PeopleCert MSP-Practitioner - MSP Practitioner, 5th edition Exam

Page: 3 / 4
Total 133 questions

Which of the following is Management document?

A.

Programme brief

B.

Project Dossier

C.

Issue Register

D.

Programme Mandate

There is a risk that the utilities market is changing, with green energy solutions becoming more attractive to customers. As UU does not currently offer this type of green energy, the benefits gained from cross-selling electricity and gas to current water customers may be overestimated.

Which activity is relevant in the ‘plan’ phase of the Plan-Do-Check-Act (PDCA) cycle?

A.

Scheduling daily monitoring of how many current water customers also buy either electricity or gas services

B.

Analysing the market trends for utility companies offering green energy solutions and how many customers they gain

C.

Surveying customers to assess if they are aware of UU's new green tariff introduced in response to this risk

D.

Purchasing and selling a small amount of energy from renewable sources to provide an element of environmental credibility

In Managing the Tranches, which role is responsible for preparing for the next tranche?

A.

The Programme Manager

B.

The Programme Board

C.

The Benefits Realization Manager

D.

The Programme Office

Halfway through Tranche 2, North City local government announced a new incentive programme to support green initiatives that help residents reduce their carbon footprint. UU is applying for this funding, claiming that its water smart meters and leak detection systems qualify as eco-friendly mechanisms aligned to the new government scheme. The cost of the application process will be more than paid for if UU is approved as part of the incentive programme.

Is this an appropriate application of the justification' theme, and why?

A.

Yes, because the programme budget should include financial contingency to deal with identified opportunities

B.

Yes, because the sponsoring group should pursue valuable opportunities and make them more likely to occur

C.

No, because the funding approach for this programme should ensure that the programme is self-funded by this point

D.

No, because the programme should consider the ‘do nothing’ option, plus at least two other options, before pursuing the opportunity

The Training Project has included some interactive games in the training materials. This is to help engineering staff members share ideas and experiences during the training of how to apply the new processes. However, the CEngO thinks that the engineering staff members will find this approach rather childish as they are very experienced and normally work independently. As a result, the CEngO has asked for the games to be removed from the training materials.

Is the CEngO's request an appropriate application of the 'knowledge' theme, and why?

A.

Yes, because the training materials should be documented in a clear format so that the engineers can access it

B.

Yes, because the engineers should be given time to reflect on the training so they can make improvements

C.

No, because games can be used to help the engineers think creatively and improve their learning

D.

No, because the objective of training is to ensure that the engineers learn lessons as quickly as possible

Who produces Business Case?

A.

Sponsoring Group

B.

SRO

C.

Programme Manager

D.

BCM

Which of following groups can be a stakeholder for building a city programme?

A.

Employees

B.

Political leadership

C.

People interested in being residents

D.

All of above

Which of the following is an Information Baseline?

A.

Governance

B.

Boundary

C.

Management

D.

All of above

The following statement needs to be recorded:

"The vision statement will be developed and tested in a facilitated workshop with the senior officers from each department, before final approval by the CEO."

In which section of the programme strategy should this be recorded?

A.

Governance approach

B.

Stakeholder engagement approach

C.

Design approach

D.

Decision-making approach

Which of the following is a Boundary document?

A.

Programme preparation plan

B.

Risk register

C.

Stakeholder profiles

D.

Benefits Map