CompTIA PK0-004 - CompTIA Project +
A project manager was directed to complete a project sooner than previously planned. Which of the following is the MOST cost-effective step to take to ensure the project’s success?
A project manager wants to introduce the practice of a WBS to the PMO, but the other managers believe this will create extra work. Which of the following would BEST communicate the need for a WBS to the other managers? (Select TWO).
A project manager is justifying a required change with the associated impact on the project.
Which of the following is the NEXT step?
A risk with minor impact has been realized. There is no change to the triple constraint. The PM should notify the:
A project manager has been asked to prepare and present a review of the execution phase. Which of the following is the BEST audience for this review?
Which of the following is an example of a project?
During a project assessment, a project manager determines the initial project cost estimates were incorrect, and there is not enough budget left, including reserves, to complete the project.
Which of the following actions should the project manager take?
In which of the following categories does a business process change fit?
A customer asks a project manager if a small change can be made during the delivery phase. The project manager does not agree to the change.
Which of the following is the MOST likely reason?
A project manager is attempting to establish the proper sequencing and duration of project activities.
Which of the following would be the MOST beneficial?
Which of the following events would MOST likely trigger communications to the largest audience for a given organization?
Which of the following is the primary purpose of an MOA or an MOU?
The PM is preparing for the planning phase kickoff meeting. It is imperative for the team to focus during the meeting on the expected outcomes.
Which of the following best describes what the PM should work on FIRST?
Which of the following project documents should be used to record the occurrence of an unplanned event?
Which of the following are characteristics of a project? (Choose two.)