A project sponsor is reviewing the project dashboard and does not understand what a CPI of 0.87 and an SPI of 1.02 indicate. Which of the following describes the project status?

A.

The project is over budget and behind schedule.

B.

The project is under budget and ahead of schedule.

C.

The project is over budget and ahead of schedule.

D.

The project is under budget and behind schedule.

A stakeholder does not want to receive tollgate approval emails, and asks the project manager to identify a different communication method. Which of the following would be BEST for the project manager to suggest?

A.

Task management software

B.

Social media

C.

Videoconferencing

D.

Face-to-face meetings

A company is under investigation for monopolization practices. Which of the following might result from this situation?

A.

Split

B.

Acquisition

C.

Outsourcing

D.

Offshoring

A project team member informs the project manager that a task on the critical path will not be completed on time.

Which of the following documents will MOST likely be updated? (Choose two.)

A.

Project scope

B.

Project charter

C.

Project schedule

D.

Risk register

E.

Incident response plan

F.

Communication plan

The PMO has removed a vendor from a project for inflating costs and failing to complete deliverables in a timely manner. The PMO received complaints that vendor resources missed appointments and provided poor

service. The vendor has initiated a lawsuit against the PMO, asserting the vendor was operating within the terms of the current agreement.

Which of the following documents should be reviewed by the PMO to support vendor removal? (Choose two.)

A.

Communication plan

B.

Project charter

C.

Service level agreement

D.

Project management plan

E.

Action items

F.

Statement of work

The responsibility of estimating how long a task will take belongs to the:

A.

project scheduler

B.

project team

C.

project manager

D.

project coordinator

A project portfolio will MOST likely align to:

A.

consumer demand.

B.

corporate strategy.

C.

lessons learned.

D.

PMO guidelines.

During the quality review of a change request, a required feature is discovered to be missing from the build. The documentation the developer received does not mention the feature; however, it is mentioned in the quality assurance manager's copy. Which of the following would prevent this issue from occurring in the future?

A.

Document the situation in the issue log.

B.

Verify the change is in the project schedule.

C.

Institute a version control process.

D.

Create a new change request with the additional requirement.

A project, which is nearing completion, is ahead of schedule and under budget. However, to improve quality to acceptable levels, the project will require additional time.

Which of the following BEST describes this scenario?

A.

Score creep

B.

Interactions between constraints

C.

Constraint reprioritization

D.

Change request

Given the following:

Which of the following is the duration of the critical path?

A.

35 days

B.

37 days

C.

38 days

D.

72 days

E.

73 days

Which of the following is performed during the monitoring and controlling phase?

A.

Quality control and training plan development

B.

Creation of schedule and fund deliverables

C.

Development of transition plan and finalizing contracts

D.

Quality assurance and governance oversight

A project manager has just received an extra resource from a functional manager. Which of the following activities is the BEST to consider for assignment to the resource?

A.

Activity A should be assigned because it is within the resource’s skillset, has already been started with three other resources, and has four days of slack.

B.

Activity B should be assigned because it is not within the resource’s skillset; however, it gives the resource an opportunity to learn a new skill, has not started, and has one day of slack.

C.

Activity C should be assigned because it is a task that any resource can do; however, it is undesirable, needs to be done, has not started, and has three days of slack.

D.

Activity D should be assigned because it is a new task, the skillset determination has not been assessed for the task, it is supposed to start tomorrow, and it has zero slack.

A construction company is building a plant in a territory that is prone to earthquakes. To address the risk and consequences of potential earthquakes during and after plant construction, the company purchases additional

insurance. Which of the following risk responses has occurred?

A.

Avoiding

B.

Mitigating

C.

Accepting

D.

Transferring

A project manager noted there were many possible features that could be incorporated into a project, and the customers wavered about whether to include particular features. Which of the following is the BEST approach to ensure appropriate delivery of the project?

A.

In one section of the project charter, specify which features are included in the project, in another section, specify which features are not included in the project.

B.

The scope statement should enumerate which features are included in the project and which features are not included in the project.

C.

At the beginning and end of every meeting, the project manager should consistently remind the project team which features are included in the project and which features are not included in the project.

D.

The project requirements document lists all the features that are included in the project, and the project manager diligently ensures that features not included in the project are not included in the MOU with the customer.

Which of the following are characteristics of qualitative risk assessments as opposed to quantitative? (Choose two.)

A.

Qualitative assessments are more difficult.

B.

Qualitative assessments are faster.

C.

Qualitative assessments require fewer resources.

D.

Qualitative assessments provide more accurate results.

E.

Qualitative assessments better identify opportunities.