Summer Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: ecus65

PMI PMI-PBA - PMI Professional in Business Analysis

Page: 6 / 6
Total 200 questions

Which document best provides the boundaries for product development?

A.

Scope definition

B.

Requirements baseline

C.

Project plan

D.

Scope document

While preparing a business case, an experienced business analyst faces difficulty in deciding which of three different solution options to recommend. The senior vice president (SVP) who requested the business case favors an outsourced solution; however, an analysis

favors a custom-developed solution, either built internally or using contract labor.

To prepare the recommendation, what should the business analyst do?

A.

Perform solution evaluation.

B.

Formulate a weighted-ranking matrix.

C.

Review the stakeholder analysis.

D.

Recommend the SVP's choice, as it is most likely to be adopted.

Which technique or tool is used to obtain acceptance of the delivered product?

A.

Expert judgment

B.

Facilitated workshops

C.

Inspection

D.

Contextual inquiry

Once a new project has been identified, the business analyst works with project team members to define what will be included in and excluded from the new system. Which of the following has the business analyst defined?

A.

Solution design

B.

Business requirements

C.

Solution scope

D.

Business case

A business analyst is trying to determine which analysis technique will be best suited to elicit information from a large number of users in a short period of time. Which elicitation technique is best suited for this purpose?

A.

Ongoing observation

B.

Facilitated workshop

C.

Questionnaire

D.

Group brainstorming

Through user acceptance testing, a software flaw was identified. What should the business analyst do next as part of the root cause analysis in order to analyze and resolve the discrepancy?

A.

Create a fishbone diagram.

B.

Create an interface analysis.

C.

Create a Delphi estimation.

D.

Create a functional decomposition.

Company A has been awarded a contract to finalize the development of a product that Company B was not able to finish. The business analyst is given a copy of the documentation left by Company B.

To which of the following documents should the business analyst pay the most attention to ensure the project succeeds this time?

A.

Business use cases

B.

Application design documentation

C.

Test case documentation

D.

Clauses in the contract

A business analyst is trying to complete the requirement documentation of a project and finds that the developers have started development. The business analyst should first facilitate the:

A.

requirements gathering workshops with the stakeholders.

B.

requirements acceptance with the customer.

C.

requirements validation with the testers.

D.

requirements sign-off with the customer.

A major stakeholder wants to know how the implementation of new features in the development of a product is progressing. Which of the following should be reported to the stakeholder?

A.

Distribution of project changes

B.

Requirements status during the project development cycle

C.

Number of requirements approved vs. number of requirements rejected

D.

Number of requirements tested and approved

A stakeholder has rejected a project's deliverable because it does not meet the original business need. It is further determined that the deliverable does not meet the requirements identified in the baseline.

What is the best approach to resolve this issue?

A.

Meet with the customer and apologize for misunderstanding the business's need.

B.

Suggest re-estimating the requirement and following the change control process.

C.

Provide the stakeholder with a copy of the approved requirements baseline and move forward without making a change.

D.

Require development resources to work overtime to modify the deliverable to satisfy the stakeholder.