PMI PMP - Project Management Professional (2025 Version)
A building management system (BMS) project is in its commissioning phase and handover to the operations team will commence soon. However, the project manager noted
that both the project and operation teams are not able to properly operate the BMS. As a result, there is an increased risk of the project schedule being delayed.
What should the project manager have done to avoid this situation?
A project to support an organizational transformation is in the planning phase. Transformation is the project sponsor's idea and is not aligned with key stakeholders because they all have different opinions about the project outcomes.
What should the project manager do next?
A project manager is reviewing a draft of the project charter with key stakeholders. During the meeting, a conflict occurs between the sponsor and the product owner.
How should the project manager deal with the situation?
A key stakeholder who is highly involved in the project claims that the reports sent by the project team are inadequate. What should the project manager do first?
A project manager has been assigned to lead a software project to generate savings at an important financial institution. Initially, the duration of the project was 13 months,
but due to various issues during execution, the project was extended to 16 months. By month 11, the expected savings were exceeded but not all of the functionalities
planned for that date were fulfilled.
How should the project manager inform the stakeholders of the project's progress?
A project manager is managing a project with team members who are working all over the globe. The project manager notices that each team
member's deliverables do not meet the requirements.
What should the project manager do first?
A vice president has asked a project manager to support a new urgent project and has informed team members that the project will start soon. The CEO of the company has not yet approved the project to start. The vice president is concerned that the project will not be approved by the CEO on time.
What should the project manager do next?
A project manager has been assigned to lead an IT project to store information on sold lottery tickets. During the project execution, a failure in the
system caused 10 numbers to be sold two times. This happened during the month of greatest demand because the prize was the highest of the
year. The project team is concerned that one of those tickets could be the winner.
What should the project manager do first?
A project has obtained all of the necessary legal requirements and policies from the local government. During the execution phase, the product owner is informed that a new law impacting the project deliverables will be published within two weeks.
What should the project lead do?
A team is focusing on quickly developing and shipping new product features due to very aggressive market demands. The team is setting aside long-term work not directly related to the current business objective, which affects product performance and generates more customer support requests.
How can the team minimize the impact of the reduced focus on quality?
A project with a hard timeline is starting its first iteration out of six. The project team is lacking the necessary skills to execute.
What should the project manager do?
A project manager finds it challenging to comply with standardized processes for knowledge transfer. The project teams and stakeholders are scattered around field sites,
the office, and remote locations. In addition, some team members have limited access to the electronically shared files.
How should the project manager manage this challenge?
An agile project has a broad set of product features intended for different user profiles and usages. It is difficult to define common acceptance criteria that can apply to all the features.
How can the project manager ensure that the appropriate acceptance criteria are applied to the features?
A project manager is leading an integration project for a retail company. The project demands a lot of time from the stakeholders to make important business decisions. The project is critical and must be completed on time and within budget.
What should the project manager do to ensure that key stakeholders are available for this project?
An organization's human resources (HR) department wants to create a high-performing team and implement a project that includes job grading, organizational restructuring, and soft skills training.
To ensure the quality of the project deliverable, which three actions should the project manager take? (Choose 3)
An IT team has reached out to the project manager for guidance on which communication method to use when system downtime will impact the resources working on the project.
Which two communication methods should the project manager recommend? (Choose 2)
A senior project manager has included a junior project manager as part of the project team. During a coaching session, the junior project manager
asks the senior project manager how to be efficient and reduce rework.
How should the senior project manager respond?
A hybrid project has just deployed, and the project manager is planning project closure with lessons learned workshops. A key stakeholder informs the project manager that having the Scrum team in the workshops is a waste of time because the project was delivered successfully.
What should the project manager do?
A project manager leads a software development project in a hybrid environment. During project planning, the project manager identified a risk where a technical resource for a critical path item may not be available when needed. One week before the resource is needed, the technical engineer had a personal emergency and had to take a leave.
What should the project manager do next?
During user acceptance testing (UAT), a manager declined a core application functionality that was originally requested by a subject matter expert (SME). Due to the manager's influence, the project team is concerned about the overall impact to the project.
What should the project manager have done?
An organization that embraced agile a couple of years ago is looking for a more efficient way to ensure that the increments produced in each sprint meet the end users’ quality requirements. What should the project lead recommend?
A sales director is upset that progress has been slow on the delivery of critical features to the customer. After consulting with the team, the project manager learns that a subject matter expert (SME) on the customer side is not cooperative in providing the input needed to complete the definition of ready (DoR).
What should the project manager do to avoid the same problem in future projects?
A project is starting its first iteration out of six. During one of the daily meetings, the project manager realized that one of the team members does not have experience working in agile environments.
What should the project manager do?
A project manager is managing a project in a fast-paced environment. The project manager needs to empower the team to collaborate toward an expected outcome and enable high-team performance. The CEO has suggested that the project manager apply a servant leadership style.
What should the project manager do to demonstrate the capabilities of a servant leader?
A project manager and project team are developing a strategic approach to engage the internal and external stakeholders. Which approach should be followed?
A Scrum team has information radiators but must also keep stakeholders aware of their progress. In addition, the project management office (PMO) has specific templates for status reporting to management. The project lead realizes that a variety of reporting will be needed to satisfy enterprise and stakeholder needs.
What should the project lead do?
A customer requests additional changes 1 day before the planned change date. How should the project manager respond to the change request?
A project is ready to deliver the first batch of the product when a quality control check rejects the product as unfit for delivery. The root cause
analysis (RCA) shows that a component added as part of the latest change request was not tested throughout the development cycle.
What should the project manager do next?
During a sprint planning, the development lead highlights the importance of working on technical debt tasks that are critical for the product performance. However, the tasks will consume most of the team's capacity and they will not be able to work on product feature development.
What should the project manager do?
A project manager is using an agile approach. During the sprint planning meeting, the product owner flagged a backlog item as high business value and easy to implement. However, the other team members identified a high dependency between this item and another item that is flagged as low business value and high complexity.
What should the project manager do to support the backlog prioritization?
A facility extension project is in the execution stage. There is a project activity to connect the power of all new equipment to an existing facility,
Point A, which requires a significant cable length. The construction team found that the power could be connected to Point B and save money.
What should the project manager do next?
A subject matter expert (SME) external to the project team provides a suggestion that will save the project delivery time. This SME has available
time to support the project, but was not planned to be involved in the current agile iteration.
What should the project manager do?
While a project manager is trying to build the first baseline for a project, a change request is being sent from one of the functional managers. What should the project manager do?
A project manager decided to use a highly adaptive approach to manage a large-scale project. In this project, there are many iterative tasks that utilize highly specialized experts. The project manager would like to create practical plans with high levels of buy-in from the team members.
What should the project manager do next?
A project team member just informed the project manager that the license for the software that the team uses to perform calculations has just expired. As a result, the team cannot continue with their project tasks.
What should the project manager do first?
A high-performing team is involved in a project with a new domain. The team is unable to deliver as expected.
What should the project manager do?
Following an investment decision-making meeting for a project, a change to the organizational structure takes place in a multinational company. Due to the organizational change, internal stakeholders are referring the project manager to various other personnel for approval of the project budget.
What should the project manager do to obtain approval of the project budget?
A new project needs to be submitted for urgent funding approval. The project, which will use a new technology, is vital to the organization. The entire Scrum team has worked together for over 3 years on multiple projects and delivered the previous project under the approved budget.
Which estimation technique should the project manager implement in this context?
A project management office (PMO) is currently stretched for project control resources. Specifically, the cost control resources are short of the staff required for this activity level. A new project is about to start soon.
What should the project lead do to obtain the needed resources?
A project manager who has been working on an ongoing volatile project is retiring. A new project manager is collaborating with the retiring project manager to ensure a smooth transition.
What should the new project manager first discuss, review, and clarify during the transition meetings?
An unforeseen event has shut down public works projects for 4 weeks. Activities on the critical path will fall behind based on the project schedule.
What should the project manager do?
After the merger of two large companies, a project manager is assigned to a project. The company hires a consultant to ensure best practices are
being used in information security. During an iteration, the consultant requests changes to a software component, claiming that it is not meeting
market requirements.
What should the project manager do?
A stakeholder informs the project manager about a few compliance-related gaps and issues. The stakeholder then presents several suggestions to the project manager to address the issues.
What should the project manager do?
During a regular project progress meeting, the CEO informed the project manager that a major stakeholder has been unaware of recent developments on the project. The
project manager is sure that the stakeholder was duly identified and classified in the stakeholder register.
Which project document should the project manager review in order to determine the reason for this issue?
A company has appointed a supplier to deliver software and has assigned an internal project manager. The supplier states that no technical development or testing is required from the customer. The project manager would like to confirm this with all of the stakeholders.
What should the internal project manager do first?
An enthusiastic, newly hired vice-president has been assigned as the product owner for a digital transformation project. The project manager
advises the product owner that some of the functional requirements are not aligned with the chief information technology officer's (CTO) strategy.
The product owner tells the project manager that the CTO is not part of the project and should not be engaged at this moment.
What should the project manager do?
A project manager's project relies on services from a department that has a new leader. Since the new leader was appointed, the services from their department have been slow which threatens the project's delivery deadline.
What should the project manager do?
A key team member has recently gone through some personal issues that has affected their performance. The project manager noticed that the
team member's emotional situation has affected the rest of the team's performance.
How should the project manager handle this situation?
Before kicking off a high-priority and complex project, what should the project manager do to ensure all project stakeholders are aware of their role scope as it relates to project activities?
A project team has installed software for the client, passed the knowledge to operations, sent the final report, and celebrated. Then 1 week later,
the client sendsa list of requirements that have not been met. The client is requesting to fix the issues quickly and within the initial budget.
What should the project manager have done to prevent this from happening?