Summer Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmas50

PMI PMP - Project Management Professional (PMBOK 7th Version)

Page: 8 / 14
Total 2196 questions

A project manager is hired to work on a very large, complex project that requires the team to complete a significant number of specialized tasks. What strategy should the project manager incorporate to help organize, assign, and monitor these tasks?

A.

Create a list of the tasks and send it to the project sponsor for review and approval.

B.

Develop a work breakdown structure (WBS) that decomposes the project deliverables into work packages.

C.

Schedule a meeting with the stakeholders to determine which tasks can be eliminated.

D.

Prepare a resource management plan that details all the resources needed to complete the tasks.

A complex project is in the execution phase. A key stakeholder who is new to the project has not been approving project deliverables, which could impact the overall progress.

What should the project manager do next?

A.

Meet with the stakeholder to understand what is causing the delays.

B.

Discuss the need to influence this stakeholder with the sponsor.

C.

Facilitate a brainstorming session to find potential workarounds.

D.

Capture this in the issue log and escalate it to the project sponsor.

A new project manager is taking over a project to deliver a new payroll management system that is running behind schedule. In addition, costs are rising due to many late changes requested by the client. What should the project manager do first?

A.

Schedule a meeting with stakeholders and explain the situation.

B.

Discuss the situation with the sponsor and seek their guidance.

C.

Arrange a time to meet with the team to understand the parameters.

D.

Meet with the team to understand the areas of concern.

A construction project is in its final stage when the owner of a private property where the pipeline is routed refuses to collaborate. The lack of collaboration causes a project delay, but the client insists that the project must be completed as per the contract. What should the project manager do next?

A.

Request additional budget from the project sponsor and raise a dispute with the property owner to force them to collaborate.

B.

Use the contingency reserve, add more resources, and reroute the pipeline to complete the project as per the contract timeline.

C.

Escalate the routing pipeline issue to the project change control board (CCB) and wait for a resolution to the conflict.

D.

Review the agreement with the property owner, schedule a meeting with them to discuss their concerns, and inform the client.

A major issue regarding conflicting priorities has been highlighted by the project team with respect to a few stakeholder requirements.

What should the project manager do?

A.

Escalate to the project management office (PMO) and request a solution for the requirements.

B.

Prioritize other items for the team and deal with the conflicting requirements later.

C.

Allow the project team to decide which requirement is the most appropriate to follow.

D.

Negotiate a common agreement with the involved stakeholders regarding the requirements.

During a blueprint review meeting, the finance department representative is not comfortable with a proposed solution that favors another department. As a result, document approval is delayed, which impacts the project schedule.

What should the project manager do?

A.

Arrange a meeting with the two departments to understand their differences and address their needs.

B.

Schedule a meeting with the project sponsor to seek advice on the approach of both departments.

C.

Work with the project team to find a compromise solution that suits both departments.

D.

Assess the risk of postponing this specific solution and advise both departments of the delay.

A project manager is struggling to provide timely updates to the project team because team members are spread across multiple time zones.

Which communication method should the project manager utilize in this situation?

A.

Interactive communication

B.

Push communication

C.

Public communication

D.

Pull communication

A project team has deployed an email marketing campaign across different countries. In one country, the end users have been opting out of the campaign because they think the email is spam. What should the project manager do first?

A.

Conduct a retrospective meeting to identify what went well and what went wrong.

B.

Review the email marketing standards of that country with the stakeholders.

C.

Schedule a meeting with project team members to identify the root cause.

D.

Schedule additional country-specific user testing to reduce email opt out.

A new project manager has been assigned to a recently approved project. The project has a multimillion-dollar budget and will require the purchase of expensive pieces of equipment. The project manager is aware that some purchasing amounts require higher levels of approval.

What should the project manager do to properly manage the purchase of equipment?

A.

Agree on a purchasing approval escalation method according to organizational governance.

B.

Ask the organization to allow the project manager to approve all of the purchases.

C.

Propose that the project sponsor approve all of the pieces of equipment that need to be purchased.

D.

Replace the most expensive pieces of equipment with cheaper ones to allow easier purchase approval.

A project manager recently took over an ongoing project. Within a few weeks on the project, the project manager discovers that there are continuous change requests from different project end users. What is the probable cause for this?

A.

Undefined change control process

B.

Unidentified project risks

C.

Improper work breakdown structure (WBS)

D.

Incomplete requirements

A project lead accepted an assignment for a project that is still in the feasibility study phase. There are many uncertainties about project specifications, including poor alignment among the project sponsors on the final targets of the project.

Which approach should the project lead choose to deliver business value?

A.

Subdivide project tasks to find the minimum viable product (MVP).

B.

Ensure commitment from sponsors on executing the project until it ends.

C.

Identify and communicate clear risk mitigation plans.

D.

Recommend predictive project management to the sponsors.

A project manager is leading a complex project with stakeholders from different countries, cultures, and languages. What can the project manager do to manage this diverse group of stakeholders?

A.

Assign team members to deliverables according to their cultures and languages

B.

Ask the PMO to assign a cultural manager to oversee relations between diverse groups

C.

Perform an analysis to better understand the communication needs and preferences of each group

D.

Establish one language as the main language for communications and one official time zone for the project

In a fixed time and budget project, the customer wants development of a core component to be based on agile practices because the final scope has not yet been fully developed. The project manager is participating in contract development with the sales team and wants to ensure that development costs do not impact project profitability. Which two controls should the project manager incorporate into the contract to address development of the core component? (Choose 2)

A.

Establish a governance committee to review contract delivery

B.

Require that only internal resources be utilized for this project

C.

Provide alternatives to scope change at specific project phases within the contract

D.

Tier the contract for fixed and agile components

E.

Limit the number of iterations for development in the contract

A new project manager has been hired at a company that has suffered many project failures. The project manager has been tasked with delivering a software product for the company’s biggest customer. The customer has not been able to articulate how a major piece of functionality should work. The project manager wants to deliver value immediately.

How should the project manager approach the software development life cycle with this customer?

A.

Raise a risk that the scoping and estimating phase of the project will be delayed if the customer cannot deliver an approved set of requirements.

B.

Add extra time to the estimating phase of the project as well as additional resources to accommodate the lack of requirements.

C.

Assign a business analyst to build a detailed set of requirements with the customer so the project manager can properly estimate the project duration.

D.

Explain to the customer that the team will build a production prototyping model to help the customer visualize how the additional features should work.

During a sprint planning meeting, a project team analyzes the effort required to complete some of the tasks before aligning on a sprint commitment. The project team faces issues when trying to estimate the testing effort for the tasks. What should the project manager do first?

A.

Obtain the acceptance criteria from the product owner.

B.

Encourage the team to do pair programming to reduce testing.

C.

Ensure the definition of done (DoD) is understood by all team members.

D.

Involve a quality assurance (QA) expert to support the testing estimation.

While an iteration is in progress, a project manager notices a delay in the prototype. The sponsor reaches out to the project manager and suggests engaging with cross-functional stakeholders.

What should the project manager do?

A.

Analyze the delay and discuss the findings with the subject matter expert (SME).

B.

Ask the developers to discuss the delay at a retrospective.

C.

Request that the product owner assess whether the team needs an external subject matter expert (SME).

D.

Record this in the issue log and define further steps.

A project manager is leading a complex project. The project stakeholders include individuals from different countries, cultures, and languages.

What can the project manager do to manage this diverse group of stakeholders?

A.

Establish one language as the main language for communications and an official time zone for the project.

B.

Perform an analysis to better understand the communication needs and preferences of each group.

C.

Organize and assign the team members to the project deliverables according to their cultures and languages.

D.

Ask the project management office (PMO) to assign a cultural manager to oversee relations between diverse groups.

A project manager is leading a contract for a new market that was awarded to their company. The client has the desire to jump-start the market with informal sector traders. What should the project manager do?

A.

Plan the project in phases, starting with the informal sector, to deliver business value quickly

B.

Divide the project team into groups to execute as small parallel projects, including the informal sector

C.

Gather requirements and convert them into backlog items to quickly deliver value

D.

Execute the projects simultaneously following the project schedule and the communications management plan

Two project managers are competing to assign a key subject matter expert (SME) to their concurrently scheduled projects. Work requiring constant physical presence means the SME can serve on only one project at a time. What should the project managers do first to facilitate allocation of the resource?

A.

Calculate the schedule performance index (SPI) based on the SME assignment

B.

Assess both projects to determine the business benefits based on the SME assignment

C.

Evaluate the associated budget and schedule based on the SME assignment

D.

Determine the cost performance index (CPI) based on the SME assignment

A project sponsor is upset that a vital project might miss an agreed-upon delivery deadline. The sponsor asks the project manager to check whether the project team can do anything to deliver on time. What should the project manager do first?

A.

Increase project team resources to maintain the timeline

B.

Conduct simulations to determine the best way forward to ensure timely delivery

C.

Reduce scope to deliver on time

D.

Work with the team to ensure the project is delivered on time

A complex project is being developed in phases as per the original plan. Half of the systems have been handed over to the customer for operational use. There is no delay in the schedule. However, the customer is still not happy because some of the systems handed over are no longer useful due to changes in the environment. What should the project manager have done to avoid this?

A.

Asked the customer to participate in project status meetings to better understand the progress

B.

Informed the project team to closely monitor the deliverables and keep the customer informed

C.

Reviewed benefits realization with the customer regularly and constantly aligned expectations

D.

Explained to the customer that the project is in good shape as the system is operational

A project team member tells the project lead that expecting a similar delivery output for every day of the sprint is not realistic. The project lead reports this to the project management office (PMO). What should the project lead do?

A.

Discuss the issue with the product owner

B.

Discuss this with the project team in the next sprint retrospective meeting

C.

Discuss this with the project team in the next sprint planning meeting

D.

Discuss this with the PMO manager

A project manager is working on an agile project. The organization does not have experience with agile delivery. During business case development, the new product owner asks when the project deliverables are considered complete.

How should the project manager respond?

A.

Items are considered complete when they satisfy the definition of done (DoD).

B.

The scrum master will approve the user stories that are complete.

C.

Backlog items are considered complete when the product owner approves the demo.

D.

At the end of each sprint, the outcome is considered ready for production.

A project manager is assigned to an IT project to deliver a new accounting system. Some managers at the company do not see the value of this project and say they will not use the new system. What two actions should the project manager take? (Choose 2)

A.

Review the list of stakeholders that will be affected by starting this business initiative.

B.

Continue with the project the way it was planned and validated by the sponsor.

C.

Describe the outcome of the project and business value to all company stakeholders.

D.

Add this issue to the risk register and monitor stakeholder engagement at the next milestone.

E.

Modify the project management plan and scope of work to avoid future difficulties.

It is taking several additional iterations for a project team to complete planned backlog items. The project manager notices that some features are not meeting the iteration-level definition and must be placed back into the backlog. What should the project manager do?

A.

Address the required changes in the next release

B.

Review and update the acceptance criteria

C.

Put more emphasis on the definition of done (DoD)

D.

Extend the iterations to complete the items

A project manager is working on an agile project. The organization does not have experience with agile delivery. During business case development, the new product owner asks when project deliverables are considered complete. How should the project manager respond?

A.

At the end of each sprint, the outcome is considered ready for production

B.

The scrum master will approve the user stories that are complete

C.

Backlog items are considered complete when the product owner approves the demo

D.

Items are considered complete when they satisfy the definition of done (DoD)

A new project includes important product features that should be delivered as soon as they are completed during the following quarter. The project team consists of junior and senior technicians.

Which two actions should the project manager take to deliver product features as soon as possible? (Choose 2)

A.

Instruct the senior technicians to lead the junior technicians.

B.

Align on clear and proper accountability levels.

C.

Empower the team to self-organize.

D.

Conduct a detailed work review of the junior technicians.

E.

Review a detailed plan with the senior technicians.

During the project planning phase, the customer explained the importance of delivering the project results proposed in the scope as soon as possible. What should the project manager do first to address this?

A.

Assess the opportunities to deliver project value incrementally

B.

Gather all the requirements’ details and schedule a refinement meeting

C.

Prepare a project management plan for the full scope using an agile approach

D.

Approve a change request to change the project approach to agile

A project manager is leading a highly visible project initiative. A few weeks after kickoff, the project manager starts receiving requests for updates from various stakeholders. What should the project manager do?

A.

Remove those stakeholders from the project since they may negatively affect project goals

B.

Invite all project stakeholders to join the daily standup meeting to ensure they are informed

C.

Schedule a meeting with relevant stakeholders to review the project communications plan

D.

Explain to the stakeholders that they must request project updates from the project sponsor

A project manager is leading a project with a risk management plan detailing strategy and actions if any of the identified risks become an issue. One of the identified risks becomes an issue, but the project manager acknowledges that the response considered in the risk management plan may not be the best.

What should the project manager do?

A.

Adopt the action prescribed in the risk management plan since it was agreed to beforehand.

B.

Submit a change request to perform a different issue response than what is registered in the risk management plan.

C.

Escalate the issue to the project sponsor and register the new risk response in the project documents.

D.

Meet with the project team and sponsor to reevaluate all issue responses registered in the risk management plan.

A project is in its first of six iterations. The project team realizes that a key deliverable is dependent on the acquisition of a new device. The vendor is new to the organization and does not have a long history in the market. What should the project manager do first?

A.

Register the risk and provide appropriate response options.

B.

Register the risk and prioritize the implementation strategy.

C.

Register the risk and escalate it to the procurement team.

D.

Register the risk and escalate it to the project sponsor.

A project to add metro stations is being executed, with seven out of eight stations currently in place. Suddenly, a notification from the local community is received, demanding that the project be stopped.

What should the project manager do first?

A.

Register the issue and escalate it to the project sponsor.

B.

Execute the contingency plan defined in the risk management plan.

C.

Meet with the project stakeholders to define a mitigation plan.

D.

Estimate the cost of changing the project location.

Halfway through the execution of a project, a key team member resigns from the company and will leave in 2 weeks.

What should the project manager do next?

A.

Persuade the team member to delay their resignation until the project is completed.

B.

Plan for the team member to finalize their assigned project tasks before leaving.

C.

Work together on the knowledge transfer plan for the remaining team members.

D.

Ask human resources (HR) to start looking for the team member’s replacement.

Two days before the end of a sprint, a team member updates the team lead that they will not be able to complete their tasks for the sprint due to a technical difficulty. What should the agile team lead do?

A.

Inform the product owner of the issue and request that they reprioritize the delayed task.

B.

Suggest the team member get more technical training in the next quarter.

C.

Update the risk register to reflect the possible risk of a schedule delay.

D.

Raise this issue during the daily meeting to determine a possible solution with the team.

An organization is about to start a time-critical project and has decided to use an agile approach for the first time. However, stakeholders are worried that they will not be able to verify the status of the project, since they believe that their usual governance model will not work for an agile project.

What should the project manager do?

A.

Recommend following the existing governance structure with the project team.

B.

Meet with stakeholders to discuss and review the governance structure.

C.

Review the governance structure to reflect scope changes.

D.

Discuss using a hybrid governance structure with stakeholders.

A project manager notices a product owner has been unresponsive over the last few weeks. During one-on-one sessions, the product owner is unable to provide complete information, leading to rework of the project stories. What should the project manager do first?

A.

Increase the sprint duration to accommodate the additional work

B.

Conduct a root cause analysis before addressing the issue

C.

Escalate the issue to the stakeholder ' s functional manager

D.

Cancel the one-on-one sessions and obtain the information via email

A project manager has just started a new project for an organization that dislikes budget and schedule deviations. The project stakeholders are very engaged and want to ensure there is clear visibility of the project’s risks and progress. How should the project manager handle stakeholder expectations?

A.

Discuss the risk response strategies with the stakeholders

B.

Add buffers to the schedule to accommodate unforeseen changes

C.

Ensure the risk register includes all identified risks

D.

Develop a communications management plan to share updates with stakeholders

A project manager is leading the construction of a high-rise mall for a customer in an emerging competitive market. Some customers want to move in as soon as the ground floor is completed. What should the project manager do to deliver business value to the client?

A.

Use management reserve and crash the schedule

B.

Implement an agile project delivery approach

C.

Explain the need to follow the quality assurance (QA) schedule to the customer

D.

Adopt an incremental project delivery approach

A project sponsor is transitioning their division to an agile environment and has emphasized that project team members and stakeholders should collaborate to achieve deliverables. On a few occasions, progress has been interrupted by one stakeholder who is unfamiliar with agile approaches. What should the project manager do first?

A.

Report the behavior to the project sponsor and find a replacement.

B.

Note the stakeholder’s attitude as a risk and continue development according to the plan to deliver value.

C.

Consider using a predictive project management framework and report the results to the project sponsor.

D.

Address the stakeholder’s behavior directly and provide feedback.

During project implementation, a critical performance issue is identified by team members. What should the project manager do?

A.

Submit a change request to handle the performance issue

B.

Review the tender requirements related to the performance issue

C.

Pass the performance issue to subject matter experts (SMEs) to handle

D.

Work with the project stakeholders to address the performance issue

A project to develop an enterprise resource planning (ERP) system for a university is ongoing. The system should improve business processes through digitalization and elimination of human errors, and also provide end users with simplified and easily accessible services. What should the project manager do to ensure achievement of the intended business value?

A.

Evaluate each change request and review the business case each time

B.

Evaluate deliverables against the business case continuously

C.

Evaluate deliverables against the business case at the end of the life cycle

D.

Evaluate customer feedback and review the business case each time

A project is in its fourth iteration out of eight, with a delivery performance of 95%. A project stakeholder asks the project manager about the status of a specific deliverable that is not visible in the status report.

What should the project manager do?

A.

Invite the stakeholder to the next iteration review.

B.

Include the deliverable in the status report and resend it to the stakeholder.

C.

Invite the stakeholder to the next daily meeting.

D.

Schedule a meeting with the stakeholder to review the status report.

A project manager is presented with a roadmap that excludes most of their recommendations. The content source of the roadmap is an influential stakeholder who disagrees with the use of specific procedures and practices. The project sponsor deems the roadmap acceptable. Which two actions should the project manager take first? (Choose 2)

A.

Align the roadmap within the project framework and perform a risk analysis.

B.

Align deliverables based on the roadmap and documented results.

C.

Request to have the roadmap reviewed by the project management office (PMO).

D.

Request reassignment to another project to avoid conflict with the stakeholder.

E.

Discuss the reasoning behind the roadmap with the stakeholder.

A project team member finishes all assigned tasks in the middle of a sprint. The team member wants to plan tasks for the next sprint to deliver business value earlier. The team member has the abilities and knowledge to execute tasks not yet started by other team members in the current sprint. What should the project manager do?

A.

Validate completeness of the tasks delivered in the current sprint

B.

Increase team velocity to execute tasks for the next sprints

C.

Reassign the team member to other tasks in the current sprint

D.

Encourage the team member to execute the next sprint tasks

A project team member tells the project lead that expecting a similar delivery output for every day of the sprint is not realistic. The project lead reports this to the project management office (PMO).

What should the project lead do?

A.

Discuss this with the PMO manager.

B.

Discuss the issue with the product owner.

C.

Discuss this with the project team in the next sprint retrospective meeting.

D.

Discuss this with the project team in the next sprint planning meeting.

During the initial phase of a construction project, the team is confused about the safety requirements it needs to consider during implementation. The project manager recently met with the client to define the project scope.

How should the project manager share this information?

A.

Meet with the team and present the scope of the safety requirements.

B.

Distribute the security requirements during the project execution phase.

C.

Modify the project charter by including the safety requirements.

D.

Send an email to the team with the details of the safety requirements.

During the team’s daily meetings, the project manager notices that some team members are consistently experiencing blockers due to communication issues and misunderstanding process directions.

How should the project manager proceed in this situation?

A.

Hold coaching sessions to further educate these team members.

B.

Take the current velocity into account for the next iteration planning.

C.

Request that these team members improve their performance.

D.

Instruct the team members on how to remove project obstacles.

A project manager has been assigned to a project. The project deadline has been established but, based on the number of stakeholders to engage and interview, it will be difficult to complete the project within the timeline. How should the project manager address this challenge?

A.

Commit to completing the deliverables associated with only the engaged parties.

B.

Submit a change request to extend the time needed to engage all of the parties.

C.

Request that the product owner define which parties should be engaged first.

D.

Prioritize the engagement of parties who are most impacted to minimize project risk.

A new team member joins the project and fails to apply the project-specific quality assurance (QA) processes.

What should the project manager have done to avoid this issue?

A.

Delegated the quality assurance (QA) tasks to the team lead.

B.

Ensured that the new team member had access to the quality management plan.

C.

Obtained external training in quality assurance (QA) for the new team member.

D.

Made sure that the new team member understood all of the requirements.

A project manager is in the beginning stages of delivering a project and is assessing and prioritizing identified risks. What should the project manager do next?

A.

Plan the risk responses and assign risk response owners.

B.

Start monitoring and controlling the identified risks.

C.

Proceed with executing the risk management plan.

D.

Spend the contingency budget on the identified risks.