CompTIA PK0-004 - CompTIA Project +

Page: 12 / 16
Total 796 questions

Which of the following describes how a project is related to a program?

A.

A program is a combination of multiple projects.

B.

A program contains an element of the project.

C.

A program is a part of a project.

D.

A program uses half of the project’s budget.

Which of the following Agile ceremonies is used to determine the backlog items that will be worked on the next weeks?

A.

SCRUM retrospective meeting

B.

Sprint planning meeting

C.

Daily standup meeting

D.

Review meeting

Using Scrum, which of the following are discussed in a daily standup meeting?

A.

What was done yesterday, what is planned for today, and what roadblocks need to be removed

B.

What was done yesterday, what is planned for the week, and what issues were resolved

C.

What was done yesterday, what is planned for today, and what deliverables were completed

D.

What was done yesterday, what is planned for this week, and what items from the backlog are priority

Which of the following shows projected project expenditures?

A.

Work breakdown structure

B.

Cash flow schedule

C.

Cash burn rate

D.

Budget milestone

Which of the following is a key aspect of the Agile project management methodology?

A.

Test-driven

B.

Daily standup meetings

C.

Short project durations

D.

Defined list of requirements

А new stakeholder has been added to a project with a BAG of $850,000. The stakeholder has raised five change requests to the CCB; two of them have been approved, and three are awaiting initial review. Considering the project has a CPI of 0.89 and an SPI of 1.14, and the approved ones will be implemented, which of the following should the project manager do LAST?

A.

Identify and document the risk.

B.

Evaluate the impact and justification.

C.

Implement the change.

D.

Update the documents and plans.

A project manager is creating the monthly report for top management. The project manager has collected the information below:

AC = 100

PV = 80

EV = 120

Based on this information, the CPI reflects which of the following about the project?

A.

It is under budget.

B.

It is over budget.

C.

It is ahead of schedule.

D.

It is behind schedule.

Which of the following risk strategies is represented by the purchase of insurance?

A.

Mitigate

B.

Accept

C.

Transfer

D.

Avoid

A new project charter is being drafted.

Which of the following would be the BEST source for the high-level project requirements?

A.

Sponsor

B.

Project manager

C.

Project management office

D.

Project team

A project manager is releasing resources and archiving documents. Which of the following phases is the project MOST likely in?

A.

Initiation

B.

Planning

C.

Monitor and control

D.

Closing

During a project, a key stakeholder asks a project team member to add a requirement. The team member adds the requirement without informing the project manager. Which of the following is described in this scenario?

A.

Change request

B.

Risk mitigation

C.

Change control

D.

Scope creep

A company hires a number of interns and assigns them key roles on a project. Which of the following should the project manager MOST likely anticipate?

A.

Reduced quality

B.

Reduced scope

C.

Reduced risk

D.

Reduced timeline

Which of the following are examples of organizational change? (Choose two.)

A.

Relocation

B.

Scope

C.

Business process

D.

Schedule

E.

Risk event

A project manager needs to identify the resources assigned to a particular task.

In which of the following documents can this information be found?

A.

Project schedule

B.

Cost plan

C.

Scope statement

D.

Impact assessment

The key stakeholders have reported the project pace as being slow. The project sponsor would like to cancel the project if it cannot be completed before the end of the year. The project is scheduled to be completed three months after the requested date.

To alter the pace of the project, which of the following should the project manager do FIRST?

A.

Give approval for the change requested by the project sponsor.

B.

Deny the request from the project sponsor.

C.

Document the change request from the project sponsor.

D.

Ask the project sponsor to change the request.