Which technique is commonly used for the Perform Quantitative Risk Analysis process?

A.

Brainstorming

B.

Strategies for opportunities

C.

Decision tree analysis

D.

Risk data quality assessment

Which of the following tools and techniques is used in the Develop Project Team process?

A.

Acquisitions

B.

Organizational theories

C.

Team-building activities

D.

Virtual teams

Identify Risks is part of which Process Group?

A.

Planning

B.

Executing

C.

Closing

D.

Initiating

A weighting system is a tool for which area of Conduct Procurements?

A.

Plan contracting

B.

Requesting seller responses

C.

Selecting seller's

D.

Planning purchase and acquisition

The project management processes are usually presented as discrete processes with defined interfaces, while in practice they:

A.

operate separately.

B.

move together in batches,

C.

overlap and interact.

D.

move in a sequence.

The scope management plan and scope baseline are contained in:

A.

organizational process assets

B.

a requirements traceability matrix

C.

the project charter

D.

the project management plan

Risk responses reflect an organization's perceived balance between:

A.

risk taking and risk avoidance.

B.

known risk and unknown risk.

C.

identified risk and analyzed risk.

D.

varying degrees of risk.

Which tool or technique is used to develop the human resource management plan?

A.

Ground rules

B.

Expert judgment

C.

Team-building activities

D.

Interpersonal skills

The Project Management Process Group in which performance is observed and measured regularly from project initiation through completion is:

A.

Executing.

B.

Initiating,

C.

Monitoring and Controlling.

D.

Planning.

When managing a project team, what helps to reduce the amount of conflict?

A.

Clear role definition

B.

Negotiation

C.

Risk response planning

D.

Team member replacement

What is a tool to improve team performance?

A.

Staffing plan

B.

External feedback

C.

Performance reports

D.

Co-location

Team performance assessments is an output of which of the following processes?

A.

Develop Human Resource Plan

B.

Perform Quality Control

C.

Develop Project Team

D.

Manage Project Team

Which of the following procurement processes results in the awarding of a procurement contract?

A.

Administer Procurements

B.

Close Procurements

C.

Conduct Procurements

D.

Plan Procurements

A project charter is an output of which Process Group?

A.

Executing

B.

Planning

C.

Initiating

D.

Closing

What does a CPI value greater than 1.0 indicate?

A.

Cost right at the estimated value

B.

Cost under the estimated value

C.

Cost right at the actual value

D.

Cost over the estimated value

The Project Human Resource Management process that involves confirming human resource availability and obtaining the team necessary to complete project activities is:

A.

Acquire Project Team.

B.

Plan Human Resource Management.

C.

Manage Project Team.

D.

Develop Project Team.

Which cost estimate technique includes contingencies to account for cost uncertainty?

A.

Vendor bid analysis

B.

Three-point estimates

C.

Parametric estimating

D.

Reserve analysis

Which of the seven basic quality tools is especially useful for gathering attributes data while performing inspections to identify defects?

A.

Histograms

B.

Scatter diagrams

C.

Flowcharts

D.

Checksheets

Organizational process assets can be divided into which of the following two categories?

A.

Project files and corporate knowledge base

B.

Templates, and processes and procedures

C.

Standards, and processes and procedures

D.

Corporate knowledge base and processes and procedures

What is the name of a graphic display of project team members and their reporting relationships?

A.

Role dependencies chart

B.

Reporting flow diagram

C.

Project organization chart

D.

Project team structure diagram