PMI PMP - Project Management Professional (2025 Version)
A project is in the execution phase. The client was actively involved in the early stages but has been less engaged lately. A number of changes to the requirements have
recently been requested.
What should the project manager do next?
A new major project is starting that consists of two interconnected subprojects. One of the subprojects was assigned to a contractor who commits to submitting biweekly status reports and attending weekly integration meetings. Halfway through the project, the contractor stops participating in the meetings and does not submit the reports. Their excuse is that these activities are consuming too much time.
How should the project manager handle this situation?
A senior project manager is working for a company that is not yet making a profit. However, the company has many innovative projects in development. Most of the project
time lines have slipped, and the staff is overwhelmed .
What should the project manager do to help the company meet their financial objectives?
A facility extension project is in the execution stage. There is a project activity to connect the power of all new equipment to an existing facility,
Point A, which requires a significant cable length. The construction team found that the power could be connected to Point B and save money.
What should the project manager do next?
A company wants to show the commercial advantages of a product in a competitive market. They commissioned a project team to create a prototype. The team is building the prototype incrementally.
What should the project manager set as a priority?
In a daily standup meeting, a project manager notices that a team member's reports include incomplete tasks with no impediments. A colleague informs the project manager that this team member is experiencing a personal issue.
What should the project manager do?
A project is behind schedule because of a delayed equipment installation. This is affecting many other activities. The manager responsible for the
equipment delivery notified the project manager that there is a capacity issue for the team doing the installation.
What should the project manager have done to prevent this situation from happening?
Drag the communication event on the left to the main subject discussed during the event on the right.
A company was acquired, and the new company management asked the project manager to begin using a specific set of metrics immediately to measure team performance. The project manager is working on a predictive project and thinks this request will distract the team and delay the project.
What should the project manager do first?
A project manager is performing earned value management (EVM) for a cross-country pipeline project. The project manager has determined the ratio of earned value (EV)
to actual cost (AC) for the project and has found the calculated result to be 0.9024.
What does this value mean for the project?
An agile project will be delivered to a client based on a fixed price in cryptocurrency. Due to the volatility of cryptocurrency, both parties have
agreed to adjust the scope to the value of the cryptocurrency at the end of every iteration and halt the project when the agreed price is reached.
Which approach should be used in this situation?
A client wants to create an innovative software for the travel industry using an agile approach. A project manager from the company was assigned
to work on the details and estimates as requested by the client.
What should the project manager do before sending the information to the client?
A project management office (PMO) director finds that the project managers leading software development projects are not consistently seeking approval from other division leaders in cybersecurity and operations before deploying code into production. The PMO director asks the project manager to develop a solution for this issue.
What should the project manager do to fix this problem?
A human resource (HR) acquisition process for a large project has recently changed. One major process change includes the approval of the financial manager and the recruitment manager. This change to the process implies longer processing. The project urgently needs new resources.
What should the project manager do?
An agile team is geographically separated across multiple continents, and the project manager is in the process of identifying the tools to manage the communication among the virtual teams. Drag the appropriate tool on the left to each project task on the right.
A project manager has just received communication from an operational functional manager to complete an additional scope item for a project that was formally closed a few weeks ago. The scope looks relatively small and simple to handle as part of the daily operations activity.
How should the project manager deal with this request?
A project has been reporting a declining schedule performance index (SPI) for the past four reviews. No corrective action is under development, and the project team does not seem concerned.
What should the project manager do first to address the SPI trend?
A project manager has been assigned to lead a project with limited funding and resources. During the requirements brainstorming session, several stakeholders request a long list of requirements for a new project, which exceeds the budget.
What should the project manager do first?
A project manager has been approached by the project sponsor about adding to the project scope How should the project manager accommodate this request?
A project team member, who is inexperienced in system development work is not performing well. Currently, there are no other staff members
available who are qualified to complete the work.
What should the project manager do?
After the demo on a software project, one of the key stakeholders contacted the scrum master and complained that they were unaware of changes made to the project. After checking, the scrum master learned that the stakeholder's details were incorrectly entered into the register.
What should the scrum master do?
A project manager is part of an organization that is assessing the use of agile delivery approaches. A new project management office (PMO) manager who had a bad experience with a Scrum approach recommended that the project board replace Scrum with a predictive approach.
What should the project manager do?
A project manager is preparing to start a new project in which the team members are distributed geographically across different countries. The project manager is using the communications management plan to engage the team members and find a communication method that suits everyone.
How should the project manager continually evaluate the effectiveness of the virtual team's engagement?
A project manager is working on a complex project with a high degree of change. What strategy should the project manager use to ensure a
successful project completion?
A project manager is leading a project that has a dependency on the client's vendor management system for critical requirements. The vendor
management team will not derive any benefits from the project. However, the project requires support from the vendor management head.
What should the project manager do next?
Drag the items on left side to the matching term within the correct project approach on the right side.
There is a conflict on an agile project about following organizational processes, many of which do not add any value to the project. To resolve this, which one of the following
should be regarded with the highest priority?
In a frequently changing project, the project manager discovers a customer requirement change during a daily meeting. What should the project manager do?
Eight highly qualified experts have been assembled to work for a 6-month period on an a specific aspect of an organization's product development process. How should the
project manager support this team to succeed?
A project manager works for an organization that intends to begin using agile delivery, but there is a lack of support from some business units. The project manager needs to address the lack of trust in agile.
What should the project manager recommend?
There are two interdependent projects: the first project is in execution, and the second one is about to be deployed. The first project has been delayed, which is now affecting the second project due to the sharing of resources.
What should the project manager do in this situation?
A project scope statement has been approved, and the project manager and core team have been assigned to the project. Suddenly, the project
manager takes a temporary leave of absence due to a medical emergency. While the project manager is on leave, the team develops the project
schedule. When the project manager returns, a detailed schedule is almost complete.
What should the project manager do?
At the end of a project's initiation phase, the budget was developed and sent to the approval board. During the approval meeting, one of the key stakeholders asked how the budget was developed for future uncertainties.
How should the project manager reply?
During the early phase of a project, the requirements documentation was not approved. It was identified that the leader of a user party was not included in any of the requirements collection communications.
Which of the documents was likely missed or outdated?
A project team has developed the initial schedule using a network diagramming method and has arrived at the overall project duration. Upon examining the schedule, the project manager finds that there are several activities that may require buffers to mitigate or eliminate potential scheduling conflicts.
Match the following common terms with their explanations that evaluate the buffers or constraints.
A team decides to adopt an agile approach for their new project. During a sprint, the project manager realizes that there is a need to show progress and optimize the collaboration among teams.
Which tool should the project manager use?
A project manager who recently joined the company has been assigned to manage a software project for a major recurring customer. What should the project manager do to
enhance the budget estimations for the project?
A project team is transitioning from a predictive to an agile approach. The project manager is trying to minimize the support issues that the product has had in production.
One particular pain point is the transition to operations, where the issues usually arise.
What should the project manager do to improve this scenario?
A project is comprised of team members who are not engaged and committed to project success. What should the project manager do to address this situation?
A project manager is leading a project in which the product requirements have not been fully met due to several uncertainties about customer acceptance. What should the project manager do?
During a project's execution phase, two team members are having conflicts with other team members within the team on technical and interpersonal levels. Which two actions should the project manager take first to address this conflict? (Choose two)
A project manager was suddenly asked to take over an ongoing project without any handover. During the first meeting, the project sponsor raised concerns about whether the project was on track to deliver the intended benefits.
What should the new project manager do first?
An agile team is developing a new content management system. Some of the team members are struggling to deliver certain features since they have never worked on this type of solution.
What should the project manager do?
A project manager manages a bridge construction project. The project manager has received a major change request from a regulatory stakeholder to add one branch of the bridge to the engineering design. The project manager prepared a change request, which was reviewed and accepted by the change control board (CCB).
What should the project manager do now?
A project team has finished its first iteration out of six. The iteration's delivery performance (velocity) was 50%.
During the iteration retrospective, the team realizes that the complexity of the work was underestimated.
What should the project manager do?
A project manager is appointed to a project that has just been approved. The project manager has extensive experience in hybrid projects, and the project team has performed many projects within a predictive framework. However, the project sponsor believes that the project needs to be executed using agile approaches.
What should the project manager do to select the most effective project framework?
A project manager is assigned to a regulatory project for their country. The deadline for delivering results in compliance with the new laws is very tight, and the project team members have not yet been assigned. One of the project manager's peers informs the project manager that a project with the same scope for a different country was completed 1 year ago.
What should the project manager do first?
An organization is about to start a multiphased project. Due to strict regulations, some of the phases must be completely planned in advance.
However, other phases allow for more flexibility and experimentation on scope and schedule. The sponsor wants to pursue the project objectives
as planned, but also wants to accommodate new information and changes as the project progresses.
Which project management approach should the project manager select for this project?
An organization is embarking on the deployment of a new digital solution that will revolutionize purchasing services The project manager has created all the necessary plans and activities to ensure a successful integration and solution launch There is a risk of a partner’s system being unavailable which could impact the project negatively
What key activity is needed to ensure the project's success?
A project manager is assigned to a new project to deliver a product at the end of the year. The project manager was informed by the vendor that a core component could not be shipped on time, which will impact the schedule.
What should project manager to do next to minimize the impact on the project?




