Which of following is a key attribute for a SRO?

A.

Good knowledge of project management approaches

B.

Should represent a relevant business area

C.

Have ongoing operational responsibilities

D.

Have access to and credibility with key stakeholders

Which of following is input for 'managing the tranches'?

A.

Programme preparation plan

B.

Programme Brief

C.

Approval to proceed

D.

Assurance review reports

Who reviews Business Case?

A.

Sponsoring Group

B.

SRO

C.

Programme Manager

D.

BCM

The programme is in the ‘evaluate new information' process at the end of Tranche 2. A new supplier has been identified that may be able to develop the next generation smart meters. This would be an alternative to developing them internally as part of the Research and Development Project and it could be faster and cheaper.

Which role should be responsible for evaluating this new information?

A.

Senior responsible owner

B.

Programme manager

C.

Business change manager

D.

Programme office lead

The CFO has been appointed as the SRO for the Smart Meter Programme.

Is this appointment an appropriate application of the ‘organization’ theme, and why?

A.

Yes, because the CFO is able to monitor whether the increase in customers and reduction in costs is achieved

B.

Yes, because the CFO can direct the programme, providing new insights as they are new to UU

C.

No, because the CFO has no previous experience or working knowledge of the utility industry operations

D.

No, because the CEO, who has industry knowledge, is better qualified to develop the programme vision

Which of below sentences describes Project Brief?

A.

List of all projects that will be part of programme

B.

Control framework for programme

C.

Control framework for projects

D.

Describes purpose, cost, time, performance requirements and constraints of a project

UU has partnered with a supplier who has expertise in training and change management. The supplier will provide a virtual change office function, helping staff in the business prepare for the significant transformation ahead and ensuring that the benefits will be realized. However, these change management services are very costly.

Is this an appropriate application of the ‘justification’ theme, and why?

A.

Yes, because the costs are justified by the support provided to staff members and the benefits to be delivered

B.

Yes, because the money saved by having a single call centre will provide contingency to pay for the change office

C.

No, because the BCM should use a network of internal change agents to support the changes in order to save money

D.

No, because defining the need for additional supporting offices is part of tailoring the ’organization’ theme

The project team working on the Training Project in Tranche 3 needs to understand the new processes and knowledge required by staff members to develop a coherent set of training materials. The project team also needs to know the skills and qualifications for each role, and any new processes. The project manager is concerned that some of the documentation provided is outdated and does not now reflect the current processes being developed.

Which aspect of information management, if applied correctly, is MOST LIKELY to address these concerns?

A.

Access control

B.

Integrity

C.

Storage

D.

Version control

The customer web-based portal being delivered by Web ’n’ Go in Tranche 2 will allow customers to make enquiries and request services online. The BCM held a workshop with call centre managers to identify what the most common problems and queries are that they typically receive. This information will help Web ‘n’ Go develop a solution that meets customer needs.

Is this use of information an appropriate application of the 'knowledge’ theme, and why?

A.

Yes, because the call centre managers’ understanding of customer needs should help Web 'n’ Go develop more effective customer processes

B.

Yes, because the BCM should encourage the call centre managers to share their experiences with each other to improve existing service to customers

C.

No, because the programme office lead should ensure that Web n' Go has the information and knowledge it needs

D.

No, because sensitive customer information should not be shared with Web ‘n' Go which is an external company