Total 1988 questions

A project needs to be outlined as a phased approach for multiple product lines with a review gate at the end of each phase. To ensure consistency for this hybrid delivery, what should the project manager do?

A.

Ask subject matter experts (SMEs) to provide a detailed plan for each phase.

B.

Commit to a detailed global plan from the initiation phase.

C.

Get agreement from stakeholders on high-level deliverables and requirements.

D.

Request the project management office (PMO) to review the initial plan

A project manager has just taken over a project that is halfway through its schedule. In a brief meeting with the client’s key project team, the project manager receives several requests from a specific client team member who was not at the project team meeting. The requests for information seem to be for trivial information that was previously submitted in project documents.

What should the project manager do first?

A.

Send an email to the client team member explaining that they have the information already.

B.

Review the stakeholder register to gain insight into the expectations of that team member.

C.

Inform the client project manager that they are sending too many trivial requests.

D.

Update the project risk register to include potential delays in answering these requests.

A project manager is assigned to a hybrid project involving multiple sectors. The sectors collaborated in the joint venture delivery facility.

The chief executive officer (CEQ) from each participating sector is a sponsor of the project. Each sector nominated project representatives, who in turn appointed a product owner who was the most experienced in delivering such projects.

Match the stakeholders on the left with the appropriate frequency for updates.

The project management office (PMO) assigns a project manager who specializes in hybrid approaches to a predictive project that is off track from both the cost and schedule perspectives. The project runs into further delays as the project manager is ramping up on the project. The stakeholders and ask senior management to replace the project manager.

How should the project manager approach this situation?

A.

Meet with the stakeholders to understand their concerns and define an action plan to resolve issues.

B.

Continue to work on the project until the stakeholders and management come to a decision.

C.

Socialize with the stakeholders to better understand their needs and reset expectations.

D.

Escalate the stakeholder issue to the management team and ask for help with resolving the conflict.

A contractor has been making small changes to the engineering specifications without submitting change requests. The contractor and the technical team did not discuss the changes with the project manager, and the modifications do not affect the budget and quality of the deliverable.

What should the project manager do?

A.

Report the violation to the change control board (CCB) and seek comprehensive

approval for these modifications.

B.

Update the change management plan to define the level of control required for

these types of modifications.

C.

Ask the quality control team to evaluate the modifications, but take no action

because the associated quality risks are insignificant.

D.

Request the engineering team to update the specifications to reflect the modifications made by the contractor.

A Scrum team is analyzing the burndown chart on day four of a 15-day sprint. The burndown chart is shown below. What should the team do next?

A.

Continue with the sprint as the progress shows buffers for potential interruptions.

B.

Ask the product owner if some low-priority stories could be cut from the sprint.

C.

Continue with the sprint work as planned and keep monitoring.

D.

Ask the project team to select any additional stories as they have additional capacity than planned.

A company is transitioning from a predictive to agile delivery of projects. Based on

the requirements, the project team estimates the budget and decides to use a fixed-price

contract with its vendor. However, during the execution of the project, the requirements

evolve and priorities start to change constantly, which puts the project and the estimate at completion (EAC) off by 40%.

What should the project manager do next?

A.

Send a detailed status report highlighting the issue with funding to all of the stakeholders.

B.

Submit a change request to the financial manager to increase the funding and continue as is.

C.

Meet with the stakeholders to recommend the use of a time and materials (T&M) contract to address the problem.

D.

Wait until the next gate review meeting to highlight the risk of low funds to the stakeholders.

After a performance review, a team member approaches the project manager and asks for feedback. The project manager mentions anecdotal information about this team member being a positive team player and generally getting their work done on time, even though they have been late with work once or twice. The team member expresses frustration at not having better information included in the annual performance review.

What should the project manager do to prevent this frustration going forward?

A.

Request the human resource (HR) department to provide the key performance indicators (KPls) that were defined for this project.

B.

Set team performance goals and explain how the team receives the same performance scores.

C.

Review the key performance indicators (KPIs) for this team member and remind the team member how they are determined.

D.

Provide the team member with velocity tracking tools and explain how the team member can see and track performance.

During project execution, a project manager discovers that the budget at completion has shifted significantly and is higher than expected.

What should the project manager do?

A.

Adjust the original budget estimates with the current cost variance.

B.

Negotiate the project changes and adjust stakeholder expectations.

C.

Perform a root cause analysis of the project performance.

D.

Review the activity duration to reforecast the project completion date.

A project manager is working to create a product that can be released to the market as soon as it passes rigorous quality standards.

Historically, the company has used a predictive methodology, but the company is exploring the implementation of agile methodologies.

The company asked the project manager to explain the value gained by using an agile process.

How should the project manager respond?

A.

Early value cannot be achieved until the product is fully released.

B.

Early value can be gained by testing the most important features in the initial stages to fix deviations.

C.

Early value will be gained only if beta products can be released to the market.

D.

Early value will be gained only if the speed can be increased to release the product to the market.

An agile project has just started, and the backlog is being prioritized. The

customer wants to prioritize business value over identified risks.

How should the customer’s request be managed?

A.

Accept risks as they decrease over a period of time.

B.

Create a risk value profile to track the relative importance of risks.

C.

Log and track risks separately as only business value is important.

D.

Assess risks together with business value during prioritization.

A project manager works for a large software development company that has multiple strategic business groups. The project manager has been assigned to develop maintenance planning software for a power plant. The project manager heard that a similar project that was executed by another business group in the company recently failed. The project manager is concerned about the project's performance and wants to take steps to help the project succeed. What should the project manager do?

A.

Evaluate the project risk and try to replace the project with another one within the organization.

B.

Inform the project sponsor about the risk and try to convince them to withdraw the project.

C.

Study and apply the lessons learned from the failed project so that this project does not follow the same pattern.

D.

Continue executing the project using the project manager's usual methods as all projects are unique.

On a project to create the perfect paper airplane, the development of the airplane Is performed In iterations. The artwork to go on the wings and tail is done using a predictive approach. One of the stakeholders provides a requirement that conflicts with the product owner's requirements.

Who is responsible for analyzing the new requirement and making the final decision?

A.

Project manager

B.

Scrum master

C.

Project sponsor

D.

Product owner

During a project review meeting, several project team members expressed that they did not have an understanding of the benefits of certain features for the project What should the project manager do next?

A.

Review the project scope statement

B.

Confirm ownership for ongoing value realization

C.

Escalate the issue to the project sponsor

D.

Appraise the stakeholders of value gain progress

On a transformational project, the project manager is confronted with resistance

from the stakeholders. To overcome this and gain acceptance of the change, what should

the project manager do first?

A.

Escalate the issue to the project sponsor.

B.

Review the stakeholder engagement plan.

C.

Update the issue log.

D.

Neutralize the negative stakeholders.

A software system is being built for a company. Once the system is in production, the team would like to collect usage data to evaluate the delivered value.

Which evaluation practice should the project lead use to obtain accurate usage data?

A.

Send out a questionnaire to all users regarding the most useful features.

B.

Embed a feedback form into the system for users to respond.

C.

Interview a sampling of users to obtain the usage data.

D.

Build the functionality in the software to collect the operational usage data.

A project manager has been asked to participate in the procurement process for a

software application that allows customers to buy online e-learning courses. The project

manager will take over the project once the supplier has been sourced.

What should the project manager do before the project starts?

A.

Ensure that the requirements for the project are understood and that the objectives

are verified before approval of an agreement.

B.

Inform the project sponsor that once the agreement has been signed, there cannot

be any changes to the scope of the project.

C.

Notify the project sponsor that the project manager cannot be involved in the

agreement negotiation process.

D.

Ask the project sponsor to involve the legal department in the negotiation for the project agreement.

A project manager is transferred to another country to perform a project within their organization. What should the project manager do first to ensure collaboration within the team for a successful delivery?

A.

Determine a leadership style that is suitable for that location.

B.

Check if resources from headquarters can also be assigned to the project.

C.

Mentor the team members to perform project management.

D.

Assign a local resource to manage communication with the team.

The project manager has initiated the project and the team's roles and responsibilities have been assigned. In preparation for the development of the project management plan, the project manager reviews lessons learned from previous projects and discovers that the same team has been missing delivery dates.

What should the project manager do to ensure timely delivery?

A.

Ask the team leader to assign other resources.

B.

Update the issue log.

C.

Include this in the risk register.

D.

Escalate the issue to the functional manager.

A project is successfully delivering its product outcomes, and the customer satisfaction rating is high. However, during an internal audit, it is discovered that certain essential process documents and approvals are missing, and the project is evaluated as being noncompliant.

What should the project manager do next?

A.

Review the latest project management standards with the project management office (PMO) and make changes to the quality management plan.

B.

Perform quality assurance to review the processes against the quality management plan and identify gaps.

C.

Review and update the project document repository with the missing documents and approvals.

D.

Change the quality management processes to align with the project objective.

A Scrum team working in an aircraft manufacturing company has completed Its first iteration for a critical project. It is very Important for the project sponsor to complete the project on time and under budget A burndown chart indicates that the project is behind schedule

Which two actions should the project manager take to manage Impediments and improve the team's velocity? (Choose two)

A.

Look for processes that cause bottlenecks and slow down the team's agility

B.

Assign the items with high complexity lo senior developers

C.

Empower the learn to make decisions to remove impediments

D.

Work with the team to remove impediments as quickly as possible

E.

Move the items with high complexity to the last iterations

A project using a hybrid approach to migrate from a current system to a new and

enhanced system is underway. The plan is to migrate the system in stages. However, the

operations team is complaining that they are not ready to start supporting the new system.

How should the project manager effectively approach this situation?

A.

Create a lessons learned register to include operations team training for future projects.

B.

Include knowledge transfer sessions between the project and operations teams at every stage.

C.

Change the project management plan to add a final stage for product handoff to the operations team.

D.

Prepare detailed documentation to be shared with the operations team during project closure.

A project manager notices that the team lacks a subject matter expert (SME) in a specific area. This expertise will be required for many future projects.

What should the project manager do?

A.

Seek help from the project sponsor to get an SME from another team in the organization.

B.

Provide an opportunity to one of the existing team members to become an SME.

C.

Hire a contractor from outside of the organization to continue with the project.

D.

Ask team members to document the issue and address it in the next project meeting.

A project needs to purchase a specific piece of equipment, as stated in the

project documents and approved by the project sponsor. The procurement division is

questioning the need to buy the specific brand of equipment and has suggested buying a cheaper alternative instead.

What should the project manager have done earlier in the project to ensure the purchase of the specific equipment?

A.

Communicated the project charter to the procurement division

B.

Included a procurement division member on the project team

C.

Reminded the project sponsor about the procurement division's reputation

D.

Communicated the project management plan to the procurement division

The vendor for a new IT data center project failed to follow the required cabling standards as stated in the requirements specification. The infrastructure manager and vendor were involved in an argument about the issue.

What should the project manager do to resolve and prevent additional arguments?

A.

Monitor the interactions between the vendor and infrastructure manager going forward.

B.

Host a meeting with the vendor and infrastructure manager to help resolve their disagreement.

C.

Escalate the issue to the sponsor so appropriate action can be taken.

D.

Instruct the vendor to correct the problem without additional arguments.

An agile project team is building a new product. The stakeholders require ongoing

illustration of project business value.

How should the project manager proceed?

A.

Prepare performance value reports for the business on an ongoing basis.

B.

Include demonstrations of the built portion of the product at the end of every sprint.

C.

Prepare a project report for the stakeholders and distribute it weekly.

D.

Confirm the minimum viable product (MVP) and demonstrate it to the business when it is ready.

The team architect resigned from the company. The new architect points out a

design flaw during a planning meeting that may potentially impact the final quality.

What should the project manager do first?

A.

Review the scope management plan.

B.

Update the design with changes.

C.

Request an architecture review.

D.

Update the quality management plan

An organization uses a hybrid approach to project management. A project manager has been assigned to an external project, project A, where two of the three modules in the project require machine learning skills. The only machine learning expert in the project manager's organization is engaged in an internal project, project B, that is about to end.

What should the project manager do?

A.

Prioritize project A over project B since A is an external project and B is an internal project.

B.

Plan projectA in sprints, starting with the module that does not require machine learning skills.

C.

Engage the human resource manager to employ a machine learning expert for project A.

D.

Plan project A to start at the end of project B when the machine learning expert is available.

While developing a new product, a key stakeholder expresses concern about

insufficient information on product feature requirements. The product team disagrees and

mentions that detailed requirements have been provided.

What should the project manager do to handle this situation?

A.

Organize a discussion with the product team to clarify the missing information.

B.

Redirect the stakeholder to discuss this request with the functional manager.

C.

Record the new requirements and ask the product team to develop them.

D.

Conduct new risk and scope analyses, identifying the missing information.

For an ongoing project, match the key performance indicators (KPIs) on the left to the correct categories on the right.

A company is moving its headquarters to another city. The project manager responsible for the assignment has been using a predictive approach during the transition. However, the information systems will be migrated using an agile approach. The project manager needs to decide which kind of control to sign with the vendor responsible for migrating the systems.

How should the project manager address this situation?

A.

Negotiate payment after all project migration is completed

B.

Sign a single agreement for the whole project

C.

Use fixed-price increments as user stories are completed.

D.

Confirm payment after each project retrospective

A new team member is hired and the training is taking longer than expected. This impacts the overall project performance.

What immediate action should the project manager take to improve the situation?

A.

Communicate this issue to the human resources department.

B.

Provide additional training to the new hire.

C.

Increase team cohesiveness by sharing information and experiences openly.

D.

Update the issue log and define the mitigation strategy.

A project manager was recently appointed to an agile project. The project will have a lot of visibility and impact for the company, so the project management office (PMO) manager wants to ensure that the project manager manages the risks correctly.

What should the project manager do?

A.

Implement the agile risk manifesto to ensure the proper tracking, analysis, and remediation of the project risks.

B.

Ask the product owner to act as a risk manager to assist with the remediation of risks.

C.

Implement the role of an agile risk manager to take care of the risk management process.

D.

Follow the risk management process while ensuring that risks are identified, analyzed, and managed during each iteration.

In a global project, the project manager has to plan and manage communication between the team members and stakeholders in order to ensure the project will remain on track and achieve its goals.

What should the project manager do?

A.

Consider cultural differences among stakeholders.

B.

Conduct an integration meeting among all stakeholders.

C.

Schedule communication training for management-level stakeholders.

D.

Understand how political aspects can affect the project.

When reviewing the project team's performance the project manager realizes that the team velocity is not fast enough to meet the next review gate goal What should the project manager do?

A.

Increase the sprint duration to allow the team more time

B.

Prioritize the contents of the backlog and remove some stories

C.

Create a change request to modify the gate review goals

D.

Use the standup meeting to assess impediments and problems

A new facility project is being developed using a hybrid approach. After the third iteration, the project manager sees a decline in the team's productivity.

What should the project manager do next?

A.

Review the iteration duration with the team.

B.

Discuss the issue in the next retrospective.

C.

Encourage the team to improve their performance.

D.

Reduce the iteration backlog.

A project manager is assigned to a technical research project. The project team has

already been assigned, and the main subject matter expert (SME) sends the project

manager a list of the technical skills required for the execution of this project.

What should the project manager do next?

A.

Send the list to the project team and ask them to get training on the required skills.

B.

Ask the functional manager to review the resource pool and recommend the right individuals to join the team.

C.

Discuss the list with the project sponsor to confirm that the resources have the required skills.

D.

Meet with the project team to understand their skills and identify potential gaps and training requirements.

An important email from a project sponsor states that a backlog item should be immediately prioritized. What should the project manager

do with many tasks still open on the Kanban board?

A.

Decompose the item immediately and begin work.

B.

Discuss the impact of starting the item with the team.

C.

Finish the small tasks in progress before decomposing the item.

D.

Communicate the impact with the project sponsor.

A new project manager is assigned to a project in the execution stage. A few key stakeholders inform the new project manager that the project has some serious issues.

What should the newly assigned project manager do first to understand the issues?

A.

Escalate the issues to the project sponsor.

B.

Review the issues log to ensure the issues are captured.

C.

Check the risk management plan to ensure there is a strategy to address the issues.

D.

Ask the key stakeholders to discuss the issues with the project team.

A project leader of an agile team realizes that one team member is unmotivated, which is affecting the whole team. What should the project leader do to improve the situation?

A.

Invest in developing the team's emotional intelligence.

B.

Ask the unmotivated team member to take a short leave.

C.

Reduce the number of daily and retrospective meetings.

D.

Send the unmotivated team member to another team.

A project manager is preparing a project closure report. The project sponsor is confident about the success of the project, but the client is not sure that the project outputs will achieve their business needs.

Which aspect should the project manager highlight in the closure report to address the stakeholder's concern?

A.

How the quality was managed

B.

How the acceptance criteria were met

C.

How the scope was managed

D.

How the stakeholders were managed

A major project is unable to access the US$12 million funding allocated for the project. This prevents the start of the procurement process and is already leading to costly delays.

What should the project manager do?

A.

Escalate to the project steering committee.

B.

Invite the finance department to the next project demo.

C.

Review the project requirements.

D.

Use the currently available resources.

A global company hired a project manager for a new implementation at all of its sites After reviewing the business case and project charter, the project manager notes that the project team has different locations and regions to consider.

What should the project manager do to address this situation?

A.

Inform the steering committee of the situation and request additional resources.

B.

Coordinate virtual and face-to-face meetings at each site to improve communication

C.

Coordinate virtual meetings to assess the project team's communication needs

D.

Inform the project sponsor of this situation and request cultural orientation training.

A project manager for a building construction project is planning to go on vacation

midway through the project execution phase. What should the project manager do first to

ensure the team is empowered and deadlines are met?

A.

Allow the team to make decisions to stay on schedule.

B.

Postpone the vacation to a different time.

C.

Ask the project sponsor to make any necessary decisions.

D.

Analyze the impacts and create a plan for team decision making

A company Is helping their client launch an Innovative product. During the sprint review, the product owner identifies that the product does not include key features that were previously prioritized as part of the product backlog.

What should the project manager do next?

A.

Extend the sprint timeline so the learn can work on the missing feature.

B.

Inform the product owner that this issue needs to be escalated to the executive level.

C.

Collaborate with the product owner and the team to plan the following sprint

D.

Initiate the change request process to include these missing features.

A project manager is leading a council's project that aims to ensure full compliance with health, ecological, and environmental standards.

At the same time, the project's goal is to remain fully adherent to the council's values, policies, and procedures.

How should the project manager ensure project success?

A.

Enforce the project manager's authority over the contracting partner delivering to the council. by

B.

Engage a third-party consulting firm to oversee the project's implementation.

C.

Develop the necessary implementation plan and ask the partners to adjust their plans to meet the project manager's objectives.

D.

Meet with the stakeholders regularly to share project objectives and mutually agree on common goals and plans.

The business manager and the product owner are requesting a more flexible way to incorporate changes into the product baseline They are concerned about losing time to market with respect to other vendors

What should the project manager do?

A.

Review the assumption log and project management plan for changes.

B.

Identify adequate change management tools to conduct the project

C.

Establish a change control board (CCB) with key stakeholders.

D.

Allow key stakeholders to make some changes to deliver the product faster

A project manager is managing multiple teams. One team member complains to the project manager about the favoritism shown by a team lead to another team member and cites multiple instances.

Risk Response Strategies Analyze if someone else could contribute Record the observations and move ahead Check for options to exclude the stakeholder

What should the project manager do to resolve the team member's concerns?

A.

Use the withdraw/avoid technique to allow the individuals to resolve the issue between themselves.

B.

Use a problem-solving approach and set up a discussion with the team lead and team member.

C.

Establish guidelines for team leads to ensure that all team members are appropriately treated.

D.

Provide direction to the team lead on how to resolve the issue with the team member directly.

A project manager is using a hybrid approach for project delivery. The

development team was sized, but is not yet fully resourced. The project manager is working

on defining the project schedule.

What should the project manager do to address the issue of developer availability?

A.

Organize a planning session with the development team and use their estimations to complete the schedule.

B.

Ask the resource manager when the new contractor is available to start and change the delivery date for the project schedule.

C.

Ask the sponsor to provide the desired completion date for project activities and complete the schedule.

D.

Use expert judgment to estimate all of the tasks and complete the schedule in the allocated time.

A large organization decided to adopt an agile methodology based on the trends

seen in the industry. The organization invested a large amount of money in adopting it, but

after a few months, the implementation failed.

What should the project manager have done differently to avoid the implementation failure?

A.

Conducted agile training for all employees ranging from the project teams through

mid-level to upper-level management.

B.

Conducted a postmortem and captured the learning in organizational process assets

(OPAs) for future use.

C.

Assessed the organization's culture, performed a suitability analysis, and determined

the future state.

D.

Hired a third-party agile delivery team to do the implementation.