PMI PMI-200 - PMI Agile Certified Practitioner (PMI-ACP)
A new agile team is forming to address a high-priority project. Team members are dispersed over a wide geographic area. The scrum master and the team are currently defining their working agreement.
What should be part of the working agreement for a dispersed team?
A client needs to release their product to market earlier than planned. They need to start receiving the expected revenue, according to their financial forecast, which will require completing the work left on all user stories in the backlog.
What should the project lead do to accommodate this request?
An agile team lead is assigned to a project that must ensure data security. What should the team lead do to guarantee that security, as a non-functional requirement, is managed throughout the project?
Just before a scheduled product launch, the customer declined to accept the final deliverable after seeing the demo. What should the project manager do to prevent this in the future?
A product's scope and acceptance criteria have been defined, and the product is planned for release at the end of the next quarter. What should the project team do next?
An agile team has defined their definition of done (DoD) for a sprint. However, during the demo, the product owner is not sure if a user story can be marked as done.
Select the most appropriate sequence of activities that would need to be completed to meet a well-defined, mature definition of done (DoD).
An agile coach advised a project manager to continuously improve their ability to support their team and remove any obstacles in the project's way. What role is the agile coach advising to the project manager to take on?
During a retrospective, a team member claims that a specific set of documentation that is continuously updated during iterations is not being used by any stakeholder. What should the team do?
Following approval of a business case, a company will introduce a new mobile app for customers to place orders. Time to market is a key concern. The product has entered into the 3rd iteration, but the team is concerned because they feel the technical designs do not meet the agreed-on definition of done (DoD). An agile coach has been hired to help validate product delivery against business requirements.
What should the agile coach do?
Midway through a two-week sprint, an agile team realizes that the features cannot be delivered within the sprint. The team determines that another week will be required to complete all committed features.
What should the team do?