PMI PMI-ACP - PMI Agile Certified Practitioner (PMI-ACP)
Project stakeholders are finding it difficult to know the real-time status of who has been assigned to various stories and the status of each work item.
What should the agile project manager do?
A project manager is managing a large complex project with cross-functional teams using an adaptive approach. Frequent communication among the team leads of these cross-functional teams is crucial for the project to stay on track and deliver value according to the project plan.
Which agile communication practice should the project manager implement to ensure the cross-functional teams interact frequently?
An agile practitioner notices that a project is increasing open defect counts after every subsequent iteration.
What should the agile practitioner do?
The first project vision statement meeting for a newly formed team did not achieve its outcome. Lack of participation combined with conflicting views of those who participated led to disagreement on how to proceed.
How can the team improve their collaboration?
Two similar stories A and B are estimated at 3 story points. Story C is estimated at 8 points. After an iteration in which A and C were completed, it is found that story A took much longer than story C.
What should the agile practitioner do?
During sprint planning, the product owner wants the team to prioritize and deliver a number of features that have the highest business value. Due to technical dependencies, the team does not agree with the prioritization.
What should the project leader do?
The transition of a monthly news publication from paper to digital is planned to start in the next few weeks. There is a debate between the product owner and the development team about the initial features to be made available and the first five stages of implementation.
What should the scrum master do to address this situation?
A scrum team is working on an important project with a short deadline. To save time and reduce overhead, the product owner proposes that the regular sprint reviews should be cancelled and replaced with a review of each release according to the release plan.
What should the scrum master do?