Who has the responsibility for monitoring the progress of benefits realization against the plan?

A.

Business Change Manager

B.

Programme Office

C.

Senior Responsible Owner

D.

Programme Manager

The engineering department has been asked to produce a weekly report for the programme board. The report will include data on how many new water meters have been installed in the last seven days. The programme manager is writing the assurance approach. The engineering department report has been included as part of the first line of defence.

Is this an appropriate application of the assurance’ theme, and why?

A.

Yes, because the increased number of gas and electricity customers is dependent on the new water meters being installed

B.

Yes, because the programme board should use the report to monitor the progress of ongoing engineering work

C.

No, because the reporting progress by the engineering department demonstrates application of the ‘decisions' theme

D.

No, because everyone in the programme should have access to progress information, not just the programme board

Which of following is NOT part of delivering the capability?

A.

Start Projects

B.

Governance: Manage and control delivery

C.

Align projects with benefits realization

D.

Gateway reviews

Which of the following is a programme management principle?

A.

Quality and assurance management

B.

Remaining aligned with corporate strategy

C.

Leadership and stakeholder management

D.

Realizing the benefits

Which of the following defines an Emergent programme?

A.

Evolved from concurrent, individual projects with need to ensure compliance to organization strategy

B.

Must do programmes often due to result of an external event and aimed to avoid negative implications

C.

Translation of political priorities into a programme to refine and deliver desired changes

D.

Programme focused on transforming the way business functions

POTI model is part of which governance theme?

A.

Business Case

B.

Blueprint

C.

Vision

D.

Risk and issue management

The CFO has informed the programme board that the predicted increase in electricity and gas customer numbers is too optimistic. The BCM has produced new targets based on this new information. The programme manager has updated the target operating model to reflect this.

Is this an appropriate application of the ‘align with priorities' principle, and why?

A.

Yes, because the target operating model should be revisited over time

B.

Yes, because the programme manager is the producer of the target operating model

C.

No, because this new information should be reflected in the benefit profile

D.

No, because this new information should be reflected in the benefits map

The task of organizational realignment relies heavily on getting results from existing staff and enhancing skills. Here are items of information to be recorded in the stakeholder engagement and communications plan. Under which heading should they be recorded?

The programme is starting Tranche 1 and there is a lot of dissatisfaction in the workforce about the planned merging of the engineering roles. The programme board has made some proposals on how to deal with this issue but is unsure whether to involve the sponsoring group.

According to the ‘decisions’ theme, which document should be consulted to clarify whether it is necessary to escalate this issue to the sponsoring group?

A.

Programme strategy: issue resolution approach

B.

Issue register

C.

Programme strategy: decision-making approach

D.

Decision register

For a programme that focuses on Political and societal change which scenario will lead to lower probability of success?

A.

New legislation reacting to societal trends

B.

Change to current legislation

C.

Changes to public service delivery model

D.

Long term societal effects