A Scrum team is completing a sprint; however, some tasks will need to carry over to the next sprint.
Which of the following should the Scrum master do to improve the team's velocity in the next sprint?
A project task has been completed ahead of schedule. Which of the following is the MOST appropriate next step?
A concrete pad needs to be laid for a new house and requires three days to cure. The project manager notes that rain may be in the immediate forecast.
Which of the following would BEST avoid the risk of rain damage?
A sponsor requests that the project team shorten the completion of a project by two months to give the sales team more leverage in renegotiating the contract with the client. The budgeted time is 500 hours, and the projected earned value is $30,000.
Which of the following represents the cost variance for both project completions?
When closing a project, which of the following must be completed to allow team members to return to their designated departments?
A team member has completed a project task. Which of the following is the FASTEST method to communicate the task completion?
During the testing phase, a team member has informed the project manager that the test environment was set with inadequate client information, putting the project in jeopardy. Which of the following should the project manager do NEXT?
A project encountered a problem and reached a milestone. In which of the following documents will the stakeholders MOST likely find information on these events?
Which of the following activity sequencing techniques uses nodes to symbolize the dependencies of each activity?
A project sponsor wants to know when the plan changed to ship the deliverables to a new location. To determine the answer, the project manager should FIRST review the:
Three IT companies have agreed to summarize their efforts as a common organization to generate new businesses in the IT cloud computing industry. Which of the following is the type of organizational change described?
While preparing to plan a project, the project manager meets with the key stakeholders to determine the
flexibility between the project constraints. Which of the following techniques should the project manager
consider to reduce personal bias and increase buy-in?
A project manager is archiving of project documents.
Which of the following phases does this describe?
Due to a lack of adherence to the risk response plan, there are numerous safety concerns within the scope of a building project.
Which of the following MOST likely explains this issue?
A project sponsor, project manager, and project facilitator are drafting a project charter. The final contents of this documentation will be presented to the project steering committee for review and approval. The following sections are currently documented:
Project description
Draft project timeline and schedule
Rough milestones
Draft project budget
Draft resources required
High-level risk review
Which of the following sections should be included in this document?