Which of the following statement is true about Quality control?

A.

Monitoring specific project results to determine If they comply with relevant quality standards

B.

Evaluating overall project performance on a regular basis

C.

Taking action to increase the effectiveness and efficiency of the project

D.

Identifying which quality standards are relevant to the project

Complete final contract performance reporting and verify product is done in _______.

A.

Plan Procurements

B.

Conduct Procurements

C.

Administer Procurements

D.

Close Procurements

Which of the following is a mandatory prerequisite for team building?

A.

Funding for staff development activities

B.

Shared work ethics among team members

C.

Commitment from top level management

D.

Removal of troublesome individuals

The practice of ceasing mass inspections and ending awards based on price is credited to which of the following:

A.

Edward Deming

B.

Philip Crosby

C.

Juran

D.

Pareto

Which of the following approaches to quality improvement is LEAST likely to produce positive results?

A.

Continuous improvement

B.

Increased inspection

C.

Statistical quality control

D.

IS09001 certified process

Decomposition is ___________.

A.

What happens when changes to the project scope are ignore

B.

Subdividing the major project deliverables into smaller, more manageable components

C.

Defining a general product description into more discrete definitions of individual components

D.

Subdividing the project into logical divisions of effort aligned within the performing organization's functional areas

When should the project expeditor form of organization be used?

A.

When the project is extremely important to the organization

B.

When a project's cost and importance are relatively low

C.

When the project manager has a lot of responsibility and accountability

D.

When the organization's primary source of revenue is derived from projects

The BEST way to organize project activities for scheduling is by ________.

A.

WBS

B.

Critical Path

C.

Task start date

D.

Responsible organization

The three major types of communication are:

A.

Written, verbal, and non-verbal

B.

Verbal, formal documentation, and informal documentation

C.

Verbal, written, and graphic

D.

Verbal, written, and electronic

The principle states that "Employees who believe that their efforts will lead to effective performance and who anticipate important rewards for their accomplishments become productive stay productive." This principle illustrates which of the following theory?

A.

Expectancy theory

B.

Maslow theory

C.

Herzberg theory

D.

None

Which of the following statements concerning bottom up estimating is true?

A.

The cost and accuracy of bottom-up estimating is driven by the size of the individual work items

B.

Smaller work items increase both cost and accuracy

C.

Larger work items increase both cost and accuracy

D.

Both A and B are true

A series of consecutive points on the same side of the average is called ____________.

A.

Run Chart

B.

Trend Analysis

C.

Outliers

D.

Cycle

A unilateral contract under which the seller is paid a preset amount per unit of service is called __________.

A.

A cost reimbursable contract

B.

A lump sum contract

C.

A time and material contract

D.

A fixed price contract

Estimated at Completion is determined by ___________.

A.

ETC + ACWP

B.

BAC - ETC

C.

BAC/CPI

D.

Both A and C

A leadership style in which the project manager shares problems with team members and formulates solutions as a group is called _________.

A.

Autocratic

B.

Consultation In a group

C.

Consensus

D.

One-to-one consultation