11.11 Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmas50

PMI PMP - Project Management Professional (2025 Version)

Page: 10 / 13
Total 2040 questions

In an agile project, the project owner has repeatedly called for ad hoc meetings with team members. What should the project manager do?

A.

Ask the team to focus only on the goal, not on ad hoc meetings.

B.

Coach the project owner about the implications of unplanned meetings.

C.

Discuss the issue with the project owner at the retrospective meeting.

D.

Escalate the situation to management because it is affecting the team.

A project manager collects various pieces of information and consolidates metrics in an agile project. The project manager finds that there is slack in the team in terms of productivity. The number of items sent to development per person has decreased by 10%, and the project manager used a root cause analysis (RCA) and discovered the reason is a lack of knowledge in one of the frameworks used for modeling.

What should the project manager do next?

A.

Foster knowledge sharing and coaching among team members.

B.

Arrange for external training amid the tight project schedules.

C.

Add new members for the underperforming team.

D.

Seek an external expert to review the framework.

A hybrid project has just started, which will result in a new technology that could disrupt the market if well accepted by the public. The product requires health and safety

approvals from the government. As this is an innovative solution, the sponsor and product owner are unsure if it will be accepted by the public.

What is the appropriate flow for product development?

A.

Complete development with all functionalities in perfect condition prior to demonstrating to stakeholders to ensure a great first impression.

B.

Complete development for each sprint and demonstrate the product increment to internal stakeholders and the government, without engaging other externalstakeholders.

C.

Complete development for the must-have functionalities only prior to demonstration in order to fail fast and get early feedback.

D.

Complete development for must-have functionalities only and demonstrate it to a focus group, but wait until all development is complete to demonstrate it to thegovernment.

A company has decided to initiate a project to eliminate a sales channel that has been unprofitable for the past 3 years. Some members of the project team are pessimistic about the project.

What should the project manager do in this situation?

A.

Engage the functional managers to describe the project's impact to the team members directly.

B.

Provide team members with specific and clear instructions on the project objectives and tasks.

C.

Communicate the project's impact and plans to engage the project team throughout the project.

D.

Escalate the team's concerns and ask the project sponsor to change the team's composition.

A project manager is assigned to an agile project that has an aggressive time line and a fixed budget. Currently, the majority of the items are in the backlog and only a few are in process or completed.

What should the project manager do?

A.

Prioritize which backlog activities should be kept.

B.

Work on the backlog activities with fewer story points.

C.

Ask for more resources to clear the backlog activities.

D.

Assign an owner for each backlog activity and track progress.

A project manager is overseeing a project as part of a program geared toward a major technology disruption. The team is comprised of brilliant young professionals who have worked on different projects for the organization in the past. However, the team complained that they previously experienced a lack of direction during project execution and are a traid of the same issue in this project.

Which two actions should the project manager take to ensure that this issue does not occur in this project? (Choose two)

A.

Keep the team engaged and focused on the project's direction.

B.

Encourage the team to do a brainstorming session and provide a mitigation plan.

C.

Focus on the resource management plan and track project progress,

D.

Set a clear vision for the project and ensure it is visible to all stakeholders.

E.

Organize a team-bonding activity and invite an external manager to speak to the team.

A project team is working on a product that is planned for multiple iterations. They are delivering incremental value.

When should the value be demonstrated?

A.

After full development is completed

B.

When a major feature is completed

C.

At the end of each and every iteration

D.

When the sponsor approves the increment

A project manager has recently moved to an organization to lead a key project. The project manager notices that team performance is below the target, and the tasks assigned are not delivered on time. Team commitment is also not as appropriate as it should be.

What should the project manager do?

A.

Study and determine the appropriate leadership style suitable for the team.

B.

Hire a project team leader who can influence the project team members.

C.

Schedule a meeting and communicate the performance concern to the team.

D.

Apply an agile approach to help improve team performance.

During the execution of a project to develop a prototype, the customer asks the project manager to stop the prototype line and purge a specific

component based on recent reliability tests that have deemed the component to be deficient. The project manager checked the quality

management plan and there is no reference to this component.

What should the project manager do next?

A.

Inform the project sponsor of the situation and wait for the sponsor to provide further directions.

B.

Call a technical meeting with the customer to agree on a specification for the component and document it in the quality management plan.

C.

Submit a change request to proceed with the replacement of the component and wait for further customer instructions.

D.

Keep running the manufacturing line because there are no quality specifications for this component.

A project was initiated due to an external business influence. During the course of the project, some of the business parameters considered at the

beginning of the project have changed.

What should the project manager do?

A.

Inform the team not to accept any changes, as it involves significant rework.

B.

Request management to update the project requirements accordingly.

C.

Request an update of only new requirements, as other changes involve rework.

D.

Inform management that the agreed-upon scope cannot be changed.

In the planning phase of a software implementation project, two of the team members disagree on how to approach end-user training. The

discussion has intensified and the team members are not able to agree.

What should the project manager do next?

A.

Remove one of the team members from the project to improve team dynamics.

B.

Make a decision based on expert judgment as a project manager.

C.

Consider the view of each team member about the issue in order to reach consensus.

D.

Remove both team members since they are not productively adding to the team.

A software delivery project began having technical impediments. The issue may cause a delay of the deliverables. The technical service team has been working on the issue, but the issue is unresolved even after 1 week of maintenance.

What should the senior project manager do now?

A.

Use interpersonal skills to expedite the issue.

B.

Send a gentle reminder to the technical service team.

C.

Update the issue log with the status and priority.

D.

Issue a formal warning to the technical service team.

A newly commissioned project has had trouble recruiting team members because the turnover rate is high. The human resource (HR) manager

has conducted several exit interviews. Many team members have expressed that the project manager has inadequate relationship management

competencies. The project manager explains that the exiting team members were lazy.

What should the project manager do to prevent this high turnover rate from continuing?

A.

Be more involved in the team member recruitment process to ensure qualified team members are chosen.

B.

Develop relationship skills as a leader and also develop the teams’ emotional intelligence skills.

C.

Avoid micromanaging the team, enforce stricter rules, and monitor employees.

D.

Explain to the recruiting manager that a project is temporary in nature, making it different than an operational environment.

A project manager is assigned to a dental equipment development project that is in the middle of its design phase. After reviewing the project prototype, it is identified that a couple of requirements specifications are missing.

Which action should the project manager take next?

A.

Discuss with the team and build a workaround plan to immediately deliver the pending requirements specifications.

B.

Ask the team to wait until they are able to update the requirements specifications.

C.

Prepare a change request for the change control board (CCB) to remove the missing requirements specifications.

D.

Meet with the development team to review and assess the requirements specifications.

During project execution, one of the project tasks is to create an important document for a service vendor. The project manager assigns a senior engineer to clearly detail

the service instructions to avoid any redo loops. Two days after the service information document was sent, the service vendor has doubts and needs more clarity on the task. This redo loop will probably cause a delay of one or more days.

What should the project manager do next?

A.

Escalate the issue to the engineer's functional manager.

B.

Discuss the issue with the engineer and determine how to prevent another problem.

C.

Document the task on the kanban board and make it the highest priority.

D.

Assign another engineer to the task due to the urgency.

An IT company's office is closed abruptly due to a new government restriction. All employees are now working remotely. Project team A has a

critical project delivery due in 2 weeks. The project manager, apprehensive about this sudden change, instantly emails the customer explaining

that the project delivery will be delayed. The customer is unhappy with this and has escalated the issue to senior management.

What should the project manager have done differently?

A.

Communicated a new delivery date to the customer along with the news about the delay

B.

Disclosed to senior management in confidence, then communicated the delay to the customer

C.

Assessed the situation with the project stakeholders first and communicated the impact to the customer

D.

Spoken to the customer on the phone and explained the reason for the delay instead of writing an email

A project manager receives an email from a customer saying that they do not want to keep working with one of the project team members. The customer does not provide

any reasons for this sentiment. The project manager is concerned because this project team member is highly skilled and experienced and is key in one of the main project deliverables.

What should the project manager do to ease the situation?

A.

Talk to the customer and project team member separately to assess the issue and decide on the next steps.

B.

Remove the project team member immediately and assign the pending activities to other team members.

C.

Tell the customer that they do not have the authority to remove project team members.

D.

Ask the project team member to call the customer to apologize for their behavior.

A project team is performing extremely well when it comes to delivering the value-added features to the customer in each sprint. However, they are missing the

documentation portion and the project manager must find a way to make sure the documentation is kept current.

Which action should the project manager take?

A.

Create a specific sprint to deliver the project documentation.

B.

Assign a dedicated resource to work on the documentation during the project.

C.

Make documentation a standard part of the definition of done (DoD).

D.

Focus on the documentation after the features are delivered.

During the third iteration of a project, the product owner requests another mandatory feature. This also happened in the previous two sprints, which resulted in failure and caused frustration within the team.

What should the project manager do next?

A.

Incorporate the changes in the last sprint before the first release.

B.

Call for an internal meeting to discuss the changes and their value.

C.

Ask the product owner to prioritize the backlog with the project team.

D.

Request the scrum team to prioritize the product backlog.

A project team is globally distributed with team members living and working in different time zones. The project manager is trying to get the team

to collaborate effectively.

Which three actions should the project manager take to accomplish this goal? (Choose three)

A.

Require the team to have daily mandatory meetings with the project management office (PMO).

B.

Recommend the use of formal written documentation in all project communications.

C.

Review the communications strategy with the team regularly with a view for continuous improvement.

D.

Send out a survey to review the preferred method, time frequency for communications.

E.

Compile a communications management plan with input from all stakeholders and distribute for review and approval.

An iteration is almost finished, but the team is struggling to complete the stories that require more time. What should the project manager do first?

A.

Meet with the project team to develop a proper resolution to the issue.

B.

Update the project artifacts to reflect the new deadlines reported.

C.

Request approval from the project sponsor to add more resources,

D.

Prepare documentation to explain the issue and communicate accordingly.

A project sponsor has approved the project charter and business case. The project manager has reviewed the artifacts to initiate the project and is unclear if the intended benefits of the project align with the strategic objectives of the business.

What should the project manager do first?

A.

Start executing the project since leadership is responsible for the business strategy.

B.

Meet with the project sponsor to better understand the strategic benefits of the project.

C.

Propose an updated business case and project charter that are more aligned with the business strategy.

D.

Conduct qualitative and quantitative risk analysis and record the results in the risk register.

A customer complains that the user stories released so far contain too much jargon and do not reflect the expectations of the product. What should the project manager do

next?

A.

Request approval from the company director to conduct training for the team.

B.

Ask the senior developer to rewrite all the stories.

C.

Engage with the customer and rewrite all the stories.

D.

Rewrite the stories to include the technical vision of the product.

A project team member informs the project manager that a stakeholder is contacting the team member to request status updates. The team member is being distracted by these repeated requests, which are interfering with the completion of assigned tasks.

What should the project manager do?

A.

Increase the frequency of updates given to this stakeholder.

B.

Inform the team member to stop sending any further updates to the stakeholder.

C.

Raise this issue to the project sponsor in the next project status review meeting.

D.

Review this stakeholder's communication requirements.

A project manager is managing a very important business transformation project. The goal of the project is to extend a desktop application with a mobile application module.

The marketing department believes that a main competitor is working on a similar product.

Which delivery approach should the project manager use for this project?

A.

Traditional delivery, to ensure high quality and that the product meets market demands

B.

Extreme Programming (XP) delivery, to mitigate the high risk related to a new product

C.

Iterative delivery, to ensure that user feedback is incorporated into the second iteration

D.

Incremental delivery, to ensure that mobile capability is released fast to the users

A project manager is about to slant the testing phase of a new project. Historical data show there is a high risk of failing the agreed acceptance criteria.

How should the project manager ensure the acceptance criteria are ret?

A.

Perform tests and routinely track results as per the quality management plan.

B.

Make sure the stakeholders are aware of the acceptance criteria.

C.

Negotiate to obtain approval if most of the tests have passed.

D.

Modify the acceptance criteria before the official delivery.

A senior employee with experience relevant to a highly complex project is seeking a promotion to be able to join the project. The employee has made a recommendation regarding the project. The project charter was recently approved.

How should the project manager address the employee's request?

A.

Evaluate the employee's recommendation by reviewing the lessons learned from a similar project.

B.

Create a salience model to determine if the employee will have influence on the project.

C.

Ask the project sponsor to revisit the project charter to consider the employee's recommendation.

D.

Assess the influence and power of the employee to see if the employee will add value.

A project manager is assigned to a multiyear enterprise resource planning (ERP) solution project. During planning, the business sponsor emphasizes the importance of demonstrating value along the way, while maintaining the integrity of the final product.

How should the project manager establish the delivery model for this project?

A.

Organize the project into multiple subsets based on business functions and deliver each subset as a component of the final product.

B.

Reestablish the project as a program with multiple small projects, as each project will be delivered as a product of its own.

C.

Communicate the latest status to the steering committee and provide a demo of the features completed.

D.

Schedule routine demos on features completed and deliver a single product once all features are completed.

During the last two iterations of a project, one of the team members had low performance. The project manager conducted two feedback sessions with the team member and escalated the issue to the resource manager and project sponsor, but there has been no improvement.

What should the project manager do next?

A.

Escalate the situation again to the project sponsor.

B.

Review this obstacle during the daily standup meeting.

C.

Request a new resource to execute the activities.

D.

Provide feedback to the resource at the sprint review.

A junior project manager was recently hired to lead a complex project scheduled to kick off in 2 weeks. The junior project manager was introduced to another project

manager for mentoring.

Which two benefits will the junior project manager realize by being assigned to a mentor? (Choose two)

A.

The junior project manager reports administratively to their mentor so that human resource (HR) questions can be answered quickly.

B.

The junior project manager can discuss certain problems with their mentor without fear of retribution.

C.

The mentor will be immediately available to take over the project if there are problems or project delays.

D.

The mentor will be involved in the decision-making processes implemented by the junior project manager.

E.

The mentor can provide past project documentation with early warning indicators that potential problems could occur.

A project manager has been managing an agile project for 6 months. Over the last two iterations, the team velocity has decreased due to a new technology that was needed

for the product.

What should the project manager do to continue with the delivery plan and return to the expected velocity?

A.

Use retrospectives to better understand the new technology's impact on the schedule, map the skill gaps, and adjust the team accordingly.

B.

Reevaluate the backlog by looking for high-value/low-effort items, and negotiate a new minimum viable product (MVP) strategy with key stakeholders.

C.

Seek sponsor approval for additional funding to hire new team members, increasing the capacity of the team and compensating for the productivity lost with the new technology.

D.

Replace poorly performing team members with more experienced members, setting an example of accountability for the team.

A project manager is managing an agile project that is part of a program with many interconnected projects. Dependency management is fundamental because there will be many milestones for different projects that are dependent upon each other during the program duration.

What should the project manager do?

A.

Assign a development team member to have the responsibility of managing dependencies.

B.

Suggest that each project develops a high-level plan to monitor the dependencies

C.

Recommend switching to a predictive approach to have detailed plans to manage the dependencies

D.

Continue the project with 2-week iterations as dependencies will be managed individually

One of the key stakeholders on the project team reaches out with an additional requirement that may impact the overall schedule. A discussion with another stakeholder suggests thai this might just be a small task.

What should the project manager do?

A.

Coordinate design document preparation

B.

Perform a qualitative risk analysis

C.

Request further clarification of the requirement

D.

Manage the engagement of this stakeholder.

In the middle of the execution phase for a big project a new stakeholder who was unfamiliar with the project joined the board of directors and is influencing the decisions made in the project. This change is impacting the project's progress

What should the project manager do first?

A.

Revise the project schedule

B.

Present the project to the stakeholder

C.

Inform the client about the change

D.

Update the risk register with a new risk

A project manager is part of a distributed team. The project team is using a product backlog, but due to an excessive workload, the backlog items are not very detailed. In the retrospective, a couple of new team members are raising the issue of knowledge transfer inside the team.

What should the project manager do?

A.

Ask the team to outline their expectations and confirm with them the approach to use for knowledge transfer.

B.

Organize knowledge-sharing workshops and ask one of the senior team members to facilitate them.

C.

Ensure that formal email communication is used when more information is needed to understand the work done.

D.

Hire a technical writer to document the work completed to date and develop a handover document.

A project manager receives information in preparation for reporting the project's monthly performance to the project steering committee,

* Actual progress = 2 units

* Planned progress = 3 units

* Actual cost (AC) = 2 units

* Budgeted cost = 3 units

What statement should the project manager make to the project steering committee?

A.

The project is currently behind schedule with a corresponding lower cost, and every effort is being made to expedite the delayed activities.

B.

The project is currently behind schedule with a corresponding cost savings, and no further actions should be taken.

C.

The project is currently behind schedule but at a lower cost, and an application for a time and budget extension will be submitted.

D.

The project is currently behind schedule but is under the planned expenditure, and the project manager is pleased to declare a project cost savings,

When defining the ground rules for a project team, the project manager observed that only two team members contributed to the discussion. As a

result, the team ground rules favor these two team members.

What should the project manager have done to avoid this situation?

A.

Come to the meeting with suggested ground rules

B.

Ask all team members to send new ideas prior to the meeting

C.

Extend the meeting to allow everyone to speak

D.

Set expectations for contributions ahead of the meeting

A company has created a cross-functional team to drive the digital transformation project for the business. The team is expected to deliver the minimum viable product (MVP) that addresses market need in the shortest possible time.

Match the roles for the team on the left to their corresponding responsibilities on the right.

While managing a project using a hybrid approach, the project manager realizes that there is a high level of rework due to quality issues. Because

of that, each feature is taking longer than initially estimated.

What should the project manager do to address the issue?

A.

Escalate the issue to the project sponsor.

B.

Address the issue during the next sprint planning meeting.

C.

Initiate a change request to extend the project end date.

D.

Extend the dates for future project milestones.

A project team was hired to perform on-site duties, but there were unexpected circumstances that required the entire team to work remotely Some team members returned to their hometowns and they are now requesting reimbursement for operational expenditures

What should the project manager do?

A.

Follow the Perform integrated Change Control process and submit a change request

B.

Ask the team members to draft a justification before processing the reimbursements

C.

Update the project management plan with the incurred costs

D.

Review the budget and allocate funds for the reimbursements

The project leader for an agile team has discovered that a certain team member has been struggling with an impediment that is hindering the team's progress. The project is now at risk of completing later than expected.

What should the project leader do?

A.

Report the impediment to the functional manager.

B.

Identify the impediment and associated risks at the daily standup.

C.

Escalate the impediment and associated risks to the business sponsor.

D.

Identify the impediment during the retrospective

An innovation project with a budget of over US$30 million is expected to have a large impact on the technology industry. The business area is concerned if the project will meet stakeholder expectations and raised this concern with the project manager.

What should the project manager do to manage business concerns and expectations before starting the project?

A.

Meet with the project finance team to measure market variations and product impact.

B.

Direct the project team to estimate user stories in greater detail.

C.

Ask the product owner to prioritize the backlog items based on the return on investment (ROI).

D.

Request that the project team develop a release plan and roadmap for the project.

A functional manager is concerned that the project's quality management techniques have advanced beyond the department's capabilities and wants the project team to review all quality management activities in two full-day workshops the following week. What should the project manager do next?

A.

Draft a project decision request to include in the scope for the current iteration and ask the sponsor to approve.

B.

Explain that the team is fully dedicated to the current sprint activities and negotiate a mutually agreeable time.

C.

Add this to the project backlog and have the product owner determine where it fits in terms of priority.

D.

Indicate that this was a not a requirement identified during project planning and it is outside of the scope.

A project manager determines that a critical path activity is going to be delayed. The team proposes a fallback plan that could get the project back on track; however, the plan would require an additional cost to an already tight budget.

What should the project manager do?

A.

Use the existing budget for executing the fallback plan and update the baseline.

B.

Add additional resources to the project to fast track certain activities and reduce delays.

C.

Evaluate the fallback plan proposed by the team and submit a change request, if required.

D.

Communicate the delay to stakeholders and maintain the existing budget baseline.

An agile project to provide a material information system has started. During the kick-off meeting, the team realizes that the stakeholders require a solution in 2 months, but it will take at least 4 months to deliver the entire project.

Who should the project manager contact to help the team accelerate the delivery?

A.

The human resources (HR) department—to ask for more resources to add to the project team.

B.

The product owner and the stakeholders—to prioritize the requirements in the product backlog.

C.

The team—to have them increase their velocity to accomplish the stakeholders requirements.

D.

The stakeholders—to have them prioritize the requirements in the product backlog.

During a project status meeting with senior managers, the project manager gives an update about the status of a deliverable. Some of the senior managers claim not to Know about the deliverable.

What should the project manager do next?

A.

Validate if the project charter changed from the original one.

B.

Meet with these stakeholders to review the project charter.

C.

Check if these stakeholders attend regular project meetings.

D.

Review the project charter to validate this claim.

A project manager is assigned to a large construction project with more than 100 project team members. The project manager is having a hard time keeping the project on track and deriving the planned benefits. The project manager wants to make sure that each requirement is linked to the business and project objective.

What should the project manager do?

A.

Review the requirements on a weekly basis.

B.

Implement a requirements traceability matrix.

C.

Add the requirements to the project charter.

D.

Understand the project management plan.

A project manager is assigned to work on a large global project. The resources for the project are dispersed among different organizations and countries. After the project kick-off meeting, the project manager learns that many virtual team members are unable to join the regular project update meetings. Their absence will impact the overall project schedule.

What immediate corrective action should the project manager take?

A.

Discuss the issue with the virtual team members and revise the communications management plan.

B.

Escalate this issue to the virtual team members' supervisors.

C.

Add this issue to the risk management plan and take action if it persists.

D.

Discuss the issue with the project sponsors and add this as an issue in the issue log.

In an agile project, the learn planned to complete 40 story points in an iteration, but only completed 30 story points. What is the schedule performance index (SPI)?

A.

30/40

B.

40/70

C.

30/70

D.

40/30

During a system demo, a project stakeholder rejects the features completed from the most recent user stories. According to the stakeholder, the product does not meet the

quality standards required by regulations.

What should the project manager have done to avoid this?

A.

Reviewed with the product owner that all the stories worked on in the iteration were in the project backlog

B.

Ensured that the project sponsor understood the scope of the project to avoid any future complaints

C.

Reviewed with the product owner that all acceptance criteria were met for the stories worked on in the iteration

D.

Ensured the stakeholder concerns were properly addressed in the iteration to avoid future setbacks