11.11 Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmas50

PMI PMP - Project Management Professional (2025 Version)

Page: 8 / 13
Total 2040 questions

A project manager has been assigned to a project and receives the project charter from the project management office (PMO) The document is very clear about customer requests During Project Scope Management some requirements seem to be different from the ones specified within the project charter

What should the project manager do?

A.

Modify the baseline of the project for minor impact changes to the project scope

B.

Use a focus group and brainstorming sessions to gather more details about the project scope

C.

Register the changes in the configuration management plan and send it to the change control board (CCB).

D.

Explain to the sponsor that these requests could endanger the schedule and cost of the project

A verbal announcement is made that the new team member joining the Scrum team has limited mobility The scrum master is aware that some team members are unsure how the dynamics of the team will change

What should the scrum master do?

A.

Create a stakeholder engagement plan

B.

Design a communications management plan

C.

Update the team charter accordingly.

D.

Set up a meeting to discuss accommodations the team will have to make

During an ongoing project a key resource asks the project manager about the project purpose and if it is aligned with the organization's strategy What should the project manager share with the key resource?

A.

The updated benefits management plan

B.

The updated scope management plan

C.

The updated project management plan

D.

The updated communications management plan

During the course of a project, a junior team member approaches the project manager for some direction and advice on risk mitigation How should the project manager respond?

A.

Tell the junior team member that the information is available in lessons learned

B.

Offer guidance and follow up with some developmental activity for the junior team member

C.

Inform the junior team member that risk mitigation is not part of their work

D.

Refer the junior team member to the senior team member who develops the risk mitigation strategy

Stakeholders in some industries prefer to deal with programmers and system analysts directly, bypassing project managers. This complicates managing resources on projects

How should a project manager solve this issue?

A.

Propose implementing a new project management information system (PMIS).

B.

Request a meeting with senior management to escalate the situation

C.

Promote adoption of the communications management plan with the project team.

D.

Host a team-building event to develop team cohesion and improve communication

A project just kicked off and management’s expectation is to ensure that the deliverable of the first iteration helps the marketing team present the product prototype to potential customers. What should the project manager do?

A.

Increase the details of the work breakdown structure (WBS) to minimize errors and delays.

B.

Split the backlog into phases to ensure that the key features are delivered first

C.

Ask the sponsor to prioritize some functionalities of the product.

D.

Identify the minimum functionality required for the product

A project manager is implementing a new software system Some department staff members are questioning the necessity of the change and feel the new system will impede their current processes

What should the project manager have done at the start of the project to prevent this resistance?

A.

Created a communications management plan that outlined the method of communicating to stakeholders.

B.

Ensured that the company culture encourages changes before accepting the project

C.

Encouraged leadership to discuss the change with departments that are typically resistant to change

D.

Involved stakeholders from all levels of the company so everyone understands the change

In a newly formed project team one experienced team member is overwhelmed by the complexity of the tasks and is not happy with the project team. What should the project manager do?

A.

Ask the team member to enter this potential schedule delay in the risk register.

B.

Explain that the tasks are unavoidable and ask the team member to find a solution to overcome the challenges

C.

Actively listen to the team member and identify ways to support their needs in completing the tasks.

D.

Set up team-building activities with the project team members to reduce tension

A product owner presented the backlog to the team, and the team raised concerns over implementing some of the features due to various impediments What should the project manager suggest that the product owner do next?

A.

Ensure that the impediments are captured and prioritized based upon the highest valued features

B.

Estimate the financial impact of the impediments and request additional funding

C.

Begin to remove the impediments, starting with the easiest ones first, to foster team accomplishment

D.

Capture the impediments and inform management that their assistance is neededin resolving the impediments

A project manager is working on the implementation of new phases in the production process of a regulated industry. Which two stakeholders can help the project manager determine and address compliance requirements? (Choose two)

A.

Risk steering committee

B.

Functional managers

C.

Board of directors

D.

Advisory team panel

E.

Chief executive officer

The following table shows the business value created and the development effort required to implement various features in a product

Which feature should the team prioritize first? Enter the feature name in the box below

A key project stakeholder showed interest in the beginning of a complex agile project but has become less involved as the sprint has progressed due to additional responsibilities A few sprints later, the key stakeholder rejected a feature deliverable The team is reworking the rejected deliverable for the next sprint

What should the project manager have done to avoid this situation?

A.

Involved the key stakeholders in the decision-making process

B.

Customized stakeholder communications based on the stakeholders’ needs

C.

Analyzed the changes in stakeholder attributes

D.

Documented the project vision and objectives

A project manager has been using predictive methodology for more than 10 years and is switching to an agile project. The team members have not previously worked together. After two sprints of work, the team has not achieved any outcome and there is a lot of pressure to get work done

What kind of leadership style should the project manager use at this stage?

A.

A directive style that makes decisions for the group to reach early outcomes

B.

A leadership style that coaches people who want help and fosters greater team collaboration

C.

A passive leadership style that allows the team to self-organize until the norming stage is reached

D.

A democratic style that uses techniques where majority opinion prevails

An organization is transitioning to agile and a project has been chosen as a pilot The assigned project manager only has experience using predictive approaches but the project manager is now required to use agile approaches with the help of an agile coach During the retrospective of the fifth sprint, the project team complains that many obstacles exist with the organization that are creating project delays and rework

What should the project manager do in this situation?

A.

Include impediment resolutions during daily standup meetings

B.

Perform a root cause analysis during the standup meetings

C.

Create a dedicated sprint to solve the obstacles with the team

D.

Promote collaboration to help remove the obstacles for the team

Some of the mote experienced members of a project team have complained about the project manager The senior project team members feel that the project manager is micromanaging them and preventing them from completing their work.

What should the project manager do when made aware of these issues?

A.

Ask for advice on how to be a better mentor to these team members.

B.

Set up a team building event to bring synergy back to the project team.

C.

Adjust the project manager's management style to better fit senior team members.

D.

Meet daily with each senior team member to monitor project status

A project manager is leading an in-house company project in its very early stages This current project is similar to another project that ended a year ago

What should the project manager do to analyze the involved stakeholders?

A.

Lower the priority of stakeholder engagement as the stakeholders already have knowledge of this kind of project

B.

Use lessons learned from the previous project as a guide for the current project's stakeholder register

C.

Refer to the stakeholder register from the previous project as it was similar to the current project

D.

Document in the risk register that the current project may have differentstakeholders than the previous project

During the implementation phase of a construction project the customer asked a key subcontractor to deliver a work package ahead of time The subcontractor was not prepared for it and asked the project manager for additional budget What should the project manager do first?

A.

Ask upper management for more funds and update the project budget

B.

Revise the project scope accordingly to cope with the budget changes

C.

Update the risk register and project log. and manage the budget closely.

D.

Submit a change request to accelerate the project as requested

A company has been following a predictive approach and always waits for the preceding phase to be completed before evaluating the quality of their products A new project manager with experience in hybrid approaches has been assigned to help increase the efficiency of the company's quality management process.

What should the new project manager do to address the process improvements?

A.

Understand the context and interdependencies of the process from the team members and then define improvements

B.

Continue with the process as is. and wait until the next phase to suggest any improvements

C.

Discuss the process improvement with the project management office (PMO) lead to update the project delivery framework

D.

Define a ground rule to comply with the quality standard and ask the team members to apply it.

Drag the characteristics of the stage on the left to the correct Tuckman Ladder stage on the right

In a multinational multi location project with virtual teams a project manager has established a project baseline The project manager discovers that multiple risk elements have appeared. The project manager did not foresee these risks during the planning stage of the project.

What should the project manager calculate to address this critical budgetary situation? (Choose two)

A.

Contingency control in the project and rebaseline

B.

Mitigation control in the project

C.

Benefits management control in the project

D.

Integrated change control in the project

E.

Currency exchange rate

A project manager is in rapid development mode on a joint application development module The company wants delivery to occur in two weeks The module needs to be integrated with other modules on a similar timeline, but release management has a three-week backlog

What should the project manager do?

A.

Push the team to deliver more so that the modules are developed and rolled out according to management's request

B.

Speak to the stakeholders to resolve the bottleneck and see how the entire process can be streamlined

C.

Have the team work toward the tighter deadline so that integration will be easier.

D.

Speak to the team and slow the current pace to ensure the team is in alignment with the release date

An integrated project involves the interaction of both hardware and software and the sponsor has approved the schedule management plan The project team evaluated the product's feasibility of functionality and accelerated testing What should the project manager do as a servant leader?

A.

Support the team as necessary to find the minimum viable product (MVP).

B.

Amend the project budget to include MVP testing

C.

Submit a change request to the project sponsor for accelerated testing.

D.

Develop the product as per the schedule to perform integration and testing

After reviewing the project management plan with key stakeholders, the project manager was told that an 18-month release plan was unacceptable and the product should launch in six months. Based on the new timeline, what should the project manager do?

A.

Plan for overtime apply crashing and fast tracking and share the risk of failure with project stakeholders

B.

Review the project backlog looking for high-priority items and come up with a minimum viable product (MVP) that fits the expected timeline

C.

Seek approval with the sponsor to triple the project budget, hiring more people to compensate for the compressed schedule

D.

Go over the critical path with stakeholders, explaining why it is not possible to deliver all the scope in the expected timeline

During the execution of a project the project manager notices that only one team member has one of the technical skills needed to build the product The project manager is afraid this might have a future impact on the quality and schedule because most of the upcoming activities will require at least three people with this specific skill.

What two actions should the project manager take to prevent the team from being unqualified? (Choose two)

A.

Exclude the activities from the roadmap

B.

Encourage working in pairs and knowledge sharing

C.

Teach the entire team the new skill.

D.

Facilitate a training event with an external trainer

E.

Increase the time estimates on the activities that require such abilities

A project manager is starting a project using a hybrid approach and notices some team members only have knowledge of predictive approaches What does the project manager need to do first in order to have good project performance?

A.

Coach those team members lacking hybrid knowledge to learn on the job.

B.

Change the team to include hybrid experts

C.

Assess the required training per team member.

D.

Deliver hybrid training to all team members

During a documentation audit of an international company it was identified that the last version of the project schedule was from one month ago even though the project manager knew it was recently updated How should the project manager have handled documentation for the project?

A.

Updated the project management plan regularly and had it securely shared with all stakeholders

B.

Assigned a project team member to ensure all project documentation was updated

C.

Reviewed the risk register to identify a response plan for the audit

D.

Kept documentation in the project management information system (PMIS), and shared it with appropriate stakeholders

A new project manager learns the work assigned to the team has already been decomposed to its lowest level The project manager reviews the work and feels some additional useful information is missing

What should the project manager review?

A.

The project charter and scope statement

B.

The requirements traceability matrix

C.

The business requirement documents (BRD)

D.

The WBS dictionary

After the second iteration of a component development project, the project team conducts a retrospective It shows that in the initial phase the project has failed to comply with a product functionality. The planning for this product has a predominantly predictive approach.

Which technique will help the project manager to accelerate the deliverable?

A.

Impact mapping

B.

Rolling wave planning

C.

Collective code ownership

D.

Scrum of Scrums

A project manager has been moved to a new division and is in charge of an existing project in an unfamiliar domain When attempting to gain an understanding of the risks for this agile project what is the primary tool the project manager should employ?

A.

Probability assessments

B.

Collaborative discussions

C.

Workshops for risk avoidance

D.

Interview with the project champion

The project velocity has recently slipped, and a decision was made to skip testing to increase the momentum and bong the project back on track What will the project manager need to focus on as a result of this decision?

A.

Increased bum rate

B.

Increased cost

C.

Increased technical debt

D.

Decreased efficiency

An agile project team is looking to develop quality standards for a project How should the project manager coach the team?

A.

Determine the tools and techniques suitable for the project and ensure that testing is done early and continuously.

B.

Inform the team that user acceptance testing is required to ensure that the product owner accepts the solution

C.

Insist that test-driven development is implemented along with the automated testing

D.

Ensure that the definition of done (DoD) is provided when the product owner agrees that all acceptance criteria have been met for the user story

Development team members are located in three different time zones It is difficult to find a suitable time to hold the daily standup for all team members

What should the project manager do?

A.

Encourage frequent small team meetings with two or three team members.

B.

Give up the daily standup and replace it with a daily report

C.

Let the team members decide themselves if they want to join the meeting.

D.

Require all team members to join the daily standup regardless of the meeting time

An experienced project manager is overseeing a merger and acquisition project. The project manager reacted differently to different threats identified on the project

Drag the mitigation strategy on the left to the project manager's actions on the right

A project manager has been appointed to a multimillion-dollar project The project is considered to be high risk since no similar projects have been undertaken before and there is no historical data Some external stakeholders are reluctant to provide support

What approach should the project manager take?

A.

Examine the plans, processes, policies, and knowledge that are specific to the organization undertaking the project

B.

Establish dialogue with stakeholders on the project constraints, assumptions, and critical inputs

C.

Convince senior management to close the project since the project lacks sponsorship and is considered to be high risk.

D.

Host a project team meeting, then update the risk register and the project management plan

During the course of a project the project manager's immediate director is communicating directly with the client to approve changes without the project manager's knowledge This is causing confusion in the project team where the scope is changing in the background, but only being mentioned in project meetings

How should the project manager handle this?

A.

Communicate directly with the director and inform them of the communications management plan

B.

Communicate directly with the client stating that any scope changes must go through the project manager

C.

Review the stakeholder engagement plan and put in place any existing actionsaccordingly

D.

Discuss the issues with the project team and let them know that the project manager will handle scope changes

The marketing team is transitioning to using hybrid approaches for their projects. The marketing director is not knowledgeable about hybrid methodologies and the project manager needs the director’s support as the marketing director is a key stakeholder.

What should the project manager do to obtain the support?

A.

Ask the marketing director to participate in daily meetings

B.

Mentor the marketing director on hybrid approaches

C.

Ask the marketing team members to coach the director

D.

Tram the marketing team and keep the director informed

The city has decided to build a new tram station The project will include various approaches The construction and infrastructure work will be accomplished using a predictive life cycle while software will be developed using an iterative life cycle Some neighbors are resisting the project have been asking the mayor to stop the project, and are threatening legal action

What two actions should the project manager take'? (Choose two)

A.

Discuss with the construction team alternatives on moving the new train station to another location.

B.

Publish information on the city’s website about the benefits that the new tram station will bring

C.

Have a meeting with the mayor and explain the importance of the new train station to the city.

D.

Conduct regular meetings with the neighbors to get their buy-in for the project

E.

Register this situation as a risk and develop a mitigation plan

A project manager is working on a software development project. A team member complains that since the project tasks are very simple, there is no reason to perform quality control The project manager understands that removing the quality management plan from the project will also help to save money, which is important to the customer

What should the project manager do?

A.

Register starting the project without a quality management plan as a risk, and allocate the budget savings to the management reserve

B.

Develop the quality management plan, as quality is as equally important as cost and schedule management.

C.

Get confirmation from management that the team member has enough experienceto build software without quality control

D.

Ask the customer to order an external quality audit after accepting the project deliverable, and decrease the budget of the project

A new regulation has been approved that will impact the deliverables in the fourth phase of the project The delivery is following an iterative approach and is currently completing the second phase.

What should the project manager do next?

A.

Consult with the project sponsor to discuss a cost increase

B.

Acquire approval for an exception to the implementation of the new regulation.

C.

Get approval for the additional budget from the steering committee

D.

Meet with subject matter experts (SMEs) to assess the impact to objectives

The project manager has learned that the project sponsor is unhappy with the development of the project requirements In order to realign the project with the sponsor's expectations, what should the project manager do?

A.

Review the project goal diagram with the team.

B.

Perform a stakeholder evaluation

C.

Confirm which templates the team should be using

D.

Review the risk management plan

During the last sprint review the product owner stated that the product does not deliver any value The project manager believes that the product meets all the provided specifications

The team is confused by the product owner's statement

What should the project manager do when using a hybrid approach?

A.

Escalate the matter to the executive board so they can decide on next steps

B.

Prioritize the project backlog and ask the development team to fix the issues

C.

Review the project's benefits management plan with the product owner.

D.

Ask the product owner to terminate the project as it is no longer aligned to the expected benefits

A project manager is assigned to lead a newly formed agile team. The functional manager has assigned tasks to team members, but the team members do not feel empowered.

How can the project manager promote empowerment and accountability among the team?

A.

Assign the tasks individually based on the role of the team member to ensure expertise on the subject.

B.

Encourage and assign the team to perform demos of their products or software with the customers

C.

Give the team autonomy to make their own decisions on how to perform the tasks.

D.

Encourage the team to keep the product owner involved when choosing ways to resolve the given task

An external project manager is managing the construction of new corporate offices for a large company The project management plan states that it is necessary to contract a highly trained external resource to revise and validate an important project component The client has rejected hiring the external resource because of the high cost even though it is within the project budget.

What should the project manager do to resolve this issue?

A.

Hire the resource in order to achieve the project objectives.

B.

Ask the client for a meeting and explain that the task will not be performed

C.

Evaluate the consequences and meet with the client to explain the possible scenarios.

D.

Try to accomplish the task internally by leveling resources from other projects

A project manager led the implementation of an electronic invoicing project that has just been completed. The financial manager communicated that the team discovered three invoices with errors.

Which two documents should the project manager update as soon as possible? (Choose two)

A.

Issue log

B.

Risk register

C.

Stakeholder register

D.

Change log

E.

Backlog register

A team is ready to start working on a project with a customer who was very difficult to work with in the past because the customer was unable to describe exactly what they wanted What approach should the project manager take to remove this impediment?

A.

Follow a predictive approach in order to obtain formal acceptance of each deliverable

B.

Work with the product owner to define the minimum viable product(s)

C.

Reinforce the negotiation and soft skills of the team through training

D.

Develop and monitor a plan with due dates to reduce the time of completing the product

A company is using a predictive approach for the development of a particular component as defined in the scope management plan Due to regularly changing regulatory requirements, the development team has requested to utilize agile approaches

What should the project manager do about the development team's request"?

A.

Escalate the request for additional financial resources

B.

Forward the request to the project management office (PMO) to amend the organizational process assets

C.

Ask the project sponsor to obtain approval for implementation of the new approach

D.

Analyze the requirements that will need to be addressed under the requested method

A project manager is leading a project that is in an advanced stage. All high-level risks identified in the risk management plan have been resolved or are no longer a risk for the project. Only low-level risks remain

What should the project manager do now?

A.

Reduce the priority of project risks as all remaining risks are low-level

B.

Notify stakeholders that all high-level risks have been resolved

C.

Reevaluate identified risks and update the risk register

D.

Reclassify low-level risks as high-level risks

Due to a company merger and acquisition process, the main stakeholder of a critical project has been changed This new stakeholder complains that they were unaware of a delay on the project of which the rest of the stakeholders were aware. All the communications about the project are shared via email at the start of every week.

How should the project manager address this situation?

A.

Send evidence to the new stakeholder that the project's status was sent according to the schedule

B.

Suggest that the new stakeholder review the project status before the next board meeting

C.

Share the communications management plan with the new stakeholder

D.

Discuss project requirements with the new stakeholder, and update the communications management plan.

A large multi-year project requires highly skilled staff for successful deployment The management team and the project sponsor have analyzed the resource requirements and agreed to have permanent staff hired for the project to avoid potential budget overrun However there is a risk of staff turnover during the course of the project, which may have an impact on the delivery

Which two actions should the project manager take to mitigate this risk? (Choose two)

A.

Introduce a recognition program to motivate and reward resource performance

B.

Enhance the competencies of the project team through training, mentoring and coaching.

C.

Increase the trained staff to create back-up for resources

D.

Meet with management to discuss dividing the project into smaller projects

E.

Convince senior management to hire third-party staff

While reviewing prototypes, the quality team found some deviations that do not affect the mam functionality but have the potential to be an issue in the future To avoid major problems in the future, the team recommends corrective actions that will require additional funds The project is already struggling to stay on budget and has even used some of the contingency reserves

What should the project manager do?

A.

Ask the product designer why the deviation was not considered in the design phase

B.

Report to the project sponsor that the product is working and the project is struggling with the budget.

C.

Evaluate and initiate the change request process with the stakeholders

D.

Ask the quality team to discard the sample and test again with a new sample