CompTIA PK0-004 - CompTIA Project +
Which of the following documents will provide the MOST detailed information regarding the work a vendor will
perform during a project?
A project team has completed a major deliverable earlier than planned and wants to deliver it for testing. The team lead sends an email providing notice of task completion to the project manager.
Which of the following describes how the project manager can increase the likelihood that the deliverable moves to testing?
A vendor was removed from a company due to non-performance but continues to submit invoices for work that was not completed. Which of the following should the project manager do to stop the vendor from sending invoices?
A project manager is overseeing a multinational project, and team leaders from numerous countries indicate the team members have low morale.
Which of the following is the MOST likely reason the project manager would be unaware of the team member’s decreased morale?
Upper management asks a project sponsor to provide several ad hoc reports as a brief overview of the project’s current status.
Which of the following types of reports should the project sponsor use to quickly summarize the status report data?
When an action is taken on a risk, which of the following is being done and which document needs to be updated?
Which of the following conflict resolution techniques relies on establishing areas of agreement rather than disagreement?
Given the information in the table below, which of the following is the total project cost?
Based on the table below:
Which of the following is the critical path if Task B has extended to ten days?
Which of the following should be included in an effective SOW?
A PM is asked to keep the Chief Information Officer (CIO) informed of a project’s health at a high level on a
daily basis. Which of the following is the BEST way for the PM to provide this information?
A project manager has received numerous complaints from staff concerning poor service provided by a vendor.
Which of the following steps should the project manager take FIRST to correct the problem?
A manufacturer is developing a product that will start in one week. The product has a delivery deadline of 90 days.
Which of the following characteristics classifies this as a project?
The PMO is confused by an entry in the risk register and would like the project manager to provide clarification regarding strategy. Based on the following entry:
Which of the following should be modified to BEST eliminate confusion?
A project can be defined as: