisfaction in the workforce about the planned merging of the engineering roles. The programme board has made some proposals on how to deal with this issue but is unsure whether to involve the sponsoring group.
According to the ‘decisions’ theme, which document should be consulted to clarify whether it is necessary to escalate this issue to the sponsoring group?
For a programme that focuses on Political and societal change which scenario will lead to lower probability of success?