A PM receives notification that an issue will impact a deliverable on the critical path. The issue is logged with a unique ID and assigned to a team member; however, the team member has not addressed it after a week. Which of the following would be the BEST approach to resolving the issue?

A.

Assign a different team member to resolve the issue before the next status meeting.

B.

Review the issue with the assigned team member to determine a due date.

C.

Set a due date to resolve the issue and inform the assigned team member.

D.

Report the team member to a functional manager for disciplinary action.

A project manager procures additional resources from a local company. Which of the following-describes this event?

A.

Reorganizing

B.

Onboarding

C.

Offshoring

D.

Outsourcing

A resource is assigned to two projects with two scheduled tasks that complete at the same time.

This is known as:

A.

shared resource contention

B.

intraproject resource contention

C.

interproject resource contention

D.

dedicated resource contention

The Chief Executive Officer (CEO) has announced that the hardware division will be sold to another company.

The sale of this division is an example of which of the following?

A.

Outsourcing

B.

Relocation

C.

Business process change

D.

Business merger

Which of the following techniques modifies the schedule based upon resource constraints?

A.

Critical Chain Method

B.

Critical Path Method

C.

Arrow Diagramming Method

D.

Precedence Diagramming Method

Which of the following resources outlines consequences of non-performance?

A.

Project sponsor

B.

Project team

C.

Customer

D.

Project management office

The project's network map has a loop with multiple project outcomes.

This is the result of which of the following scheduling tools?

A.

Establishing project schedule baselines

B.

Critical Path Analysis

C.

Critical Chain Method

D.

Graphical evaluation and review technique

A meeting has taken place with quality assurance tram members and the project manager.

Which of the following events would MOST likely have triggered the meeting?

A.

Audit

B.

Risk register update

C.

Task completion

D.

Resource change

Which of the following project phases occurs when requirements are detailed?

A.

Initiation

B.

Monitor and control

C.

Planning

D.

Closing

Communication on a project is flowing well. Team members are motivated, and they are allowed to make decisions about their work.

Which of the following management styles is the project manager MOST likely using?

A.

Exploitive

B.

Retrospective

C.

Participative

D.

Authoritative

One of the tasks on a project’s critical path is progressing too slowly. The team member who is responsible for completing the task is assigned to multiple projects with aggressive deadlines.

Which of the following roles has the responsibility of resolving the issue?

A.

CCB

B.

PMO

C.

Project sponsor

D.

Project scheduler

There is a project in which the team can only meet once every three months. When the team does meet, no

one can remember what was discussed and decided upon last time; thus, progress is being delayed. Which of

the following project management tools would help?

A.

Issue log

B.

Project charter

C.

Dashboard

D.

Meeting minutes

A customer has stated that meeting the project schedule and milestones takes priority and is, therefore, willing to spend additional funds to sustain operations. The project team must ensure completion of the:

A.

business continuity plan.

B.

incident response plan.

C.

disaster recovery plan.

D.

risk management plan.

E.

quality management plan.

A project manager has been assigned a complex project and does not know all the activities required to complete it.

Which of the following if the BEST approach to determine the work packages for the WBS?

A.

Brainstorming

B.

Analogous

C.

Bottom-up

D.

Forward pass

Which of the following should a project manager consider as part of a make or buy analysis?

A.

Organization type

B.

KPIs

C.

Project charter

D.

Trade secrets