The initial development of a Project Scope Management plan uses which technique?

A.

Alternatives identification

B.

Scope decomposition

C.

Expert judgment

D.

Product analysis

What is a hierarchically organized depiction of the identified project risks arranged by risk category?

A.

Risk register

B.

Risk breakdown structure (RBS)

C.

Risk management plan

D.

Risk category

The business needs, assumptions, and constraints and the understanding of the customers needs and high-level requirements are documented in the:

A.

Project management plan.

B.

Project charter.

C.

Work breakdown structure.

D.

Stakeholder register.

Which of the following correctly explains the term "progressive elaboration'?

A.

Changing project specifications continuously

B.

Elaborate tracking of the project progress

C.

Elaborate tracking of the project specifications with a change control system

D.

Project specifications becoming more explicit and detailed as the project progresses

Which type of contract is a hybrid of both a cost-reimbursable and a fixed-price contract?

A.

Cost Plus Award Fee Contract (CPAF)

B.

Firm-Fixed -Price Contract (FFP)

C.

Time and Material Contract (T&M)

D.

Cost Plus Incentive Fee Contract (CPIF)

Which of the following is an example of a technique used in quantitative risk analysis?

A.

Sensitivity analysis

B.

Probability and impact matrix

C.

Risk data quality assessment

D.

Risk categorization

Which process is usually a rapid and cost-effective means of establishing priorities for Plan Risk Responses?

A.

Identify Risks

B.

Plan Risk Management

C.

Perform Qualitative Risk Analysis

D.

Perform Quantitative Risk Analysis

Every project creates a unique product, service, or result that may be:

A.

tangible

B.

targeted

C.

organized

D.

variable

Which type of managers do composite organizations involve?

A.

Functional managers and manager of project managers

B.

Functional managers only

C.

Project managers only

D.

Technical managers and project managers

In which process group is the scope first defined?

A.

Initiating

B.

Planning

C.

Executing

D.

Controlling

Which tool or technique is used to develop a project charter?

A.

Project manager information systems

B.

Expert judgment

C.

Change control meetings

D.

Brainstorming

Which standard has interrelationships to other project management disciplines such as program management and portfolio management?

A.

Program Management Body of Knowledge Guide

B.

The Standard for Program Management

C.

Organizational Project Management Maturity Model (OPM3$)

D.

Guide to the Project Management Body of Knowledge (PMBOK®)

The Cost Management processes and their associated tools and techniques are usually selected during which of the following?

A.

Project finance management

B.

Project cost estimation

C.

Project life cycle definition

D.

Project plan development

What causes replanning of the project scope?

A.

Project document updates

B.

Project scope statement changes

C.

Variance analysis

D.

Change requests

Which is a tool or technique used in Define Scope?

A.

Templates, forms, and standards

B.

Change requests

C.

Product analysis

D.

Project assumptions

Which Process Group and Knowledge Area include the Sequence Activities process?

A.

Executing Process Group and Project Time Management

B.

Executing Process Group and Project Cost Management

C.

Planning Process Group and Project Time Management

D.

Planning Process Group and Project Cost Management

In which type of contract are the performance targets established at the onset and the final contract price determined after completion of all work based on the sellers performance?

A.

Firm-Fixed-Price (FFP)

B.

Fixed Price with Economic Price Adjustments (FP-EPA)

C.

Fixed-Price-Incentive-Fee (FPIF)

D.

Cost Plus Fixed Fee (CPFF)

Which input to the Identify Stakeholders process provides information about internal or external parties related to the project?

A.

Procurement documents

B.

Communications plan

C.

Project charter

D.

Stakeholder register

An element of the project scope statement is:

A.

Acceptance criteria.

B.

A stakeholder list.

C.

A summary budget,

D.

High-level risks.

What entity is assigned various responsibilities related to the centralized and coordinated management of those projects under its domain?

A.

Project management office

B.

Project team office

C.

Executive sponsor office

D.

Program management office