Summer Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: ecus65

PMI PMP - Project Management Professional (2025 Version)

Page: 11 / 12
Total 1988 questions

A new marketing vice president just joined a software startup and is concerned that the agile model does not provide the needed accountability for their role. What should the responsible project manager do to ensure the vice president is comfortable with the project meeting its agreements?

A.

Require proper approval of all requirements from the marketing vice president and formally document the agreements.

B.

Foster an environment of open communication where all parties can discuss issues and agree on objectives.

C.

Establish an executive review board where all stakeholders discuss and approve features and requirements.

D.

Leverage the use of the review/demo sessions with the vice president to acknowledge that the agreements were met.

A software delivery project began having technical impediments. The issue may cause a delay of the deliverables. The technical service team has been working on the issue, but the issue is unresolved even after 1 week of maintenance.

What should the senior project manager do now?

A.

Use interpersonal skills to expedite the issue.

B.

Send a gentle reminder to the technical service team.

C.

Update the issue log with the status and priority.

D.

Issue a formal warning to the technical service team.

A project manager is managing an agile project that is part of a program with many interconnected projects. Dependency management is fundamental because there will be many milestones for different projects that are dependent upon each other during the program duration.

What should the project manager do?

A.

Assign a development team member to have the responsibility of managing dependencies.

B.

Suggest that each project develops a high-level plan to monitor the dependencies

C.

Recommend switching to a predictive approach to have detailed plans to manage the dependencies

D.

Continue the project with 2-week iterations as dependencies will be managed individually

A project team member raised a risk that the threat of country-wide power cuts may affect the project time line for a software development project. In the last month, this risk

materialized and the project time line had to be extended by 2 months.

Which two actions should the project manager take? (Choose two)

A.

Ask the team member to work overtime to make up the time lost so that the project schedule is not impacted.

B.

Analyze the impact of the issue and submit a change request to update the project schedule.

C.

Inform the project sponsor that the risk has materialized and request that the project budget be increased.

D.

Extend the project deadline and update the project schedule to reflect the delay.

E.

Log it in the risk register and work with the relevant owner to implement the mitigation action plan.

A learn member has a sudden emergency that may last for several days. There are no other team members who can cover their tasks and job duties. What should the project manager do to address this concern?

A.

Hold an emergency project team meeting to discuss the situation.

B.

Ask the human resources (HR) manager for an external replacement.

C.

Log the situation in the issue log.

D.

Update the key stakeholders on the issue.

An agile project manager has started working in a company that builds shopping centers. The project manager wants to implement some agile

practices, which are relevant to the project.

What should the project manager do in order to gain buy-in from the different stakeholders?

A.

Organize a meeting with relevant stakeholders explaining the benefits of agile and the practices relevant for the project.

B.

Send the project management plan, which includes the suggested agile practices, to the stakeholders.

C.

Ask the project management office (PMO) to get buy-in from the stakeholders, because agile is an approach that differs from their previous

ways of working.

D.

Organize a meeting with a consultant to provide training to the stakeholders on agile practices.

A multimillion-dollar project has started and is in the execution phase. A local regulatory authority has just announced changes to the requirements that will need to be implemented in 6 months, prior to completing the project execution phase.

What should the project manager do next?

A.

Add the new requirements to the project scope immediately since they are mandatory changes.

B.

Review the new requirements with the compliance department to determine if a change request is needed.

C.

Ignore the new requirements as the current budget and schedule do not allow for any changes.

D.

Proceed with the defined project requirements and delay implementing the new requirements.

A team is using an agile approach to maintain the project backlog. A new project obstacle was identified as a blocker and added to the backlog list. The team is facing challenges to remove this obstacle

What should the project manager do next?

A.

Escalate the obstacle to a servant leader for resolution.

B.

Ignore the obstacle and present the partial solution to the customer

C.

Focus on generating business value despite the obstacle

D.

Make changes to reprioritize the backlog because of the obstacle.

A project sponsor is concerned that the scope is not being met correctly and has questioned several team members about this individually. When the project sponsor approached the project manager, the project manager realized that the issue was that the project sponsor understood the scope in a different manner than the project team.

What should the project manager do to address this issue?

A.

Request that the project team change their task deliverables to reflect the project sponsor's requirements.

B.

Set up a daily standup and request that the project sponsor attend to understand the project's tasks and deliverables.

C.

Ask the project team to compile a project scope document and obtain approval from the project sponsor.

D.

Facilitate a stakeholder alignment session so that the team and project sponsor are in agreement with the deliverables.

A CEO of a general contracting company urgently asks the project manager to sign up two project team members to participate in a specific training course. Halfway

through the training, both team members complain that the training is too difficult, above their experience level, and that the material does not align with their tasks.

What should the project manager have done to prevent this situation?

A.

Communicated with the two team members that the purpose of the training is to provide material that might be useful to them in the future

B.

Sent an immediate request to the human resources (HR) department to replace the current team members with higher skilled candidates

C.

Observed and assessed the competencies and skills of the team members and analyzed the training material beforehand

D.

Planned a training to follow the specific course to bring the two team members to the required experience level

A few new team members working on a public housing project are unfamiliar with the system. They do not understand how to evaluate residents applying for a subsidy to build a house, including the rules and criteria for applicant approval.

What should the project manager do?

A.

Plan a training session for the new team members not familiar with the system.

B.

Communicate the rules and criteria to the team members through email.

C.

Work only with the team members familiar with the system

D.

Document which rules and criteria the new team members are not familiar wit

A project team is globally distributed with team members living and working in different time zones. The project manager is trying to get the team

to collaborate effectively.

Which three actions should the project manager take to accomplish this goal? (Choose three)

A.

Require the team to have daily mandatory meetings with the project management office (PMO).

B.

Recommend the use of formal written documentation in all project communications.

C.

Review the communications strategy with the team regularly with a view for continuous improvement.

D.

Send out a survey to review the preferred method, time frequency for communications.

E.

Compile a communications management plan with input from all stakeholders and distribute for review and approval.

During the last iteration of a hybrid project, one of the key members of the team wants to leave the project. What should the project manager do to address this concern?

A.

Keep activities as planned regardless of the resource change.

B.

Update the burndown chart to reflect this resource's absence.

C.

Have a meeting with the resource to understand the issue.

D.

Request an additional resource to finish the project.

An important project to build a new airport was suddenly stopped because of complaints from residents in the surrounding communities. The residents stated they were not consulted and that the project would cause ecological and pollution damage.

What should the project manager have done first to avoid this situation?

A.

Identified the stakeholders and their expectations

B.

Presented the project to the community

C.

Added this situation to the risk register

D.

Added these requests to the project scope statement

A team member has very strong technical skills and is interested in a leadership role. A leadership position opens up outside of the team in the organization. The project manager has observed that the team member has a major gap in communicating in a professional manner.

What should the project manager do?

A.

Suggest the team member focus on positions with technical aspects and possible technical career opportunities.

B.

Recommend the team member for effective communication training and support their career development interests.

C.

Encourage the team member to stay in their current role as they are important to the project.

D.

Ask the team member to refrain from pursuing new opportunities as they are not a suitable fit for a leadership position.

A project manager is leading a project that is at 90% completion. One of the key stakeholders requests a certification program to be included as part of the project. Another stakeholder disagrees and informs the project team that there should be no change to the project management plan since the project is nearing completion.

What should the project manager do?

A.

Update the project management plan and adjust the project budget with this change request.

B.

Raise a change request to the change control board (CCB) and inform the project sponsor about the change.

C.

Ask the key stakeholder to take the lead in handling the request since they are more knowledgeable.

D.

Request a meeting with the stakeholders and their team members to inform them about this change.

A team is working on a project with three iterations. The project manager is reviewing the burndown chart What is the point where the chart shows that the team is performing below the plan?

An iteration is almost finished, but the team is struggling to complete the stories that require more time. What should the project manager do first?

A.

Meet with the project team to develop a proper resolution to the issue.

B.

Update the project artifacts to reflect the new deadlines reported.

C.

Request approval from the project sponsor to add more resources,

D.

Prepare documentation to explain the issue and communicate accordingly.

During project planning, a development team is assigned an agreed-upon work package to determine the appropriate pattern for integrating a new service with a legacy system. The lead developer has requested a meeting with the project manager and Is looking for direction as to which technology to select.

How should the project manager help guide the lead developer?

A.

Advise the lead developer and team to consult with the project architect and for their development team leader.

B.

Reassign this work package to another area given the lead developer's concerns,

C.

Direct the lead developer to conduct a weighted evaluation of all products and solutions.

D.

Listen to the concerns and suggest that the lead developer and the team be empowered to recommend the best approach.

A project manager in an automotive company is scheduling activities for a complex project Some of the project requirements are fixed and some are flexible Match the items on the left with the methodology on the right that the project manager is using.

A project team member wants to select specific challenging tasks in the subsequent iteration. How can the project lead help the team member in the next iteration?

A.

Assign the challenging tasks to the team member.

B.

Ask the product owner to assign the challenging tasks.

C.

Reprioritize the challenging tasks to future sprints.

D.

Coach the team member to pick up the challenging tasks.

A project manager has been assigned to a project where the budget is very tight. Incurring extra costs is not an option.

What should the project manager do to manage this situation?

A.

File a change request to make the customer billable for all extra costs incurred for the project.

B.

Ask the accounting department to forward all project expenses to the project manager's email.

C.

Monitor the budget for the project continually and anticipate any issues if possible.

D.

Ask the project resources to finish their assignments in less time than originally planned.

A proof of concept for a proposed solution was conducted during the project implementation, and it was determined that the current technology cannot support it. What should the project manager do next?

A.

Ask another team member to redo the proof of concept using the current technology to ensure It is truly not an option.

B.

Use a root cause analysis (RCA) technique like Ishikawa diagrams to determine why the current technology is not supportive.

C.

Add this item to the issue log and explore possible resolution options with the team.

D.

Update the risk register indicating that a new technology must be chosen by the team lead.

A project manager has been assigned to an important project that will help set the future of the company. Meanwhile, the project management office (PMO) is implementing

adaptive tools in a mostly predictive environment and has requested that the project manager follow this process as well. However, the functional manager has expressed concerns about the use of new tools on such an important project.

What should the project manager do?

A.

Review the adaptive tools' impact and obtain agreement from the functional manager.

B.

Follow the functional manager's recommendation to implement only predictive tools in the project.

C.

Make the decision on which project approach to use that would best fit the project.

D.

Follow the project management office's (PMOs) request to implement the adaptive tools in the project.

During the development phase, a team member encounters an issue with a specific task and attempts to resolve it for the next several days. The other team members ask

the project manager to reassign the task to another team member to avoid jeopardizing the target date. The current team member assigned communicates they will feel frustrated if the task is reassigned to another team member.

How should the project manager address this situation?

A.

Seek help from experts to support the team member in fixing the problem.

B.

Facilitate a session to reach an agreement with the team as a whole.

C.

Negotiate with the customer a delay in the project delivery.

D.

Accept the team's request to reassign the team member.

A junior project manager was recently hired to lead a complex project scheduled to kick off in 2 weeks. The junior project manager was introduced to another project

manager for mentoring.

Which two benefits will the junior project manager realize by being assigned to a mentor? (Choose two)

A.

The junior project manager reports administratively to their mentor so that human resource (HR) questions can be answered quickly.

B.

The junior project manager can discuss certain problems with their mentor without fear of retribution.

C.

The mentor will be immediately available to take over the project if there are problems or project delays.

D.

The mentor will be involved in the decision-making processes implemented by the junior project manager.

E.

The mentor can provide past project documentation with early warning indicators that potential problems could occur.

An agile team completes a deliverable that is to be certified by another expert team. The second team does not take the deliverable for many months.

What should the servant leader do?

A.

Escalate this to the project director for a resolution.

B.

Escalate this to the agile lead of the second team.

C.

Review the process and remove the impediment.

D.

Remove the certification need from the project scope.

While managing a project using a hybrid approach, the project manager realizes that there is a high level of rework due to quality issues. Because

of that, each feature is taking longer than initially estimated.

What should the project manager do to address the issue?

A.

Escalate the issue to the project sponsor.

B.

Address the issue during the next sprint planning meeting.

C.

Initiate a change request to extend the project end date.

D.

Extend the dates for future project milestones.

A project manager is leading an agile team. The daily standups and iteration meetings are currently facilitated by the product owner. A team member contacts the project manager and mentions that they are looking to improve their facilitation skills.

How should the project manager respond to this request?

A.

Ask the team member to review the lessons learned on facilitation from previous projects.

B.

Suggest that the team member facilitate an upcoming iteration and review the outcomes in the iteration retrospective.

C.

Engage their functional manager to determine if there is alignment to their development plan before agreeing.

D.

Add new elements to the project backlog to account for the training needs of the team member.

A newly assigned project manager is reviewing the project management plan and realizes that the project is running behind schedule. What should the new project manager

do to address this situation?

A.

Modify the project management plan and get approval from relevant stakeholders

B.

Add more resources to recover the schedule without making changes to the baseline.

C.

Issue a change order to the change control board (CCB) and rebaseline the schedule.

D.

Negotiate with the project sponsor immediately and establish a new project charter.

A hybrid project has just started, which will result in a new technology that could disrupt the market if well accepted by the public. The product requires health and safety

approvals from the government. As this is an innovative solution, the sponsor and product owner are unsure if it will be accepted by the public.

What is the appropriate flow for product development?

A.

Complete development with all functionalities in perfect condition prior to demonstrating to stakeholders to ensure a great first impression.

B.

Complete development for each sprint and demonstrate the product increment to internal stakeholders and the government, without engaging other external

stakeholders.

C.

Complete development for the must-have functionalities only prior to demonstration in order to fail fast and get early feedback.

D.

Complete development for must-have functionalities only and demonstrate it to a focus group, but wait until all development is complete to demonstrate it to the

government.

An insurance company is planning to make a big change to its core application. The project manager realizes there is resistance to change from the sales agents since they

are accustomed to taking orders manually and entering them in the system at the end of the day. With the new change, they will use point-of-sale devices to take orders online.

What should the project manager do to get commitment from the sales agents?

A.

Use a business case to model a sales pitch and gain consensus from the sponsors.

B.

Request help from the project sponsor to get support from the sales agents.

C.

Escalate the issue to senior management to gain team buy-in

D.

Explain the change benefits to the sales agents' manager to get their support.

A project manager is managing a new development program to automate some technical functions. During project kickoff, the project manager

expresses the need for a technical architect to support the project for a moderate amount of time. The project sponsor informs the project

manager about an existing technical architect who possesses valuable knowledge but is already assigned at the portfolio level.

What engagement model should the project manager use for the technical architect role to ensure project success?

A.

Hire a new technical architect who would be solely dedicated to the current project.

B.

Share the existing technical architect so they can be allocated to the current project and other projects.

C.

Hire a new technical architect who would be shared between the current project and other projects.

D.

Assign the existing technical architect to solely be dedicated to the current project.

A project manager is working in a company that has several global offices. During resource planning for a new project, the project manager realizes that the company requires projects to include team members from different continents.

What should the project manager do to ensure a successful project execution?

A.

invite all resources to the project manager's location to form a cohesive team until all deliverables are completed,

B.

Send emails with information about the project deliverables on the first day of the project.

C.

Connect with every location and check their preferred methods of communication.

D.

Plan for a meeting with the project sponsor to discuss the possibility of utilizing only local colleagues.

A complex project is in the execution phase. A key stakeholder who is new to the project has not been approving project deliverables, which could impact the overall

progress.

What should the project manager do next?

A.

Capture this in the issue log and escalate it to the project sponsor.

B.

Meet with the stakeholder to understand what is causing the delays.

C.

Facilitate a brainstorming session to find potential workarounds.

D.

Discuss the need to influence this stakeholder with the sponsor.

A project manager receives information in preparation for reporting the project's monthly performance to the project steering committee,

* Actual progress = 2 units

* Planned progress = 3 units

* Actual cost (AC) = 2 units

* Budgeted cost = 3 units

What statement should the project manager make to the project steering committee?

A.

The project is currently behind schedule with a corresponding lower cost, and every effort is being made to expedite the delayed activities.

B.

The project is currently behind schedule with a corresponding cost savings, and no further actions should be taken.

C.

The project is currently behind schedule but at a lower cost, and an application for a time and budget extension will be submitted.

D.

The project is currently behind schedule but is under the planned expenditure, and the project manager is pleased to declare a project cost savings,

A project manage is in the middle of an angle project comprised of 100 user stories broken down into five iterations. Each user story is worth U$$50. The actual expenditure is U$$2,00 and 50 user stories have been delivered.

Which statement is true?

A.

The project is over budget and behind schedule.

B.

The project is under budget and on schedule.

C.

The project is under budget and behind schedule.

D.

The project is on budget and on schedule.

A project manager is in the middle of handling a major upgrade to an existing product. The project manager learns that the resources initially promised as part of the project are being moved to another priority project.

What should the project manager do?

A.

Retrieve the documentation that shows the resource allocation.

B.

Examine ways of modifying the scope of the project.

C.

Adopt a resource leveling procedure to level the resources.

D.

Perform an impact analysis to see the effect on the project.

A project manager is assigned to a new project team that has several stakeholders who can have significant influence over the project outcomes.

The project manager categorized the stakeholders into four different groups and wants to define the communication strategy.

How should the project manager handle communication?

A.

Utilize a uniform communication structure across all groups.

B.

Define and direct communication to influential stakeholders.

C.

Describe the four groups in the project stakeholder matrix.

D.

Develop and define a communication strategy for stakeholders.

A major issue about conflicting priorities has been highlighted by the project team with regard to a few stakeholder requirements. What should the project manager do?

A.

Prioritize other items for the team and deal with the conflicting requirements later.

B.

Allow the project team to decide what is the most appropriate requirement to follow.

C.

Escalate to the project management office (PMO) and request a solution for the requirements.

D.

Negotiate a common agreement with the involved stakeholders regarding the requirements.

One of the team members is always late to the daily standup meeting. What should the project manager do?

A.

Schedule the meeting at the end of the day to accommodate everyone.

B.

Ignore the situation since the team member is accomplishing their deliverables.

C.

Reinforce the ground rules for standup meetings with the entire team.

D.

Speak with the team member directly to reinforce the ground rules.

A project manager is nearing completion of an automation project. One of the key stakeholders requests a meeting to discuss some new ideas that would make the project even more appealing to end users. As a result, the stakeholder suggests that the project manager does not close the project.

What should the project manager do first?

A.

Update the project charter with the new requirement.

B.

Add a risk to the risk register.

C.

Add it to the issue log as an ongoing issue.

D.

Review and validate the scope management plan.

In an agile project, the learn planned to complete 40 story points in an iteration, but only completed 30 story points. What is the schedule performance index (SPI)?

A.

30/40

B.

40/70

C.

30/70

D.

40/30

A project team member does not submit the project status report on time. The team member is frustrated about being required to complete the report. The team member believes that the report does not reflect the reality of the project, has too many pages, and will not be read by stakeholders.

What should the project manager do?

A.

Review the requirements of the report with the team member to redefine its purpose.

B.

Escalate to the team member's functional manager that the report was not submitted as requested.

C.

Instruct the team member to provide the report and document this in the performance review.

D.

Reassign the report to another team member to prepare and submit it as requested.

A project team began working on a complex project that involves new technology as a product. The team is new to the technology and the proposed approach. Additionally, the customer is apprehensive about how the product will be received in the market.

What should the project manager do to help the team and the customer?

A.

Manage the risks associated with the proposed approach.

B.

Assist the team with identifying the minimum viable product (MVP) to validate assumptions.

C.

Coordinate with the business unit to get detailed requirements.

D.

Work closely with the marketing team on market research and product segments

A project manager just completed the planning phase when a new stakeholder was assigned to the project. The deliverables were discussed with the customer, but the new stakeholder is still concerned about the benefits of two of the deliverables.

What should the project manager do next to address this stakeholder’s concerns?

A.

Review the benefits realization plan with the stakeholder.

B.

Provide the stakeholder with regular updates on project progress.

C.

Add the stakeholder to the stakeholder engagement plan.

D.

Review the prior analysis results with the stakeholder.

A project manager is working directly with a vice president who is also the project sponsor. The project is an organizational transformation for a company that primarily works on predictive projects. The project manager has been asked to use a hybrid approach to deliver before a defined date by using sprints.

What should the project manager do first?

A.

Formalize the product owner assignment.

B.

Review similar projects in the company.

C.

Set the project's purpose, mission, and vision.

D.

Carry out the product backlog creation.

A sponsor and project manager found out that a vendor in a different time zone has delayed the delivery of its products and needs close supervision until the project gets back on track. The only option is to relocate three key members of the project team to spend 6 months abroad

What should the project manager do next?

A.

Communicate to the whole team the decision to relocate team members abroad and the implications of doing so in the next project status meeting

B.

Communicate individually with the affected team members to negotiate the decision and confirm their willingness to relocate

C.

Communicate the decision to the human resources (HR) department so they can direct the project team members to be sent abroad

D.

Communicate to the affected team members' manager and schedule a meeting to discuss the details of this assignment

A key project team member has exhibited high interest in a project. The input from

this person has been very useful, and the project is steadily progressing. Suddenly, this individual's participation decreases, and activities that they were responsible for are not being completed within the planned period.

What should the project manager do?

A.

Reallocate tasks for the team member of concern so that work is handled by another team member.

B.

Schedule a meeting to discuss recent observations with the team member.

C.

Organize a team-building session with all of the team members.

D.

Consult the resource allocation matrix to see if the team member is still required for the

project.

A project manager is leading a major water pipeline project and realizes midway into

the project that the project completion date is not achievable. Local farmers who rely on the

water for irrigation may be affected due to the delay. The project manager is afraid of their

displeasure and reaction, which will affect the project.

How should the project manager plan the communication to the stakeholders?

A.

Document and accept this risk and communicate this decision to the project sponsor.

B.

Collect feedback from the farmers and keep the information within the project team.

C.

Deliver the information to the stakeholders with the project management office's (PMO)

assistance.

D.

Propose a solution to the stakeholders and communicate it to the local farmers.