CompTIA PK0-004 - CompTIA Project +
A project manager is overseeing the construction of a new building. There are likely existing underground water, gas, and electrical lines. Which of the following is an example of mitigation?
At the midway point of execution, the project plan calls for a full review of the risk register. To which of the following is the appropriate party to communicate the official results of this review?
A project manager needs a systems administrator as a resource on a project. The project manager approaches the operations manager to obtain the resource. In which of the following organizational structures is the project manager MOST likely operating?
Input into a project’s requirements is needed for clarification. With which of the following roles would the project manager MOST likely consult?
A project manager notices several of the action items discussed during a team-building exercise have been ignored by the project team. Although the team-building exercise was well attended and feedback was well received, nothing was accomplished.
To make the meetings more productive, which of the following steps should the project manager take? (Choose two.)
Detailed policy guidance is BEST provided by:
A project manager is informed that the project sponsor was terminated from the project effective immediately. To ensure business continuity, the project manager has been asked to assume additional tasks to complete
the project on time. Many of these tasks were performed by the former project sponsor.
Which of the following types of change does this illustrate?
A project sponsor wants to replace the current PM with a more experienced PM. However, removing the current PM might have a negative impact on the team's morale and motivation in a critical stage of the project. After talking to the main stakeholder, the sponsor decides to provide the PM with training according to the need instead of removing the PM. Which of the following risk management strategies was used in this scenario?
Some resources are waiting to be assigned to a new project. These resources are called:
A vendor who is scheduled to arrive in two days encounters a delay and needs to reschedule the visit. The project manager needs a timely response from the project sponsor regarding the delay; however, the sponsor is in an all-day meeting and is not responding to email.
Which of the following is the BEST method to get the sponsor’s attention?
Which of the following metrics are used to determine a project's EAC?
A project team is executing a transition plan for a project. During which of the following project phases does this normally occur?
Many QUESTION NO:s have arisen regarding a newly identified project. Project team members are anxious to know who will be part of the team and what the project will deliver. Which of the following would be the BEST way to provide this information?
A politically sensitive project is being proposed. The sponsor decides to outsource the work despite having a highly capable team.
Which of the following BEST describes the risk mitigation strategy being used?
The problem statement of a project helps to identify: