A project team is defining detailed risks. Which of the following project phases is taking place?

A.

Initiation

B.

Monitor and control

C.

Execution

D.

Planning

Which of the following provides tools and standard documentation for the project team?

A.

Project management office

B.

Project manager

C.

Project coordinator

D.

Project steering committee

In a Scrum retrospective, which of the following categories are used to classify the feedback from the team?

A.

Direct and indirect

B.

Pros and cons

C.

Pluses and minuses

D.

Likes and dislikes

Despite receiving regular updates, a sponsor learns a project recently slipped.

Which of the following documents can the sponsor review to determine the project’s performance? (Select two.)

A.

Status report

B.

Communication plan

C.

Issue log

D.

Project schedule

E.

Action items list

F.

Risk register

Which of the following activity sequencing techniques uses nodes to symbolize activities and arrows to show how their dependencies are connected?

A.

Critical Path Method

B.

Arrow Diagramming Method

C.

Critical Chain Method

D.

Precedence Diagramming Method

A project team completed a brainstorming activity to determine potential issues with a project. Which of the following activities should the project team do NEXT?

A.

Risk identification

B.

Risk quantification

C.

Risk planning

D.

Risk response

Gas prices were included in the cost baseline for a transportation and hauling project. Although the estimates

used to create the baseline were based on historical data, which of the following should the project manager

consider as a root cause for potential issues with cost overruns?

A.

Requirements

B.

Lessons learned

C.

Budget

D.

Environment

Which of the following documents should the project manager complete if requirements have been defined, but neither a vendor nor a platform has been identified?

A.

RFP

B.

RFQ

C.

RFI

D.

SOW

An active project has a CPI of 0.92. Which of the following can be determined?

A.

The project is currently over budget.

B.

The project has a budget surplus.

C.

The project is ahead of schedule.

D.

The project is behind schedule.

Severe weather has impacted a construction project, delaying scheduled work for five days. Which of the

following project changes is the project manager most likely to consider FIRST?

A.

Requirements change

B.

Funding change

C.

Timeline change

D.

Risk event

A project manager at a projectized organization is finishing the objective goals for the appraisal process. Performance goals have been identified for colocated individuals working on the team. Which of the following is the appropriate communication method for relaying the goals to the team members?

A.

Email

B.

Distribution of printed media

C.

Face-to-face

D.

Video conferencing

A project is coming to the end of a phase. The PMO requires that the quality team review the work and budget before moving on to the next phase of the project. The project manager must schedule the review of the phase and have the stakeholders present.

This review is referred to as:

A.

change management

B.

A milestone

C.

a tollgate

D.

an incident response

A vendor advises the project manager that a key component of the project is no longer available and recommends a higher-cost replacement. To have this change approved, the project manager submits a change request that contains which of the following?

A.

Description, cost difference of the replacement, and WBS

B.

Description, justification, and cost

C.

Cost difference of the replacement, justification, and communications plan

D.

Description, quality impact, and cost

A project team has failed to deliver on changes the project manager outlined on a call two weeks ago. The project team members indicate they did not remember the contents on the call. Which of the following should the project manager do FIRST to improve the level of awareness of changes to the project schedule?

A.

Define the communications plan.

B.

Record the missed tasks on the issue log.

C.

Provide meeting minutes after each call.

D.

Complete a fishbone diagram.

A project manager needs status on the project timeline.

Which of the following team members should provide an update?

A.

Product owner

B.

Business analyst

C.

Scheduler

D.

Sponsor