PMI PMP - Project Management Professional (2025 Version)
A project manager is assigned to a project that is in the execution phase that has different types of stakeholders. Some of the stakeholders are very interested in the project, whereas other do not show the same level of interest.
What should the project manager do to assure the project finishes correctly?
A project manager is facilitating a project steering committee meeting where the prioritization of work items in the backlog is being discussed. The
engineering executive wants to prioritize features based on level of effort, completing the smallest items first. The quality executive wants to
complete the most complex tasks first to have adequate time to ensure a quality product is delivered. The compliance officer wants to complete
items with associated regulatory components as they are essential items.
How should the project manager prioritize the work items?
During a system demo, a project stakeholder rejects the features completed from the most recent user stories. According to the stakeholder, the product does not meet the
quality standards required by regulations.
What should the project manager have done to avoid this?
In a marine construction project, the project manager is informed by the marine authority that the work permit will not be issued until certain environmental reinforcement work has been completed. After reviewing the project management plan, the reinforcement work is not included in the project scope.
What should the project manager do?
An agile project team is working on an infrastructure product to be delivered incrementally over several iterations. Midway through the third iteration, the whole company is
informed that the operating systems supported by the infrastructure will be terminated in the upcoming quarter. Several thousand machines will be impacted by this change.
What should the project manager do first?
During the third iteration of a project, the product owner requests another mandatory feature. This also happened in the previous two sprints, which resulted in failure and caused frustration within the team.
What should the project manager do next?
A company initiated a project to introduce a new product to the market. The product must undergo the industry's regulatory process prior to approval and launch However, the company sees a great demand for this product and wants it to launch as soon as possible.
What should the project manager do to realize this opportunity?
A project manager has established daily standup meetings with the team during the execution phase of the project. The project manager has been successful in removing 75% of the
obstacles reported, but the timeline continues to deviate further each day with no signs of improvement.
What should the project manager have done to avoid this issue?
A project's business case was just approved and the project manager is creating the benefits management plan. It is unclear how the benefits from the project align with the organization's vision.
What should the project manager do first to verify alignment?
At the end of a canceled project, the project manager sent surveys to all stakeholders. The survey also included templates for stakeholders to
outline situations, solutions, results, and suggestions.
How should the project manager use the information collected?
A project manager just finished a meeting to identify the main stakeholders of the project. What should the project manager do next?
A project manager is part of a distributed team. The project team is using a product backlog, but due to an excessive workload, the backlog items are not very detailed. In the retrospective, a couple of new team members are raising the issue of knowledge transfer inside the team.
What should the project manager do?
A project team member was unhappy with a new change in project governance and complained to one of the project sponsors. The project sponsor challenged the project manager.
How should the project manager resolve this conflict?
A project manager is reviewing the status of a large project with team members in different countries. Through the status review, the project
manager notices that one team is consistently behind schedule and their work often needs to be corrected.
What should the project manager do to improve the quality of this team's work?
The first task a project manager needs to complete on a new project is improving stakeholder engagement. How should the project manager complete the power/interest grid based on the following scenario:
• The marketing director is the key stakeholder. as the project will create a new product for the company.
• The finance director is providing funding and does not have much time to follow the tracking of the project.
• The sales representatives assigned to the team provided some negative feedback on the requirements
• The human resources (HR) intern assigned to the team was satisfied with the new product interlace.
A company's project management office (PMO) has started to implement iterative tools. The project manager is starting a new project and has
identified an opportunity to use the new tools. There is disagreement among stakeholders about the use of the adaptive tool.
What should the project manager do first?
A project team is executing a large regulatory project comprised of a multitude of internal and external stakeholders. An initial impact analysis revealed several systems, including an enhancement to existing modules as well as new builds. After completion of the initial design workshop, the team conducted a brainstorming session to better understand the types of likely users.
Which technique will best serve this purpose?
In an agile project that is about 45% complete, most team members are siloed and lack an understanding of each other's work. What would have
most likely caused this communication breakdown?
A project manager is working on a product development project. When the product is delivered, there are major issues that require rework and
delay new feature development.
Which action should the project manager take to resolve the quality issues?
At the end of a workshop to review project deliverables, a number of follow-up action items were generated. What should the project manager do next?
A project manager is assigned to a project with a long timeline and complex scope. The client requires a high-level, long-term plan as well as
something that will work immediately, adding features to the product as the project progresses.
How should the project manager plan and deliver this project?
A project manager manages multiple information technology (IT) projects in a matrix organization. The project manager schedules a meeting with one of the functional
managers to coordinate testing support for two software development projects. Unfortunately, the functional manager is not able to attend the meeting and informs the project manager that there may not be any resources available to test the software.
What should the project manager do?
A project manager has been assigned a project to build a new solar farm that will provide clean energy to a new housing complex. The government has decided to reduce
the tax on renewable energy products starting 1 January. The supplier has reached out and stated that the order placed for solar panels to be delivered on 20 December
might be delayed until early January. On the other hand, the project will face similar constraints due to the December holidays.
What should the project manager do about this risk?
One of the key stakeholders on the project team reaches out with an additional requirement that may impact the overall schedule. A discussion with another stakeholder suggests thai this might just be a small task.
What should the project manager do?
A key team member informs the project manager that they have been accepted to a master’s degree program. The team member explains that the first semester of the master's program will coincide with the last phase of the project.
What should the project manager do?
An organization is transitioning to an agile approach. At the project's first sprint review, the product owner did not accept the result of the sprint and has some concerns.
What should the project manager do?
A project manager is closing a project and preparing to hand it over to the operations team. During handover, a delayed invoice was submitted with a higher-than-planned
cost against the project work. Consequently, project handover was delayed and the project's reported completion costs were increased.
What should the project manager have done to avoid this situation?
A sales manager submitted a new feature request to the product owner, and the request was added to the product backlog. During the sprint planning meeting, the team struggles over which algorithm is the most efficient one to use. The team thinks that some development work is needed to decide.
What should the project manager do?
A project manager has been assigned to a hybrid project. The project manager needs to ensure all team members are collaborating and are aware of the project's ongoing changes.
What should the project manager do?
During a retrospective, one of the team members reports that a functional manager wants to be involved in task allocation. What should the project manager do?
In the middle of the execution phase for a big project a new stakeholder who was unfamiliar with the project joined the board of directors and is influencing the decisions made in the project. This change is impacting the project's progress
What should the project manager do first?
In a highly politicized organizational environment, the stakeholders are driven by their own operational or business goals, which results in
conflicting interests regarding the project. What should the project manager do to steer the stakeholders toward the collective project goal?
A project manager has taken over a project that has been without a project manager for the last couple of weeks. The team is feeling lost and there are a few team
members who are confused about the next steps and the final outcome of the project.
What should the new project manager do?
During the development of a project in a dynamic market environment, new unforeseen legal requirements have come into effect. The project
manager is not sure if some of the project deliverables will be fully compliant with the new requirements.
What should the project manager do?
A project has come to the closing stage. The work is generally finished, and the project manager wants to commence the closure process for the project. What should the project manager ensure is in place prior to the closing process?
A key customer stakeholder asks the project team to include new tasks in the backlog and begin analyzing new requests. The customer expects results as soon as possible and pressures the team to attend noncritical meetings. The team is frustrated by this situation.
How should the project manager approach this situation?
A project manager is assigned to a new project. The project is for a new product that the company wants to launch as soon as possible to test market readiness. The project is part of a large business transformation, and the objective is to open delivery channels for the new product.
Which delivery approach should the project manager recommend?
The project manager's firm is executing a construction project. The project is stalled due to reemerging conflicts and misunderstandings among stakeholders.
What should the project manager do to ensure a smooth start and completion of the project?
A project manager identifies a risk that has a high probability of occurring. How should the project manager manage this risk?
A project manager works in an organization that embraces using different project approaches. The project manager's current project uses a
predictive approach with clear requirements. A few months following the kickoff, the project manager notices that the virtual development teams
are not communicating enough, and coordination is becoming an issue. The teams are not aligned on the tasks being done or the current
impediments.
What should the project manager do?
A project manager is working for an organization in country A and has been tasked with opening the first brick-and-mortar store in country B. The sponsor has identified the city for the store and wants to minimize any potential issues with the local government.
Which action should the project manager take to address the sponsor's request?
The investment committee is the authority for the approval of funding required for a business improvement project. The investment committee approved funding to complete
the preliminary feasibility study. The project is on an expedited schedule, and the project manager requires interim funding to continue with the preliminary feasibility
activities that must commence immediately.
How should the project manager get these funds approved?
A project manager has been authorized to begin a project and realizes that an effective high-performing team is needed to finish the project successfully. What should the project manager do next?
A company is engaged in a transformation journey, and the project manager for this endeavor is new to this project. During one of the project status update meetings, a key stakeholder, the project manager's functional manager, is dissatisfied with the work in progress, and points to the project manager.
What should the project manager do?
A project team is working on a product that is planned for multiple iterations. They are delivering incremental value.
When should the value be demonstrated?
An agile project team received an assignment to develop an industrial system that interfaces with robots. The project team does not have any previous experience
performing this type of work. Team members are interested in acquiring such expertise but it may result in a project delay.
How should this situation be handled?
A project team is struggling to obtain the required data for a complex project in order to proceed to the next stage. What should the project manager do?
A geographically distributed project team working on an iterative project adopts a new mode of communication following changes in health protocols. The colocated team members are finding themselves challenged with understanding verbal communication and collaboration methods.
What should the project manager do?
In an agile project, some stakeholders are asking to have a meeting with the team every 2 weeks in order to understand project progress. What
should the project lead do next?
A project manager was recently assigned to a project that is in the execution phase and is experiencing roadblocks. During a review of the
processes and procedures, the project manager notices similarities to a previous project that experienced similar roadblocks. The project manager
reviews the task schedule and finds that certain tasks are well behind expectations. In speaking with the project team, the project manager
confirms that the team is following the processes exactly.
What should the project manager do?