A project sponsor is reviewing the project dashboard and does not understand what a CPI of 0.87 and an SPI of 1.02 indicate. Which of the following describes the project status?
A stakeholder does not want to receive tollgate approval emails, and asks the project manager to identify a different communication method. Which of the following would be BEST for the project manager to suggest?
A company is under investigation for monopolization practices. Which of the following might result from this situation?
A project team member informs the project manager that a task on the critical path will not be completed on time.
Which of the following documents will MOST likely be updated? (Choose two.)
The PMO has removed a vendor from a project for inflating costs and failing to complete deliverables in a timely manner. The PMO received complaints that vendor resources missed appointments and provided poor
service. The vendor has initiated a lawsuit against the PMO, asserting the vendor was operating within the terms of the current agreement.
Which of the following documents should be reviewed by the PMO to support vendor removal? (Choose two.)
The responsibility of estimating how long a task will take belongs to the:
A project portfolio will MOST likely align to:
During the quality review of a change request, a required feature is discovered to be missing from the build. The documentation the developer received does not mention the feature; however, it is mentioned in the quality assurance manager's copy. Which of the following would prevent this issue from occurring in the future?
A project, which is nearing completion, is ahead of schedule and under budget. However, to improve quality to acceptable levels, the project will require additional time.
Which of the following BEST describes this scenario?
Given the following:
Which of the following is the duration of the critical path?
Which of the following is performed during the monitoring and controlling phase?
A project manager has just received an extra resource from a functional manager. Which of the following activities is the BEST to consider for assignment to the resource?
A construction company is building a plant in a territory that is prone to earthquakes. To address the risk and consequences of potential earthquakes during and after plant construction, the company purchases additional
insurance. Which of the following risk responses has occurred?
A project manager noted there were many possible features that could be incorporated into a project, and the customers wavered about whether to include particular features. Which of the following is the BEST approach to ensure appropriate delivery of the project?
Which of the following are characteristics of qualitative risk assessments as opposed to quantitative? (Choose two.)