Month End Sale Special - 75% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: newyear

PMI PMI-RMP - PMI Risk Management Professional (PMI-RMP) Exam

Page: 9 / 9
Total 333 questions

A risk manager is managing risks in a project. During the initial stages of project execution, a new risk is identified. There is a very small chance that this risk will occur and even if it occurs, the impact would be low.

What should the risk manager do with this risk?

A.

Put the risk on the watch list.

B.

Seek guidance from subject matter experts (SMEs).

C.

Ignore this risk as it is not critical.

D.

Inform the stakeholders about this risk.

The project team has correctly identified, assessed, and planned responses for a project ' s risks. The risk manager is required to prepare a quarterly report on the performance of managing the risks.

What are two options the risk manager should consult for the analysis? (Choose two.)

A.

Proximity dales for open risks

B.

Backlog of change orders to be submitted to client

C.

Risks that have materialized and the overall risk profile

D.

Number of schedule baseline changes approved

E.

Risks due to the number of claims submitted to the client

At an oil and gas company, a major unified management information system is to be implemented. The project manager noted that risks gathered from the organization ' s business functions are not properly identified and categorized, making it difficult to develop an effective risk response.

How should the project manager handle this situation?

A.

Outsource conducting the risk response plan to risk consultants.

B.

Ask functional managers to improve their risk register and process.

C.

Adjust the risk response plans to effectively handle the identified risks.

D.

Coach the functional groups on how to properly conduct the process.

A project team is preparing a project plan for a government-funded project with multiple stakeholders, including government employees. The project sponsor requests the risk manager estimates the potential costs associated with delays that may arise from government employees, due to bureaucratic processes and other administrative factors.

How should the risk manager approach this task?

A.

Create a risk register to document all potential risks and estimated impacts, including delays due to government employees.

B.

Develop a risk response plan that includes specific mitigation strategies for government-related delays.

C.

Perform a quantitative risk analysis to determine the potential financial impact of government-related delays.

D.

Conduct a qualitative risk analysis to assess the likelihood and impact of potential delays.

A company has implemented a policy requirement for employees to use complex passwords and update them regularly. A few employees are unable to make the changes, which increases the likelihood of cybercriminals compromising their passwords.

What should the risk manager do?

A.

Increase the residual risk monitoring.

B.

Increase the inherent risk monitoring.

C.

Reassess the inherent risk level.

D.

Reassess the residual risk level.

A subcontractor working on a project may cause delays in the construction schedule. The project manager records this risk in the risk register and issues a change request sponsor rejects the change request.

What should the project manager have done differently?

A.

Executed the risk strategy response and recorded it in the risk register.

B.

Performed an analysis to affirm the request is valid before submitting.

C.

Informed the client and the project sponsor that the request is being submitted.

D.

Contacted the other stakeholders so they know the request is in process.