Weekend Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmas50

CompTIA PK0-004 - CompTIA Project +

Page: 3 / 16
Total 796 questions

A Scrum team is completing a sprint; however, some tasks will need to carry over to the next sprint.

Which of the following should the Scrum master do to improve the team's velocity in the next sprint?

A.

Take a more hands-on leadership approach.

B.

Add the unfinished work to the backlog.

C.

Schedule a sprint retrospective.

D.

Hold additional daily stand-up meetings.

A project task has been completed ahead of schedule. Which of the following is the MOST appropriate next step?

A.

Provide the next task to the newly freed resource.

B.

Communicate the success to the team.

C.

Notify the project sponsor of the new completion date.

D.

Update the schedule and add lag to the next task.

A concrete pad needs to be laid for a new house and requires three days to cure. The project manager notes that rain may be in the immediate forecast.

Which of the following would BEST avoid the risk of rain damage?

A.

Place a tarp over the fresh concrete to protect it.

B.

Refinish the concrete if it rains during that time.

C.

Pour the concrete as quickly as possible to allow the most drying time.

D.

Wait to pour the concrete until rain is not in the forecast.

A sponsor requests that the project team shorten the completion of a project by two months to give the sales team more leverage in renegotiating the contract with the client. The budgeted time is 500 hours, and the projected earned value is $30,000.

Which of the following represents the cost variance for both project completions?

A.

-$4.8K and -$7K

B.

-$4.9K and $7K

C.

$4.8K and -$7K

D.

$4.8K and $7K

When closing a project, which of the following must be completed to allow team members to return to their designated departments?

A.

Perform retrospective

B.

Release resources

C.

Obtain sign-off from the sponsor

D.

Close contracts

A team member has completed a project task. Which of the following is the FASTEST method to communicate the task completion?

A.

Social media

B.

Email

C.

Instant messaging

D.

Team meeting

During the testing phase, a team member has informed the project manager that the test environment was set with inadequate client information, putting the project in jeopardy. Which of the following should the project manager do NEXT?

A.

Ask the team member to move to a different test environment.

B.

Ask the team member to refrain from testing the scenarios.

C.

Revisit the risk management plan and provide corrective actions.

D.

Revisit the contingency plan and provide corrective actions.

A project encountered a problem and reached a milestone. In which of the following documents will the stakeholders MOST likely find information on these events?

A.

Issues log

B.

Change log

C.

Status report

D.

Meeting minutes

Which of the following activity sequencing techniques uses nodes to symbolize the dependencies of each activity?

A.

Critical Path Method

B.

Critical Chain Method

C.

Arrow Diagramming Method

D.

Gantt Chart Method

A project sponsor wants to know when the plan changed to ship the deliverables to a new location. To determine the answer, the project manager should FIRST review the:

A.

project management plan

B.

scope statements and issue log

C.

project dashboard and status report

D.

action items and meeting minutes

Three IT companies have agreed to summarize their efforts as a common organization to generate new businesses in the IT cloud computing industry. Which of the following is the type of organizational change described?

A.

Expansion

B.

Rightsizing

C.

Merger

D.

Onboarding

While preparing to plan a project, the project manager meets with the key stakeholders to determine the

flexibility between the project constraints. Which of the following techniques should the project manager

consider to reduce personal bias and increase buy-in?

A.

Send the stakeholders a survey about the project constraints to complete anonymously

B.

Watch and determine which constraint is most important

C.

Compare the constraints two at a time and have the stakeholders vote on importance

D.

Look at historical information regarding the flexibility preferences of key stakeholders

A project manager is archiving of project documents.

Which of the following phases does this describe?

A.

Initiation

B.

Planning

C.

Execution

D.

Closing

Due to a lack of adherence to the risk response plan, there are numerous safety concerns within the scope of a building project.

Which of the following MOST likely explains this issue?

A.

Risks were not identified.

B.

Risks were not mitigated.

C.

Risks were not exploited.

D.

Risks were not communicated.

A project sponsor, project manager, and project facilitator are drafting a project charter. The final contents of this documentation will be presented to the project steering committee for review and approval. The following sections are currently documented:

    Project description

    Draft project timeline and schedule

    Rough milestones

    Draft project budget

    Draft resources required

    High-level risk review

Which of the following sections should be included in this document?

A.

Business information

B.

Full risk assessment results

C.

Draft work breakdown structure

D.

Full resource requirements