During the storming stage of a project team’s development, it is common to experience confusion about tasks and responsibilities because:
A key stakeholder asked several members of the project team to make project changes without submitting
them for approval. Because the stakeholder is related to the Chief Executive Officer (CEO), the team members
are reluctant to deny these requests. Which of the following should the project manager do FIRST to control
this situation?
A task on the critical path will not be completed on time. The project manager is reviewing both the schedule and the risk register to create a corrective action plan. The project completion date and quality of the deliverable cannot change. Which of the following activities should the project manager perform NEXT?
At a project kickoff meeting, several team members acted unprofessionally. The project manager would like to set expectations for team interaction. Which of the following would BEST accomplish this?
Which of the following documents serves the primary purpose of requesting details about a vendor’s capabilities?
A PM notes a feature that was delivered does not appear in the latest requirement document. The PM
immediately submits a change request for remediation. Which of the following actions has the PM omitted?
A project manager is not required to participate in performance appraisal meetings with team members. The project manager is working within which of the following organizational structures?
Which of the following features describe a projectized organization? (Select two.)
A fire occurred in the production facility over the weekend, affecting the machinery being used to produce a deliverable. No injuries were reported.
Which of the following is MOST appropriate for the project manager to do NEXT?
A new project manager is working in an environment where resources report to another supervisor. The
project manager is having difficulty with a particular member and wants to escalate the issue. Which of the
following documents should the project manager consult?
A project has activities on the critical path that must be completed before other activities can start:
Task A is dependent on Task C before Task D can be completed.
Task A requires Task B to start.
Task B takes twice as long to complete as Task C.
Which of the following is the appropriate ordering of the critical path?
Which of the following defines the minimum level of engagement of a stakeholder?
A project team is not delivering their tasks in a timely manner. Additionally, tasks are being reworked because requirements continue to be identified as work packages are being delivered.
Which of the following are NOST likely missing from the project? (Select two.)
Which of the following documents is typically signed by the vendor and includes a reference for how customers’ internal information will be protected?
The Chief Executive Officer (CEO) has changed the direction of a business and no longer needs one of the
divisions. A deal is reached to sell the division to a company in another state. Which of the following BEST
describes this type of organizational change?