Which of the following describes how a project is related to a program?
Which of the following Agile ceremonies is used to determine the backlog items that will be worked on the next weeks?
Using Scrum, which of the following are discussed in a daily standup meeting?
Which of the following shows projected project expenditures?
Which of the following is a key aspect of the Agile project management methodology?
Ð new stakeholder has been added to a project with a BAG of $850,000. The stakeholder has raised five change requests to the CCB; two of them have been approved, and three are awaiting initial review. Considering the project has a CPI of 0.89 and an SPI of 1.14, and the approved ones will be implemented, which of the following should the project manager do LAST?
A project manager is creating the monthly report for top management. The project manager has collected the information below:
AC = 100
PV = 80
EV = 120
Based on this information, the CPI reflects which of the following about the project?
Which of the following risk strategies is represented by the purchase of insurance?
A new project charter is being drafted.
Which of the following would be the BEST source for the high-level project requirements?
A project manager is releasing resources and archiving documents. Which of the following phases is the project MOST likely in?
During a project, a key stakeholder asks a project team member to add a requirement. The team member adds the requirement without informing the project manager. Which of the following is described in this scenario?
A company hires a number of interns and assigns them key roles on a project. Which of the following should the project manager MOST likely anticipate?
Which of the following are examples of organizational change? (Choose two.)
A project manager needs to identify the resources assigned to a particular task.
In which of the following documents can this information be found?
The key stakeholders have reported the project pace as being slow. The project sponsor would like to cancel the project if it cannot be completed before the end of the year. The project is scheduled to be completed three months after the requested date.
To alter the pace of the project, which of the following should the project manager do FIRST?