Summer Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: ecus65

PMI PMP - Project Management Professional (2025 Version)

Page: 9 / 12
Total 1988 questions

A building management system (BMS) project is in its commissioning phase and handover to the operations team will commence soon. However, the project manager noted

that both the project and operation teams are not able to properly operate the BMS. As a result, there is an increased risk of the project schedule being delayed.

What should the project manager have done to avoid this situation?

A.

Allocated a dedicated handover team at early stages of the project

B.

Allocated proper resources for training on BMS in the project plan

C.

Made some adjustments to BMS to be more suitable for the teams

D.

Brought both teams together in a joint meeting to resolve the issue

A project to support an organizational transformation is in the planning phase. Transformation is the project sponsor's idea and is not aligned with key stakeholders because they all have different opinions about the project outcomes.

What should the project manager do next?

A.

Ask the project sponsor to help with engagement of the key stakeholders.

B.

Communicate project outcomes and results with the key stakeholders.

C.

Define a high-level project scope and share it with the key stakeholders.

D.

Conduct a workshop on project goals and deliverables with the key stakeholders.

A project manager is reviewing a draft of the project charter with key stakeholders. During the meeting, a conflict occurs between the sponsor and the product owner.

How should the project manager deal with the situation?

A.

Postpone the meeting and invite a subject matter expert (SME) to join the next meeting.

B.

Continue the meeting and ask the project sponsor and product owner to take their discussion offline.

C.

Postpone the meeting and ask the project sponsor and product owner to take their discussion offline.

D.

Continue the meeting and use facilitation techniques to improve communication within the team.

A key stakeholder who is highly involved in the project claims that the reports sent by the project team are inadequate. What should the project manager do first?

A.

Ask the project team to review and modify all of these reports.

B.

Ask the sponsor to meet with the stakeholder to diffuse the situation with the reports.

C.

Explain to the stakeholder that these are the approved templates for the reports.

D.

Ensure that the reports comply with the communications management plan.

A project manager has been assigned to lead a software project to generate savings at an important financial institution. Initially, the duration of the project was 13 months,

but due to various issues during execution, the project was extended to 16 months. By month 11, the expected savings were exceeded but not all of the functionalities

planned for that date were fulfilled.

How should the project manager inform the stakeholders of the project's progress?

A.

Report that the project has not fulfilled all the expected functionalities.

B.

Complete the outstanding functionalities before informing the sponsor of the project progress.

C.

Communicate the benefit expectations and the action plan for the pending functionalities.

D.

Send an email with the monthly project progress to all relevant stakeholders.

A project manager is managing a project with team members who are working all over the globe. The project manager notices that each team

member's deliverables do not meet the requirements.

What should the project manager do first?

A.

Assemble the project team via conference call to tell them that disciplinary action will be taken if any more noncompliant deliverables are

submitted.

B.

Discuss the process used to create the noncompliant deliverables with the project team to see if there was a potential misunderstanding.

C.

Schedule time with the project sponsor to inform them that the project schedule is slipping due to the time it will take to rework the

deliverables.

D.

Meet with the project team to explain that noncompliant deliverables must be reworked and submitted immediately to avoid project delays.

A vice president has asked a project manager to support a new urgent project and has informed team members that the project will start soon. The CEO of the company has not yet approved the project to start. The vice president is concerned that the project will not be approved by the CEO on time.

What should the project manager do next?

A.

Ask the vice president to approve the project charter to kick off the project

B.

Ask the vice president to define who will be the product owner for the project

C.

Investigate if the value and benefits of the project are identified

D.

Start working on the project immediately and determine the scope later

A project manager has been assigned to lead an IT project to store information on sold lottery tickets. During the project execution, a failure in the

system caused 10 numbers to be sold two times. This happened during the month of greatest demand because the prize was the highest of the

year. The project team is concerned that one of those tickets could be the winner.

What should the project manager do first?

A.

Reassure the sponsor by explaining the probability of this risk materializing is extremely low.

B.

Carry out tests to verify that the system does not fail again due to the high occurrence of events.

C.

Review the list of risks to verify that this issue was considered and execute the detailed action plan.

D.

Inform the sponsor about the issue and make a request for sufficient funds to be made available.

A project has obtained all of the necessary legal requirements and policies from the local government. During the execution phase, the product owner is informed that a new law impacting the project deliverables will be published within two weeks.

What should the project lead do?

A.

Review the product backlog items to evaluate the impact on scope and prioritize accordingly.

B.

Develop a change request for more resources and update the project budget and schedule.

C.

Ask the internal legal department to evaluate if the regulatory law could be managed internally.

D.

Work with the team to develop an alternative solution with no additional effect on the project's budget.

A team is focusing on quickly developing and shipping new product features due to very aggressive market demands. The team is setting aside long-term work not directly related to the current business objective, which affects product performance and generates more customer support requests.

How can the team minimize the impact of the reduced focus on quality?

A.

Adapt the management plan to reduce the quality constraints.

B.

Reduce complexity to focus on the minimum viable product (MVP).

C.

Consider implementing test-driven methodology.

D.

Work on the technical debt at a later stage in the project.

A project with a hard timeline is starting its first iteration out of six. The project team is lacking the necessary skills to execute.

What should the project manager do?

A.

Allow the team to proceed as they attempt to meet the timeline.

B.

Add a subject matter expert (SME) to the project team.

C.

Invite stakeholders to discuss a mitigation plan to finish on time.

D.

Fill the skill gap personally to execute the project.

A project manager finds it challenging to comply with standardized processes for knowledge transfer. The project teams and stakeholders are scattered around field sites,

the office, and remote locations. In addition, some team members have limited access to the electronically shared files.

How should the project manager manage this challenge?

A.

Request changes in the processes since it is not suitable for the company environment.

B.

Communicate a strong message to the team explaining the importance of knowledge transfer.

C.

Study the environment and the available resources to determine which approach to use.

D.

Send the intended information through email since it is the primary communication tool.

An agile project has a broad set of product features intended for different user profiles and usages. It is difficult to define common acceptance criteria that can apply to all the features.

How can the project manager ensure that the appropriate acceptance criteria are applied to the features?

A.

Define the acceptance criteria and specific functional test cases only after analyzing the user feedback from testing the early feature release.

B.

Integrate the acceptance criteria review into the definition of ready (DoR) for each feature and associated tests into the feature's definition of done (DoD).

C.

Use the broadest set of acceptance criteria to ensure that all features have a common quality baseline and associated functional test cases.

D.

Integrate the specific tests into the definition of ready (DoR) for each feature and the acceptance criteria into the feature's definition of done (DoD).

A project manager is leading an integration project for a retail company. The project demands a lot of time from the stakeholders to make important business decisions. The project is critical and must be completed on time and within budget.

What should the project manager do to ensure that key stakeholders are available for this project?

A.

Add time reserve in the project schedule to allow extra time for the stakeholders to make decisions.

B.

Share the project schedule, milestones, and meeting agendas with the stakeholders ahead of time.

C.

Work with the available stakeholders to make business decisions and keep all unavailable stakeholders informed.

D.

Schedule meetings with all of the stakeholders to make business decisions when needed.

An organization's human resources (HR) department wants to create a high-performing team and implement a project that includes job grading, organizational restructuring, and soft skills training.

To ensure the quality of the project deliverable, which three actions should the project manager take? (Choose 3)

A.

Collect feedback and conduct surveys and questionnaires.

B.

Hire a certified expert to lead the project quality process.

C.

Document quality gaps and analyze them for continuous improvement.

D.

Develop a proper quality management plan with measurable metrics.

E.

Apply an existing external framework for performance improvement.

An IT team has reached out to the project manager for guidance on which communication method to use when system downtime will impact the resources working on the project.

Which two communication methods should the project manager recommend? (Choose 2)

A.

Communicate via email to the project's email distribution group.

B.

Communicate via instant messaging.

C.

Communicate via the project team's document management site.

D.

Communicate in the IT risk forum.

E.

Communicate verbally to the key project stakeholders.

A senior project manager has included a junior project manager as part of the project team. During a coaching session, the junior project manager

asks the senior project manager how to be efficient and reduce rework.

How should the senior project manager respond?

A.

Use a work breakdown structure (WBS) to create a project schedule based on the project and resource requirements.

B.

Monitor resource allocation to ensure that team members work 8 hours per day.

C.

Assign project tasks to the team regardless of their skills to accomplish the project schedule.

D.

Schedule daily meetings with key stakeholders to assess the effectiveness of the project management plan.

A hybrid project has just deployed, and the project manager is planning project closure with lessons learned workshops. A key stakeholder informs the project manager that having the Scrum team in the workshops is a waste of time because the project was delivered successfully.

What should the project manager do?

A.

Ask the Scrum team members to share retrospectives.

B.

Ask the scrum master to attend the workshops.

C.

Invite the Scrum team members as optional participants.

D.

Invite the Scrum team members as mandatory participants.

A project manager leads a software development project in a hybrid environment. During project planning, the project manager identified a risk where a technical resource for a critical path item may not be available when needed. One week before the resource is needed, the technical engineer had a personal emergency and had to take a leave.

What should the project manager do next?

A.

Update the lessons learned report and the risk log to reflect that this risk has materialized.

B.

Revise the project management plan and move the task to a time when the technical resource will be available.

C.

Consult the risk register for an appropriate planned risk response and implement.

D.

Review the business requirement with stakeholders and exclude the task assigned to the technical resource.

During user acceptance testing (UAT), a manager declined a core application functionality that was originally requested by a subject matter expert (SME). Due to the manager's influence, the project team is concerned about the overall impact to the project.

What should the project manager have done?

A.

Obtained a list of the critical stakeholders from the project sponsor

B.

Consulted with the project sponsor on stakeholder roles and responsibilities

C.

Identified and consulted stakeholders during requirements gathering

D.

Requested stakeholders to participate in project initiation and planning phases

An organization that embraced agile a couple of years ago is looking for a more efficient way to ensure that the increments produced in each sprint meet the end users’ quality requirements. What should the project lead recommend?

A.

Develop a more comprehensive template for the definition of done (DoD).

B.

Increase the percentage allocated for testing each backlog item.

C.

Organize more frequent sprint reviews with a broader audience.

D.

Establish a quality assurance (QA) team separate from the development team.

A sales director is upset that progress has been slow on the delivery of critical features to the customer. After consulting with the team, the project manager learns that a subject matter expert (SME) on the customer side is not cooperative in providing the input needed to complete the definition of ready (DoR).

What should the project manager do to avoid the same problem in future projects?

A.

Review the responsibility matrix at the customer kick-off meeting.

B.

Rely on internal SMEs for expert input on implementing the user stories.

C.

Include a contractual penalty for delays created by the customer.

D.

Require customer SMEs to attend at least half of the daily meetings.

A project is starting its first iteration out of six. During one of the daily meetings, the project manager realized that one of the team members does not have experience working in agile environments.

What should the project manager do?

A.

Give the team member some time to learn agile practices.

B.

Assign an agile mentor and follow the training process.

C.

Ask to increase the capacity of the team to finish on time.

D.

Ask the sponsor for additional budget for training.

A project manager is managing a project in a fast-paced environment. The project manager needs to empower the team to collaborate toward an expected outcome and enable high-team performance. The CEO has suggested that the project manager apply a servant leadership style.

What should the project manager do to demonstrate the capabilities of a servant leader?

A.

Encourage all team members to develop the perfect plan to achieve the desired results.

B.

Create an environment where all team members compete to achieve the desired results.

C.

Assess the business case and define the project priorities to motivate all team members.

D.

Define the project's objectives and create an environment where all team members can succeed in achieving them.

A project manager and project team are developing a strategic approach to engage the internal and external stakeholders. Which approach should be followed?

A.

Schedule status meetings with all stakeholders to allow their participation in all project discussions and reports.

B.

Analyze both internal and external stakeholders and develop a customized engagement strategy for each stakeholder.

C.

Involve only the internal stakeholders, as the external stakeholders should not have access to confidential information.

D.

Classify all high-risk stakeholders and request that the project sponsor communicate directly with them.

A Scrum team has information radiators but must also keep stakeholders aware of their progress. In addition, the project management office (PMO) has specific templates for status reporting to management. The project lead realizes that a variety of reporting will be needed to satisfy enterprise and stakeholder needs.

What should the project lead do?

A.

Determine the minimum communications needed for the project, and adapt the communication plans as needed.

B.

Document only the plan for written communications, and send meeting invites for verbal communication sessions.

C.

Follow the project management office (PMO) guidelines for communications instead of generating a project communications management plan.

D.

Create a communications management plan informing all project team members and stakeholders who will receive what type of communication.

A customer requests additional changes 1 day before the planned change date. How should the project manager respond to the change request?

A.

Reject the changes as the lead time is too short.

B.

Determine whether the project team is capable of making the changes.

C.

Review the additional changes and perform integrated change control.

D.

Check if the changes are covered in the statement of work (SOW).

A project is ready to deliver the first batch of the product when a quality control check rejects the product as unfit for delivery. The root cause

analysis (RCA) shows that a component added as part of the latest change request was not tested throughout the development cycle.

What should the project manager do next?

A.

Review the change control process to ensure quality management artifacts are updated as part of the change.

B.

Review the quality management process and perform a process audit as part of ongoing quality assurance.

C.

Review the communications management plan to ensure change requests are communicated to the affected team members.

D.

Review the quality management process with the project management office (PMO) to ensure compliance with best practices.

During a sprint planning, the development lead highlights the importance of working on technical debt tasks that are critical for the product performance. However, the tasks will consume most of the team's capacity and they will not be able to work on product feature development.

What should the project manager do?

A.

Invite technical stakeholders for backlog prioritization.

B.

Work on the features already prioritized by the product owner.

C.

Ask the sponsor for more resources to continue at the same pace.

D.

Add the technical debt tasks to the sprint backlog.

A project manager is using an agile approach. During the sprint planning meeting, the product owner flagged a backlog item as high business value and easy to implement. However, the other team members identified a high dependency between this item and another item that is flagged as low business value and high complexity.

What should the project manager do to support the backlog prioritization?

A.

Prioritize the item flagged as high business value and low complexity for this sprint.

B.

Support the team to move both items to the next sprint when the team will know more.

C.

Facilitate the discussion until the team reaches an agreement about the two items.

D.

Prioritize the item flagged as a dependency with low business value and high complexity.

A facility extension project is in the execution stage. There is a project activity to connect the power of all new equipment to an existing facility,

Point A, which requires a significant cable length. The construction team found that the power could be connected to Point B and save money.

What should the project manager do next?

A.

Perform a cost-benefit analysis to evaluate using the Point B option.

B.

Add the issue to the change log and request additional budget through the change control board (CCB).

C.

Seek a decision from the construction team after explaining the project budget and schedule constraint.

D.

Use the Point B option because it will save the project cost and time.

A subject matter expert (SME) external to the project team provides a suggestion that will save the project delivery time. This SME has available

time to support the project, but was not planned to be involved in the current agile iteration.

What should the project manager do?

A.

Bring the SME on board immediately and discuss the implications later.

B.

Ask the existing team members to collaborate with the SME and complete the activity.

C.

Ask the SME to complete all of the necessary changes, which will save time.

D.

Direct the team member to ignore the SME's changes as they were not planned.

While a project manager is trying to build the first baseline for a project, a change request is being sent from one of the functional managers. What should the project manager do?

A.

Discuss this with the functional manager and related parties.

B.

Reject the functional manager's change request immediately.

C.

Analyze the impact of the change request on the project.

D.

Apply for a formal change control board (CCB) approval.

A project manager decided to use a highly adaptive approach to manage a large-scale project. In this project, there are many iterative tasks that utilize highly specialized experts. The project manager would like to create practical plans with high levels of buy-in from the team members.

What should the project manager do next?

A.

Assign critical tasks to the most experienced team members.

B.

Review the budget with the team for the needed resources.

C.

Review lessons learned from similar projects with the team.

D.

Explain the higher-level objectives to be assigned to the team.

A project team member just informed the project manager that the license for the software that the team uses to perform calculations has just expired. As a result, the team cannot continue with their project tasks.

What should the project manager do first?

A.

Issue a formal complaint to the project sponsor claiming a lack of proper tools.

B.

Meet with the IT team to evaluate how fast the software license can be renewed.

C.

Ask the team to fast-track the project and perform tasks that do not require calculations.

D.

Ask the team members to find an alternative way to perform calculations.

A high-performing team is involved in a project with a new domain. The team is unable to deliver as expected.

What should the project manager do?

A.

Support the team in identifying the area of development and address the gap.

B.

Dissolve the team and include the team members in other existing teams.

C.

Identify the struggling team members and move them out of the team.

D.

Set up a clear expectation that the team is to deliver as in their previous projects.

Following an investment decision-making meeting for a project, a change to the organizational structure takes place in a multinational company. Due to the organizational change, internal stakeholders are referring the project manager to various other personnel for approval of the project budget.

What should the project manager do to obtain approval of the project budget?

A.

Provide the decision executive with all of the project details and request budget approval from the appropriate person.

B.

Identify the right person with help from local management, present the project summary, and request budget approval.

C.

Approach each of the referred individuals separately and request approval of the project budget from the appropriate person.

D.

Obtain the latest organizational chart and send an email to the appropriate person requesting budget approval.

A new project needs to be submitted for urgent funding approval. The project, which will use a new technology, is vital to the organization. The entire Scrum team has worked together for over 3 years on multiple projects and delivered the previous project under the approved budget.

Which estimation technique should the project manager implement in this context?

A.

Budget estimate

B.

Definitive estimate

C.

Story points

D.

Order of magnitude

A project management office (PMO) is currently stretched for project control resources. Specifically, the cost control resources are short of the staff required for this activity level. A new project is about to start soon.

What should the project lead do to obtain the needed resources?

A.

Evaluate running the project without the required resources and depend on the lessons learned from similar past projects.

B.

Prepare to perform the duties of the cost controller for the duration of the project.

C.

Meet with the PMO team and review the resource management plan ahead of the project kickoff to ensure resource availability.

D.

Inform the project sponsor and initiate a recruitment exercise outside of the PMO.

A project manager who has been working on an ongoing volatile project is retiring. A new project manager is collaborating with the retiring project manager to ensure a smooth transition.

What should the new project manager first discuss, review, and clarify during the transition meetings?

A.

Resource management plan

B.

Change management plan

C.

Lessons learned log

D.

Risk register

An unforeseen event has shut down public works projects for 4 weeks. Activities on the critical path will fall behind based on the project schedule.

What should the project manager do?

A.

Add 4 additional weeks to the schedule and request additional resources.

B.

Ask the sponsor to obtain a special work permit to continue work.

C.

Review the project management plan to see the impact of the possible delay.

D.

Crash the resource management plan to keep the schedule on track.

After the merger of two large companies, a project manager is assigned to a project. The company hires a consultant to ensure best practices are

being used in information security. During an iteration, the consultant requests changes to a software component, claiming that it is not meeting

market requirements.

What should the project manager do?

A.

Continue the iteration and add the requested changes.

B.

Continue the iteration and review the change with the customer.

C.

Cancel the iteration and meet with the product owner.

D.

Cancel the iteration and add the requested changes.

A stakeholder informs the project manager about a few compliance-related gaps and issues. The stakeholder then presents several suggestions to the project manager to address the issues.

What should the project manager do?

A.

Use the compliance issues to identify coaching and mentoring opportunities.

B.

Log the feedback from the compliance gaps in the lessons learned register.

C.

Review this with the project sponsor to avoid compliance gaps and issues.

D.

Discuss the suggestions with the staff responsible for the compliance issues.

During a regular project progress meeting, the CEO informed the project manager that a major stakeholder has been unaware of recent developments on the project. The

project manager is sure that the stakeholder was duly identified and classified in the stakeholder register.

Which project document should the project manager review in order to determine the reason for this issue?

A.

Requirements traceability matrix

B.

Stakeholder register

C.

Stakeholder engagement assessment matrix

D.

Issue log

A company has appointed a supplier to deliver software and has assigned an internal project manager. The supplier states that no technical development or testing is required from the customer. The project manager would like to confirm this with all of the stakeholders.

What should the internal project manager do first?

A.

Distribute the project plan to all of the interested parties.

B.

Host an alignment session with stakeholders to formalize the project requirements.

C.

Communicate to the supplier that customer testing is required.

D.

Develop a user acceptance testing plan to ensure the quality of the deliverables.

An enthusiastic, newly hired vice-president has been assigned as the product owner for a digital transformation project. The project manager

advises the product owner that some of the functional requirements are not aligned with the chief information technology officer's (CTO) strategy.

The product owner tells the project manager that the CTO is not part of the project and should not be engaged at this moment.

What should the project manager do?

A.

Advise the CTO about the possible impacts caused by the project.

B.

Influence the product owner to review the engagement needed from other stakeholders.

C.

Continue building the backlog since they are functional requirements.

D.

Review the organizational process assets (OPAs) for historical information from similar projects.

A project manager's project relies on services from a department that has a new leader. Since the new leader was appointed, the services from their department have been slow which threatens the project's delivery deadline.

What should the project manager do?

A.

Add the issue to the issue log and communicate the issue in the next regular report to project stakeholders.

B.

Escalate the issue to the project sponsor notifying them of the slow services from the department.

C.

Send all service requests to the department earlier in the project to lessen the impact on the delivery date.

D.

Arrange a meeting with the leader to explain the project's needs and understand the leader's perspective.

A key team member has recently gone through some personal issues that has affected their performance. The project manager noticed that the

team member's emotional situation has affected the rest of the team's performance.

How should the project manager handle this situation?

A.

Help all team members learn to deal with their emotions by building a culture of empathy.

B.

Separate the key team member and replace them while they emotionally recover.

C.

Meet with the team to discuss how to handle the performance problem.

D.

Ask the human resources (HR) department for their support providing emotional help.

Before kicking off a high-priority and complex project, what should the project manager do to ensure all project stakeholders are aware of their role scope as it relates to project activities?

A.

Create a communications management plan.

B.

Create a responsible, accountable, consulted, informed (RACI) chart.

C.

Develop a kanban board.

D.

Send a copy of the project charter to all project stakeholders.

A project team has installed software for the client, passed the knowledge to operations, sent the final report, and celebrated. Then 1 week later,

the client sendsa list of requirements that have not been met. The client is requesting to fix the issues quickly and within the initial budget.

What should the project manager have done to prevent this from happening?

A.

Reviewed the acceptance criteria and obtained client approval.

B.

Allocated a risk budget for any post-release improvements.

C.

Conducted a pilot to understand the client's performance parameters.

D.

Established meetings with the client throughout the project phases.