Pre-Summer Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmas50

PMI PMI-RMP - PMI Risk Management Professional (PMI-RMP) Exam

Page: 9 / 9
Total 278 questions

The project manager for project X was expecting the mobilization of critical equipment from another project, project Y. However, a day before the mobilization was scheduled, another project manager notifies project X ' s project manager that the equipment would not be available for at least another month due to delayed activities for project Y. This has jeopardized meeting a critical milestone for project X.

How should project X ' s project manager avoid this situation in the future?

A.

Prepare a contingency response plan to implement when delays occur

B.

Ask the other project manager to officially confirm the new date in writing

C.

Request that the other project manager be added to relevant reports

D.

Request that the other project manager inform if any additional delays are expected

A project team in a multinational organization is working on a risk management plan for a multimillion-dollar project. This project involves three global regions with a wide range of critical stakeholders with varying degrees of risk appetite.

What should the risk manager advise the project team to do?

A.

Align the project risk thresholds with the risk appetite of a critical region.

B.

Align the project risk thresholds with the organizational risk appetite.

C.

Concentrate on the risk appetites of the influential stakeholders.

D.

Concentrate on the risk appetites of the vulnerable stakeholders. 

A software company has recently completed a project that delivered a new web application. Throughout the project, several issues were realized that resulted in cost and schedule overruns. The project ' s executive sponsor has requested a deep-dive into what went wrong since the company will be developing additional web applications in the future.

What should the risk manager do?

A.

Gather the project ' s status reports and meeting minutes to determine when issues occurred and how quickly the issues were addressed.

B.

Conduct a retrospective meeting with stakeholders and inquire about what went well and what could be improved on future projects.

C.

Work with the project manager to determine if additional resources could have prevented or mitigated the issues that arose on the project.

D.

Review the project ' s risk register and determine how comprehensive and effective each risk and issue response was.