Summer Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmas50

PMI PMP - Project Management Professional (PMBOK 7th Version)

Page: 7 / 14
Total 2196 questions

A government agency is developing a new connectivity policy. The assigned project

manager is a famous economist with international recognition. The team is eager to work with

the project manager, but feels intimidated. The project manager realizes that a junior

economist, whose tasks are behind schedule, is especially intimidated by the situation.

What should the project manager do first?

A.

Evaluate the performance of the junior economist in the upcoming months.

B.

Reassign some of the junior economist ' s tasks to other economists.

C.

Request to replace the junior economist with a more experienced economist.

D.

Consider organizing paired work sessions for the junior and senior economists.

A protect manager is managing a project that will handle sensitive data for millions of users The sponsor mentioned that, lo their knowledge, the project does not seem to have any compliance requirements in their country.

What should the project manager do in this situation?

A.

Request expert advice from the compliance leader to confirm if there are any compliance requirements for the project.

B.

Check with The national compliance agency to determine if the project has any compliance requirements in this country

C.

Trust in the expertise of the sponsor and believe that there are no compliance requirements for this project.

D.

Conduct independent research regarding the data protection policy of the country for legal and regulatory compliance.

A project team member reads in a financial newspaper that the main project supplier is facing some financial difficulties and communicates this to the project manager. What should the project manager do?

A.

Add the situation to the project risk register to be managed

B.

Identify competitors that are qualified to replace the current supplier

C.

Inform the purchasing department that manages the supplier relationship

D.

Use the issue log to record the situation immediately

A company is moving to a hybrid approach and conducted capacity activities for all of the project managers. During these capacity-building activities, the focus was on agile approaches and team facilitation skills. When starting the implementation phase, the project managers faced issues motivating the newly hired agile staff.

Why are the project managers having issues motivating the agile staff?

A.

The capacity building activities missed the servant leadership concept transfer.

B.

Transitional periods normally cause this type of problem.

C.

The agile staff is not used to being led by a project manager.

D.

Project managers are expected to become coaches in agile teams.

A project manager working on a large-scale network implementation is frustrated

with the hardware supplier. Their deliveries have been consistently late and frequently do not have vital components. The project manager ' s company has decided to cancel the contract and move to a new supplier, but the only other option is an overseas company.

What should the project manager do first to proceed with this change?

A.

Engage the services of an interpreter who understands the project domain.

B.

Check social media to determine if there are any common connections that use the new supplier.

C.

Request assistance from the procurement department on the next steps.

D.

Become aware of any cultural characteristics of the new supplier that could impactnegotiation.

During the first project meeting with a new project manager, a stakeholder complains about not receiving periodic reports. What should the project manager do first?

A.

Add the stakeholder details into the periodic reports and update the project management plan

B.

Invite the stakeholder to all future project review meetings and update the project management plan

C.

Update the project management plan with the new information and inform all of the relevant stakeholders

D.

Meet with the stakeholder to better understand their expectations and update the stakeholder engagement plan

A project team consists of members based in country A and subject matter experts

(SMEs) based in country B with a 12-hour time difference. What can the project manager do

to improve interactions between the team members in both countries?

A.

Ensure full participation of both the product owner and business SMEs in scopeplanning sessions.

B.

Identify virtual communication methods and arrange for regular team meetingsaccordingly.

C.

Explore the opportunity to have both teams colocated.

D.

Plan for frequent face-to-face meetings.

A project manager is working with a team that is new to agile. One of the more

influential stakeholders struggles with the nature of agile. The project manager knows that this

stakeholder is needed as an advocate and wants to do everything possible to make the

stakeholder comfortable with the project.

What should the project manager include in the status report to illustrate the project ' s

performance?

A.

Results of the MoSCoW assessment

B.

Cost-benefit analysis

C.

Return on investment (ROI) analysis

D.

Earned value analysis (EVA)

An agile leader is working on a complex project that is entering the final phase where solutions from different vendors are being integrated. This is the most critical delivery stage for the project

How should the agile leader ensure successful delivery?

A.

Ensure participation from all team members

B.

Ask the client to attend all daily calls.

C.

Ensure cross-departmental teams are colocated

D.

Request additional project resources

On a project with multiple international locations, a trend for delays has been

flagged. When looking into the issue, the project manager realized that some of the key

activities were scheduled over the holiday periods in the overseas offices.

What should the project manager do next?

A.

Update the schedule to reflect the holidays and share the workload among offices tomitigate schedule slippage.

B.

Hire additional personnel on a temporary basis to cover the extra workload during theholiday seasons.

C.

Request that the offices in overseas locations work overtime to mitigate scheduleslippages.

D.

Update the schedule to reflect the holidays and notify the project sponsor of thedelayed completion.

A protect team has completed many iterations without proper sizing of the stories In some iterations the team sized some stories and completed them ahead of time In other iterations the team sized the stones but was unable to complete the planned activities

What should the team do differently during planning for the next iteration " ?

A.

Request the product owner and team facilitator to provide the size of the story

B.

Average the story points provided by each team member for a story

C.

Continue multiple rounds of planning poker and arrive at the size of the story

D.

Collaborate with different teams and arrive at the size of the story

A project manager is assigned to a digital transformation project for a bank. The company culture is conservative and resistant to transformation or innovation. What should the project manager do first to support the transformation ' '

A.

Provide a digital transformation guide and explain that the change is unavoidable

B.

Ask the bank executives to officially announce that the project manager is leading the project

C.

Provide proper training sessions to the stakeholders so they understand the purpose of the change

D.

Hire an expert in digital transformation and assign that person as the champion for the change

During the forming phase of a project team a project manager implements several team-building initiatives and decides it would be fun to have improvisations theater activities. After the sessions the project manager received feedback from some key team members who felt that although the activity was fun it was not appropriate for the purpose of team building.

What should the project manager have done to avoid this negative feedback ' ?

A.

Assessed and analyzed personality indicators from the project team

B.

Sent the activity details to everyone involved prior to the session

C.

Communicated the decision to conduct this activity to the key team stakeholders

D.

Selected a vendor for the activity according to the procurement management plan

The marketing team is moving from predictive to hybrid approaches for their projects. The marketing director is not familiar with hybrid approaches and does not support the new direction. What should the project manager do?

A.

Advise the marketing director to receive formal training.

B.

Ask the marketing team members to coach their director.

C.

Train the marketing team and keep their director informed.

D.

Mentor the marketing director on the approaches.

A project manager learns from a marketing analyst that a competitor just published a press release announcing a product launch using a specific innovation The project manager is concerned because the company is initiating a project involving the same innovation A key goal of the new project is that the product will be the first to market won the innovation

What should the project manager do next?

A.

Document the issue in the issue log and escalate to the project sponsor

B.

Inform the project sponsor and suggest canceling the project

C.

Review the project goals and eat criteria m the project charter

D.

Ask the leader of research and development to decide on next steps

A financial company is developing a new application for mobile banking using a hybrid approach The project is delayed as the product concept has not yet been developed to the key stakeholder s satisfaction despite multiple design iterations. The key stakeholder has now started participating in all daily standups. The project manager has observed that the key stakeholder ' s presence has had a negative impact on the team ' s morale, while also impacting productivity

How should the project manager ensure that the stakeholder s issues are addressed effectively without impacting the team?

A.

Set up a meeting with the stakeholder to address their concerns directly

B.

Move to a predictive design-and-requirements gathering approach

C.

Talk to the team separately to address the stakeholder ' s concerns

D.

Schedule a team retrospective and invite the stakeholder

During the planning for a long project, the project manager recognized that several

members of the team are new to their roles. How should the project manager incorporate this

into planning?

A.

Increase the overall project duration to account for the inexperienced team memberson the project.

B.

Ensure planning has accounted for replacing team members in new project roles whodo not deliver on project goals.

C.

Assess the training requirements and ensure time for professional developmenttraining by senior members.

D.

Revisit the project resource allocation to remove the inexperienced team membersassigned to the project.

An agile project has a documented list or requirements prioritized in high, medium, and low categories. The project team has expressed that it is difficult to know what to work on next as so many items are listed as high priority.

What should the project manager recommend?

A.

Ensure the product owner determines the priority based on a product roadmap. release plan, and iteration plan.

B.

Ask the team to prioritize the high-priority items based on what they feel is a logical sequence to build.

C.

Ask the team to prioritize the high-priority Items based on the release plan and what allows tor testing most effectively.

D.

Discard the current categorization of requirements as high, medium, and low and prioritize numerically.

A project manager is managing two integrated projects in a program A key integration point is misaligned, which has resulted in delays. One of the team ' s integration leads is a subject matter expert (SME) m this integration area. The other team ' s integration lead is not a SME but is more senior and has worked on the project longer Both team leads are blaming each other

What should the project manager do first to resolve this situation?

A.

Assign the resolution of the issue to the senior integration lead who has worked on the project longer

B.

Meet with both integration leads to understand the root cause and determine a resolution

C.

Escalate the issue to the program architect who developed the integration plan

D.

Assign the resolution of this issue to the integration lead who is a SME

A project manager is defining the sprint goals with the team, A team member who is responsible for acceptance testing starts criticizing the goals and cannot come to an agreement with the other team members.

How should the project manager handle this situation?

A.

Request to meet with the team member and ask that any issues be escalated separately.

B.

Reprimand the team member and provide immediate coaching on goal alignment.

C.

Proceed with defining the goals with the team members given the majority approval from the team.

D.

Approach the team member with empathy and obtain agreement through collaboration.

A project sponsor asks the project manager to explore a hybrid approach for a new

project. The product manager for this project has already prepared a detailed specification for the product.

What should the project manager do to proceed with the project management plan?

A.

Ask the team to assess whether the product specification can be expressed in userstories to enable a Scrum or Kanban approach.

B.

Explore with the product manager to determine if there are viable opportunities todeliver value incrementally and increase business value.

C.

Recommend to the project sponsor that a predictive approach is appropriate for theproject due to the stable product requirements.

D.

Ask the product manager whether they are prepared to act as product owner for theproject in order to participate in iterative planning and reviews.

Two learn members are consistently having misunderstandings and find it difficult to work together. How should the project manager handle this situation?

A.

Remove one of the team members

B.

Identify the issues between the team members and guide them toward a resolution

C.

Warn the team members about their behavior

D.

Train the team members on communication techniques and interpersonal behavior

A protect manager is struggling to obtain participation from key stakeholders who do not usually attend project meetings What should the project manager do1?

A.

Distribute the communications management plan

B.

Reschedule meetings lo align with the stakeholders ' availability

C.

Escalate the issue to senior management

D.

Set clear meeting expectations by sharing agendas in advance

A project team is reviewing solved project issues from the last phase of a project. The lead risk analyst points out that the next phase of the project includes a critical element with some

reserves needed

What should the project manager do to successfully complete the next phase?

A.

Request a reserve analysis and update the risk management plan

B.

Update the risk response plan to include the needed reserve

C.

Perform a schedule network analysis to avoid any critical path delays

D.

Review the risk response plan to verify inclusion of the needed reserve

In a software project using an agile approach, there have recently been work

overruns. After assessing the situation, the project manager concluded that the overruns are

occurring because of insufficiently refined product backlog items.

What should the project manager do to correct this issue?

A.

Work with the sponsor to revise the product vision.

B.

Create a definition of ready (DoR) for the backlog items.

C.

Discuss the issue with the service request manager.

D.

Refine the product backlog items with the stakeholders.

A project manager entered into a contract with a vendor to build a new system. During the acceptance test stage, the project manager noticed that the system quality was not satisfactory-How should the project manager support their claim to the vendor?

A.

Share unsuccessful results from previous projects with a similar scope

B.

Provide the failed test results along with the agreed-upon acceptance criteria

C.

Show that the acceptance criteria were changed by the vendor without approval.

D.

Document in the risk log that the issues in the system were already identified

The main project stakeholder was fired and replaced by another stakeholder. The

new stakeholder reviewed the project scope and requested numerous changes, arguing that

the stakeholder ' s team is unhappy with the results to date.

What should the project manager do?

A.

Put the new requirements in the backlog with high priority and implement therequested changes.

B.

Put the new requirements in the backlog and submit a formal change request forapproval.

C.

Put the new requirements in the backlog and let the product owner check their valueand priority.

D.

Put the new requirements in the backlog with low priority and implement the requestedchanges.

A project manager is leading a project that is on time and under budget. In the

weekly meeting with the team, the project manager finds out that one of the tasks due next

week does not have an assigned resource available for it. The resource is currently assigned

to another project.

What should the project manager do to manage the situation?

A.

Ask the procurement department to supply a different resource.

B.

Change the schedule according to the availability of the resource.

C.

Ask the sponsor to obtain the resource as originally planned.

D.

Contact the other project manager to request the resource.

An ongoing project is facing a challenging situation where the customer is not satisfied. The team is new to agile development and frequently communicates with the customer and gives regular status reports. What should the project lead do to satisfy the customer?

A.

Reduce frequent communication and improve the status report format to include team progress

B.

Schedule a meeting with the customer and explain the team is new to agile and the situation will improve

C.

Review the situation with the customer and make the required adjustments with the team

D.

Review project progress with the customer and modify the frequency of sprint review

A project manager for an iterative project received feedback from an on-site team member that the virtual team was not meeting the deliverables on time. The project manager gathered details on what the status report should contain m order to track deliverables

What is the remedial action the project manager should take?

A.

Perform stakeholder engagement with the virtual team

B.

Add status reports to the communications management plan

C.

Convene an on-site meeting for both of the teams

D.

Add status report creation as a product backlog item

A company is engaged in a transformation journey, and the project manager for this endeavor is new to the project. During one of the project status update meetings, a key stakeholder, who is also the project manager’s functional manager, is dissatisfied with the work in progress and points to the project manager.

What should the project manager do?

A.

Show the functional manager that the progress is on time based on the schedule.

B.

Admit that the functional manager is right and promise to rectify the situation immediately.

C.

Schedule a one-on-one meeting with the functional manager to prove the project is on time.

D.

Listen carefully and show understanding of the growing needs of the functional manager.

An organization that is running several simultaneous projects suddenly experiences a surge of resignations, leading to a lack of talent. Consequently, some of the projects have been missing key milestones. What should the project manager do to recover from the delays?

A.

Reduce the projects’ scope to meet the upcoming target dates.

B.

Crash the schedule from the delayed projects to meet upcoming target dates.

C.

Fast-track the delayed projects so they can meet upcoming target dates.

D.

Ask for project sponsor approval to revise the upcoming target dates.

A project to add metro stations is being executed, with seven out of eight stations currently in place. Suddenly, a notification from the local community is received demanding the project be stopped. What should the project manager do first?

A.

Meet with project stakeholders to define a mitigation plan

B.

Register the issue and escalate it to the project sponsor

C.

Estimate the cost of changing the project location

D.

Execute the contingency plan defined in the risk management plan

The execution stage of a construction project is beginning. There are many areas and phases to be built. The project team wants to review the relationships between the most important tasks to ensure that major items are executed properly during this stage. What project artifact should the project manager review with the team?

A.

Project milestone chart

B.

Project schedule management plan

C.

Project statement of work (SOW)

D.

Project program evaluation review technique (PERT)

A project manager is leading a project with a negative risk that has just become an issue. The risk has been recorded, and a response plan has been set. However, a project team member proposes a response that differs from the response recorded in the risk management plan, which the team member believes will be cheaper and equally effective.

What should the project manager do?

A.

Evaluate the new proposal with the project team to determine if it is a more beneficial alternative.

B.

Adhere to the issue response proposed in the risk management plan, as it is the agreed-upon solution.

C.

Ask the project team member to write a formal email explaining the proposal and send it to the change control board (CCB).

D.

Implement the new proposal as soon as possible, as it is supposed to be cheaper and equally effective.

During daily team coordination meetings, team members constantly ask which tasks they should focus on first.

How should the project manager ensure the team is fully productive?

A.

Encourage project team members to prioritize the product backlog.

B.

Work with the product owner to ensure the project backlog is prioritized.

C.

Ensure team members are working according to the project management plan.

D.

Review the project backlog during the team’s coordination meeting.

During the initial phase of a construction project, the team is confused about the safety requirements it needs to consider during implementation. The project manager recently met with the client to define the project scope. How should the project manager share this information?

A.

Distribute the safety requirements during the project execution phase

B.

Modify the project charter by including the safety requirements

C.

Send an email to the team with the details of the safety requirements

D.

Meet with the team and present the scope of the safety requirements

During a blueprint review meeting, the finance department representative is not comfortable with a proposed solution that favors another department. As a result, document approval is delayed and impacts the project schedule. What should the project manager do?

A.

Work with the project team to find a compromise solution that suits both departments

B.

Schedule a meeting with the project sponsor to seek advice on the approach of both departments

C.

Arrange a meeting with the two departments to understand their differences and address their needs

D.

Assess the risk of postponing this specific solution and advise both departments of the delay

It is taking several additional iterations for a project team to complete planned backlog items. The project manager notices that some of the features are not meeting the iteration-level definition and must be placed back into the backlog.

What should the project manager do?

A.

Put more emphasis on the definition of done (DoD).

B.

Extend the iterations to complete the items.

C.

Review and update the acceptance criteria.

D.

Address the required changes in the next release.

Near the closing stage, a project is delayed due to staff shortages. In order to meet the mandatory deadline, additional resources are necessary, but there is no additional budget. What should the project manager do first to obtain the funding to hire the needed resources?

A.

Ask the sponsor for additional financial resources

B.

Introduce a change request

C.

Use management reserves

D.

Update baselines to accommodate the delay

A project manager is executing a project on time and on budget. Before a stage gate review, the project manager receives the regular business management report, but this time it indicates a negative impact on the project success factors. What should the project manager do?

A.

Continue with execution since the project was successful up to this phase

B.

Call for business development to revalidate inputs at the next stage gate

C.

Provide the necessary analysis to enable examination of the business value

D.

Request a delay to the stage gate until business development provides the next update

During the requirements gathering and analysis stage for the project, the team members are debating some functionality issues that are expected to be included in the scope. Due to this discussion, the planning activity for the scope definition is running late. What should the project manager do?

A.

Timebox the team members’ debate to ensure the activity is completed on time.

B.

Review expectations with all team members who are working on this activity.

C.

Discuss the issue with the team members who are delaying the activity.

D.

Ask team members to document all points that will need to be refined later.

A project manager has been assigned to a new agile project with a lot of rapidly changing knowledge areas.

How should the project manager manage knowledge transfers on this project?

A.

Request the stakeholders to completely document all the domain knowledge before starting the project.

B.

Ask the project team to set up the initial sprints to transfer domain knowledge before focusing on the deliverables.

C.

Work with the quality assurance (QA) team to make sure all domain knowledge is being transferred properly among stakeholders.

D.

Mentor the team and stakeholders to ensure domain knowledge is being exchanged properly among them during sprints.

A project manager has been assigned to a new agile project with rapidly changing knowledge areas. How should the project manager manage knowledge transfers on this project?

A.

Require stakeholders to fully document all domain knowledge before starting

B.

Mentor the team and stakeholders to ensure domain knowledge is exchanged during sprints

C.

Ask the team to set up initial sprints for knowledge transfer before focusing on deliverables

D.

Work with QA to ensure domain knowledge is transferred properly among stakeholders

One member of the project team has the necessary skills to execute a critical feature of the product. However, another team member wants to take on the challenging task.

What should the project manager do?

A.

Assign the task to the less experienced member to help improve their skills, with the support of the experienced member.

B.

Schedule a meeting with both team members to let them discuss the best course of action.

C.

Encourage both team members to collaborate and work using their respective strengths to deliver the project.

D.

Negotiate with the customer to postpone the particular feature to resolve the situation between the team members.

A project manager is leading a hybrid project. A project team member has not been delivering on time; as a result, the project is about to be delayed.

What should the project manager do?

A.

Negotiate revised timelines with the project sponsor.

B.

Revise the project schedule with the customer.

C.

Discuss the situation with the project team member.

D.

Schedule a meeting with the project team to address timelines.

A company started a project to create a new product that will be delivered in iterations. The artwork development plan included extensive consultation and validation before the build. The company changed the focus of the project to speed to market because one of their competitors announced the launch of a similar product. What should the project lead do?

A.

Work with the product owner to assess the impact and reprioritize the product backlog.

B.

Schedule a meeting with the project sponsor to identify and allocate additional resources.

C.

Submit a formal change request and obtain approval from the change control board (CCB).

D.

Meet with the Scrum Master to determine if the development cycle can be reduced.

A project manager takes over a project team and notices that the team members always wait for management to make decisions during team meetings. In previous work, the project manager discovered that a team is more committed to the deliverables when team members make decisions themselves. However, this team is not willing to be put on the spot.

What should the project manager do?

A.

Encourage the team to start making one decision in every meeting.

B.

Develop decision-making behavior, such as team key performance indicators (KPIs).

C.

Continue the current practice as long as the team members can still perform.

D.

Understand the team members’ obstacles and discuss means of improvement.

Just as a team reaches a mutual consensus on a preferred design, a stakeholder submits a request to add new features that enhance the company’s competitive advantage.

What should the project manager do?

A.

Start the process to include the new features of the product in the next iteration.

B.

Reject all requested changes and bypass the company’s change control process.

C.

Encourage the project team to add premium features to impress the client.

D.

Allow all requested changes and bypass the company’s change control process.

A project manager has been tasked with developing a project schedule with fully detailed requirements. The project manager reaches out to subject matter experts (SMEs) for their initial thoughts on task duration. The project manager is concerned when these estimates appear to differ significantly. What should the project manager do to help with the estimate development?

A.

Ask the SMEs to hold up cards that show their estimate, discuss the highest and lowest estimates, and then estimate again.

B.

Recommend using an iterative approach, with a focus on estimates, that the SMEs agree with.

C.

Use historical information to help guide the estimates that were proposed by the SMEs.

D.

Escalate to the project sponsor and explain the differences in the estimations coming from the SMEs.