Which type of analysis systemically gathers and analyzes qualitative and quantitative information to determine which interests should be taken into account throughout the project?

A.

Product

B.

Cost-benefit

C.

Stakeholder

D.

Research

Which of the following statements correctly characterizes pull communication?

A.

It includes letters, memos, reports, emails, and faxes.

B.

It requires recipients to access communication content at their own discretion.

C.

It is the most efficient way to ensure a common understanding among all participants.

D.

It is primarily used when the volume of information to be transferred is minimal.

Which process involves documenting the actions necessary to define, prepare, integrate, and coordinate all subsidiary plans?

A.

Collect Requirements

B.

Direct and Manage Project Execution

C.

Monitor and Control Project Work

D.

Develop Project Management Plan

You are assigned to implement the project control plan. What should you do to ensure the plan is effective and current?

A.

Perform periodic project performance reviews.

B.

Identify quality project standards.

C.

Follow ISO 9000 quality standards.

D.

Complete the quality control checklist.

Which tool or technique is required in order to determine the project budget?

A.

Cost of quality

B.

Historical relationships

C.

Project management software

D.

Forecasting

Enterprise environmental factors are an input to which process?

A.

Control Scope

B.

Define Scope

C.

Plan Scope Management

D.

Collect Requirements

Which basic quality tool is most useful when gathering attributes data in an inspection to identify defects?

A.

Control charts

B.

Pareto diagrams

C.

Ishikavva diagrams

D.

Checksheets

A tool and technique used during the Create WBS process is:

A.

decomposition

B.

expert judgment

C.

inspection

D.

variance analysis

Which document defines how a project is executed, monitored and controlled, and closed?

A.

Strategic plan

B.

Project charter

C.

Project management plan

D.

Service level agreement

Using values such as scope, cost, budget, and duration or measures of scale such as size, weight, and complexity from a previous similar project as the basis for estimating the same parameter or measurement for a current project describes which type of estimating?

A.

Bottom-up

B.

Parametric

C.

Analogous

D.

Three-point

Which tool or technique of Plan Quality involves comparing actual or planned practices to those of other projects to generate ideas for improvement and provide a basis by which to measure performance?

A.

Histogram

B.

Quality audits

C.

Benchmarking

D.

Performance measurement analysis

Grouping the stakeholders based on their level of authority and their level of concern regarding project outcomes describes which classification model for stakeholder analysis?

A.

Influence/impact grid

B.

Power/influence grid

C.

Power/interest grid

D.

Salience model

The following is a network diagram for a project.

The critical path for the project is how many days in duration?

A.

10

B.

12

C.

14

D.

17

Which component of the human resource management plan describes when and how project team members are acquired and how long they will be needed?

A.

Resource breakdown structure

B.

Staffing management plan

C.

Project organizational chart

D.

Scope management plan

The scope management plan and scope baseline are contained in:

A.

organizational process assets

B.

a requirements traceability matrix

C.

the project charter

D.

the project management plan

The only Process Group that comprises processes that typically occur from the beginning to the end of the project life cycle is:

A.

Planning.

B.

Executing,

C.

Monitoring and Controlling.

D.

Closing.

Changes to formally controlled documentation, plans, etc. to reflect modified or additional ideas or content are known as:

A.

updates.

B.

defect repairs.

C.

preventive actions.

D.

corrective actions.

Funding limit reconciliation is a tool and technique of which Project Cost Management process?

A.

Estimate Costs

B.

Control Costs

C.

Plan Cost Management

D.

Determine Budget

In a construction project schedule, what is the logical relationship between the delivery of the concrete materials and the pouring of concrete?

A.

Start-to-start (SS)

B.

Start-to-finish (SF)

C.

Rnish-to-finish (FF)

D.

Finish-to-start (FS)

What are the identified risks for doing excessive decomposition in a WBS?

A.

Insufficient project funding and disqualification of sellers

B.

Insufficient project funding and ineffective use of resources

C.

Disqualification of sellers and non-productive management efforts

D.

Non-productive management effort and inefficient use of resources