Which of the following inherently affects quality standards?

A.

SLA

B.

MOA

C.

MOU

D.

WBS

A project manager is successfully adhering to an eight-week project schedule through week three. A change in the marketplace will require the project manager to deliver the product one week early.

Given the project schedule above, which of the following aspects are missing for the project manager to plan and execute an accelerated schedule? (Choose two).

A.

Cost

B.

Predecessors

C.

Lag

D.

Durations

E.

Resource loading

F.

Subtasks

G.

Float

Which of the following documents does a vendor rely on MOST before committing funding and resources to a project?

A.

SOW

B.

PO

C.

SLA

D.

MOU

A project coordinator logs potential events that can affect project constraints, and then records the results of brainstorming of potential strategies.

Which of the following documents should the project coordinator use?

A.

Risk register

B.

Issue log

C.

Communication plan

D.

Status report

The project manager is reviewing the earned value of work completed compared to the planned value and is representing it in a dollar figure.

This type of analysis is an example of which of the following?

A.

Cost performance index

B.

Risk mitigation

C.

Schedule variance

D.

Cost variance

The project manager for a TV tower construction project receives notification that a strong storm is expected the following week.

Which of the following should the project manager do NEXT?

A.

Evaluate the risk, inform major stakeholders about the problem, and issue a change request immediately.

B.

Evaluate the risk, fill in the issue log, and communicate it according to the communication plan.

C.

Evaluate the risk, develop a mitigation plan, and communicate it according to the communication plan.

D.

Evaluate the risk, reschedule all outdoor tasks for a later time, and inform major stakeholders.

A vendor has accepted a proposed project from a customer.

Which of the following is MOST likely to be the first document created by the project manager?

A.

Project charter

B.

Project management plan

C.

Project statement of work

D.

Project schedule

The executive sponsor asks a project manager to summarize the following for a project:

1. Final capital expenditures.

2. Anticipated cost of new employee resources to support the solution.

3. Maintenance estimates.

Which of the following information should the project manager provide?

A.

Cost baseline

B.

Burn rate

C.

Cost variance report

D.

Total project cost

A project is taking more effort than anticipated. Which of the following constraints will MOST likely be affected?

A.

Scope

B.

Time

C.

Quality

D.

Cost

Which of the following is a schedule that illustrates the duration of an activity?

A.

Process diagram

B.

Ishikawa diagram

C.

Gantt chart

D.

Pareto chart

An authorized change to a construction project was implemented. During the modification, the team identified a defect in which the change caused the building power output to be outside the KPPs.

Which of the following actions should the project manager take?

A.

Submit a new change request.

B.

Initiate the regression plan.

C.

Add remediation to the schedule.

D.

Accept the new power output.

A new project sponsor has joined the project team, and the constraints on the project have been reprioritized. The project cost was previously the most important factor, but the new sponsor has indicated that meeting a new, shorter deadline is the priority.

Which of the following effects is this MOST likely to have on the project?

A.

The deliverables and quality will remain the same, but the cost will increase.

B.

The deliverables and quality will remain the same, but the cost will decrease.

C.

The deliverables and cost will remain the same, but the quality will increase.

D.

The cost and quality will remain the same, but the deliverables will increase.

A team member was replaced on a project by a new team member of equal capability. Which of the following should the project manager do FIRST?

A.

Resource loading

B.

Resource leveling

C.

Prioritizing tasks

D.

Allocating resources

A project has fallen behind schedule. Upon investigation, the project manager determines that team members have implemented requirements relayed via impromptu hallway meetings with the client.

Which of the following should the project manager do to resolve this issue?

A.

Update the scope management plan.

B.

Modify the project baselines.

C.

Implement change control management.

D.

Inform the stakeholders of the issue.

A project manager provides status reports to a customer on a biweekly basis, but the customer is very busy and only has a few minutes to review the project.

Which of the following are critical for the project manager to provide?

A.

Cost, schedule, organizational chart, and risks/issues

B.

Risks/issues, cost, RACI chart, and action items

C.

Schedule, cost, risks/issues, and milestones

D.

Action items, organizational chart, schedule, and NDA