PMI PMP - Project Management Professional (2025 Version)
In an agile project, the project owner has repeatedly called for ad hoc meetings with team members. What should the project manager do?
A project manager collects various pieces of information and consolidates metrics in an agile project. The project manager finds that there is slack in the team in terms of productivity. The number of items sent to development per person has decreased by 10%, and the project manager used a root cause analysis (RCA) and discovered the reason is a lack of knowledge in one of the frameworks used for modeling.
What should the project manager do next?
A hybrid project has just started, which will result in a new technology that could disrupt the market if well accepted by the public. The product requires health and safety
approvals from the government. As this is an innovative solution, the sponsor and product owner are unsure if it will be accepted by the public.
What is the appropriate flow for product development?
A company has decided to initiate a project to eliminate a sales channel that has been unprofitable for the past 3 years. Some members of the project team are pessimistic about the project.
What should the project manager do in this situation?
A project manager is assigned to an agile project that has an aggressive time line and a fixed budget. Currently, the majority of the items are in the backlog and only a few are in process or completed.
What should the project manager do?
A project manager is overseeing a project as part of a program geared toward a major technology disruption. The team is comprised of brilliant young professionals who have worked on different projects for the organization in the past. However, the team complained that they previously experienced a lack of direction during project execution and are a traid of the same issue in this project.
Which two actions should the project manager take to ensure that this issue does not occur in this project? (Choose two)
A project team is working on a product that is planned for multiple iterations. They are delivering incremental value.
When should the value be demonstrated?
A project manager has recently moved to an organization to lead a key project. The project manager notices that team performance is below the target, and the tasks assigned are not delivered on time. Team commitment is also not as appropriate as it should be.
What should the project manager do?
During the execution of a project to develop a prototype, the customer asks the project manager to stop the prototype line and purge a specific
component based on recent reliability tests that have deemed the component to be deficient. The project manager checked the quality
management plan and there is no reference to this component.
What should the project manager do next?
A project was initiated due to an external business influence. During the course of the project, some of the business parameters considered at the
beginning of the project have changed.
What should the project manager do?
In the planning phase of a software implementation project, two of the team members disagree on how to approach end-user training. The
discussion has intensified and the team members are not able to agree.
What should the project manager do next?
A software delivery project began having technical impediments. The issue may cause a delay of the deliverables. The technical service team has been working on the issue, but the issue is unresolved even after 1 week of maintenance.
What should the senior project manager do now?
A newly commissioned project has had trouble recruiting team members because the turnover rate is high. The human resource (HR) manager
has conducted several exit interviews. Many team members have expressed that the project manager has inadequate relationship management
competencies. The project manager explains that the exiting team members were lazy.
What should the project manager do to prevent this high turnover rate from continuing?
A project manager is assigned to a dental equipment development project that is in the middle of its design phase. After reviewing the project prototype, it is identified that a couple of requirements specifications are missing.
Which action should the project manager take next?
During project execution, one of the project tasks is to create an important document for a service vendor. The project manager assigns a senior engineer to clearly detail
the service instructions to avoid any redo loops. Two days after the service information document was sent, the service vendor has doubts and needs more clarity on the task. This redo loop will probably cause a delay of one or more days.
What should the project manager do next?
An IT company's office is closed abruptly due to a new government restriction. All employees are now working remotely. Project team A has a
critical project delivery due in 2 weeks. The project manager, apprehensive about this sudden change, instantly emails the customer explaining
that the project delivery will be delayed. The customer is unhappy with this and has escalated the issue to senior management.
What should the project manager have done differently?
A project manager receives an email from a customer saying that they do not want to keep working with one of the project team members. The customer does not provide
any reasons for this sentiment. The project manager is concerned because this project team member is highly skilled and experienced and is key in one of the main project deliverables.
What should the project manager do to ease the situation?
A project team is performing extremely well when it comes to delivering the value-added features to the customer in each sprint. However, they are missing the
documentation portion and the project manager must find a way to make sure the documentation is kept current.
Which action should the project manager take?
During the third iteration of a project, the product owner requests another mandatory feature. This also happened in the previous two sprints, which resulted in failure and caused frustration within the team.
What should the project manager do next?
A project team is globally distributed with team members living and working in different time zones. The project manager is trying to get the team
to collaborate effectively.
Which three actions should the project manager take to accomplish this goal? (Choose three)
An iteration is almost finished, but the team is struggling to complete the stories that require more time. What should the project manager do first?
A project sponsor has approved the project charter and business case. The project manager has reviewed the artifacts to initiate the project and is unclear if the intended benefits of the project align with the strategic objectives of the business.
What should the project manager do first?
A customer complains that the user stories released so far contain too much jargon and do not reflect the expectations of the product. What should the project manager do
next?
A project team member informs the project manager that a stakeholder is contacting the team member to request status updates. The team member is being distracted by these repeated requests, which are interfering with the completion of assigned tasks.
What should the project manager do?
A project manager is managing a very important business transformation project. The goal of the project is to extend a desktop application with a mobile application module.
The marketing department believes that a main competitor is working on a similar product.
Which delivery approach should the project manager use for this project?
A project manager is about to slant the testing phase of a new project. Historical data show there is a high risk of failing the agreed acceptance criteria.
How should the project manager ensure the acceptance criteria are ret?
A senior employee with experience relevant to a highly complex project is seeking a promotion to be able to join the project. The employee has made a recommendation regarding the project. The project charter was recently approved.
How should the project manager address the employee's request?
A project manager is assigned to a multiyear enterprise resource planning (ERP) solution project. During planning, the business sponsor emphasizes the importance of demonstrating value along the way, while maintaining the integrity of the final product.
How should the project manager establish the delivery model for this project?
During the last two iterations of a project, one of the team members had low performance. The project manager conducted two feedback sessions with the team member and escalated the issue to the resource manager and project sponsor, but there has been no improvement.
What should the project manager do next?
A junior project manager was recently hired to lead a complex project scheduled to kick off in 2 weeks. The junior project manager was introduced to another project
manager for mentoring.
Which two benefits will the junior project manager realize by being assigned to a mentor? (Choose two)
A project manager has been managing an agile project for 6 months. Over the last two iterations, the team velocity has decreased due to a new technology that was needed
for the product.
What should the project manager do to continue with the delivery plan and return to the expected velocity?
A project manager is managing an agile project that is part of a program with many interconnected projects. Dependency management is fundamental because there will be many milestones for different projects that are dependent upon each other during the program duration.
What should the project manager do?
One of the key stakeholders on the project team reaches out with an additional requirement that may impact the overall schedule. A discussion with another stakeholder suggests thai this might just be a small task.
What should the project manager do?
In the middle of the execution phase for a big project a new stakeholder who was unfamiliar with the project joined the board of directors and is influencing the decisions made in the project. This change is impacting the project's progress
What should the project manager do first?
A project manager is part of a distributed team. The project team is using a product backlog, but due to an excessive workload, the backlog items are not very detailed. In the retrospective, a couple of new team members are raising the issue of knowledge transfer inside the team.
What should the project manager do?
A project manager receives information in preparation for reporting the project's monthly performance to the project steering committee,
* Actual progress = 2 units
* Planned progress = 3 units
* Actual cost (AC) = 2 units
* Budgeted cost = 3 units
What statement should the project manager make to the project steering committee?
When defining the ground rules for a project team, the project manager observed that only two team members contributed to the discussion. As a
result, the team ground rules favor these two team members.
What should the project manager have done to avoid this situation?
A company has created a cross-functional team to drive the digital transformation project for the business. The team is expected to deliver the minimum viable product (MVP) that addresses market need in the shortest possible time.
Match the roles for the team on the left to their corresponding responsibilities on the right.
While managing a project using a hybrid approach, the project manager realizes that there is a high level of rework due to quality issues. Because
of that, each feature is taking longer than initially estimated.
What should the project manager do to address the issue?
A project team was hired to perform on-site duties, but there were unexpected circumstances that required the entire team to work remotely Some team members returned to their hometowns and they are now requesting reimbursement for operational expenditures
What should the project manager do?
The project leader for an agile team has discovered that a certain team member has been struggling with an impediment that is hindering the team's progress. The project is now at risk of completing later than expected.
What should the project leader do?
An innovation project with a budget of over US$30 million is expected to have a large impact on the technology industry. The business area is concerned if the project will meet stakeholder expectations and raised this concern with the project manager.
What should the project manager do to manage business concerns and expectations before starting the project?
A functional manager is concerned that the project's quality management techniques have advanced beyond the department's capabilities and wants the project team to review all quality management activities in two full-day workshops the following week. What should the project manager do next?
A project manager determines that a critical path activity is going to be delayed. The team proposes a fallback plan that could get the project back on track; however, the plan would require an additional cost to an already tight budget.
What should the project manager do?
An agile project to provide a material information system has started. During the kick-off meeting, the team realizes that the stakeholders require a solution in 2 months, but it will take at least 4 months to deliver the entire project.
Who should the project manager contact to help the team accelerate the delivery?
During a project status meeting with senior managers, the project manager gives an update about the status of a deliverable. Some of the senior managers claim not to Know about the deliverable.
What should the project manager do next?
A project manager is assigned to a large construction project with more than 100 project team members. The project manager is having a hard time keeping the project on track and deriving the planned benefits. The project manager wants to make sure that each requirement is linked to the business and project objective.
What should the project manager do?
A project manager is assigned to work on a large global project. The resources for the project are dispersed among different organizations and countries. After the project kick-off meeting, the project manager learns that many virtual team members are unable to join the regular project update meetings. Their absence will impact the overall project schedule.
What immediate corrective action should the project manager take?
In an agile project, the learn planned to complete 40 story points in an iteration, but only completed 30 story points. What is the schedule performance index (SPI)?
During a system demo, a project stakeholder rejects the features completed from the most recent user stories. According to the stakeholder, the product does not meet the
quality standards required by regulations.
What should the project manager have done to avoid this?

