11.11 Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmas50

PMI PMP - Project Management Professional (2025 Version)

Page: 7 / 13
Total 2040 questions

A project is in the execution phase. The client was actively involved in the early stages but has been less engaged lately. A number of changes to the requirements have

recently been requested.

What should the project manager do next?

A.

Reject the changes and stay the original course as initially agreed with the client.

B.

Review the changes and make the decision based on the project team's recommendations.

C.

Discuss the changes with the client and jointly make the decision on how to proceed.

D.

Review the risk register to see if mitigations have already been outlined for this scenario.

A new major project is starting that consists of two interconnected subprojects. One of the subprojects was assigned to a contractor who commits to submitting biweekly status reports and attending weekly integration meetings. Halfway through the project, the contractor stops participating in the meetings and does not submit the reports. Their excuse is that these activities are consuming too much time.

How should the project manager handle this situation?

A.

Remind the contractor to join the meetings and submit their report as this is their commitment.

B.

File a claim for not fulfilling the contract terms in accordance with alternative dispute resolution.

C.

Compromise with the contractor to only attend the weekly meetings without submitting the reports.

D.

Assess the situation as a risk and reach out to the contractor to check the origin of this resistance.

A senior project manager is working for a company that is not yet making a profit. However, the company has many innovative projects in development. Most of the project

time lines have slipped, and the staff is overwhelmed .

What should the project manager do to help the company meet their financial objectives?

A.

Prioritize the projects, giving higher priority to projects that will increase profit.

B.

Make sure the project is fast tracked so that slipped time lines are recovered.

C.

Request that upper management hire additional staff to support the projects.

D.

Ensure that all of the projects are of high quality and are delivered on time.

A facility extension project is in the execution stage. There is a project activity to connect the power of all new equipment to an existing facility,

Point A, which requires a significant cable length. The construction team found that the power could be connected to Point B and save money.

What should the project manager do next?

A.

Perform a cost-benefit analysis to evaluate using the Point B option.

B.

Add the issue to the change log and request additional budget through the change control board (CCB).

C.

Seek a decision from the construction team after explaining the project budget and schedule constraint.

D.

Use the Point B option because it will save the project cost and time.

A company wants to show the commercial advantages of a product in a competitive market. They commissioned a project team to create a prototype. The team is building the prototype incrementally.

What should the project manager set as a priority?

A.

Implement the plan-do-check-action (PDCA) cycle.

B.

Deliver business value as soon as possible.

C.

Emphasize the use of Kanban methods.

D.

Ensure that the project sponsor knows the schedule.

In a daily standup meeting, a project manager notices that a team member's reports include incomplete tasks with no impediments. A colleague informs the project manager that this team member is experiencing a personal issue.

What should the project manager do?

A.

Coach the team member on how to keep work and personal issues scjparate.

B.

Ask the human resources (HR) manager to speak with this team member.

C.

Reallocate this team member's tasks to others for the immediate future.

D.

Understand the team member's personal issue and offer them support.

A project is behind schedule because of a delayed equipment installation. This is affecting many other activities. The manager responsible for the

equipment delivery notified the project manager that there is a capacity issue for the team doing the installation.

What should the project manager have done to prevent this situation from happening?

A.

Defined the skill requirements more clearly in the scope statement.

B.

Asked the manager to follow the agreed-upon resource management plan.

C.

Conducted periodic reviews with the manager on resource availability.

D.

Consulted with the installation team on a regular basis to check for conflicts.

Drag the communication event on the left to the main subject discussed during the event on the right.

A company was acquired, and the new company management asked the project manager to begin using a specific set of metrics immediately to measure team performance. The project manager is working on a predictive project and thinks this request will distract the team and delay the project.

What should the project manager do first?

A.

Assess and analyze the impact of using these metrics.

B.

Involve the team in reviewing the proposed metrics.

C.

Request an extension to implement the new metrics.

D.

Support the required metrics during the next project phase.

A project manager is performing earned value management (EVM) for a cross-country pipeline project. The project manager has determined the ratio of earned value (EV)

to actual cost (AC) for the project and has found the calculated result to be 0.9024.

What does this value mean for the project?

A.

The project has started exceeding the planned cost.

B.

The project is earning less value an was planned.

C.

The project has earned more value than planned.

D.

The project is close to exceeding the planned cost.

An agile project will be delivered to a client based on a fixed price in cryptocurrency. Due to the volatility of cryptocurrency, both parties have

agreed to adjust the scope to the value of the cryptocurrency at the end of every iteration and halt the project when the agreed price is reached.

Which approach should be used in this situation?

A.

A flow-based approach starting with the smallest stories.

B.

An iterative approach starting with the highest value epic.

C.

A predictive approach with short phases.

D.

An incremental approach with a minimum viable product (MVP).

A client wants to create an innovative software for the travel industry using an agile approach. A project manager from the company was assigned

to work on the details and estimates as requested by the client.

What should the project manager do before sending the information to the client?

A.

Put the tasks with estimates in the backlog and clarify that the project will not need any reserves.

B.

Sequence the tasks with estimates and add standard risk reserves to use for software development.

C.

Analyze the tasks, provide estimates, include a prototype demo, and send to the client directly.

D.

Work with the team to understand their views and add the appropriate dependencies and risks.

A project management office (PMO) director finds that the project managers leading software development projects are not consistently seeking approval from other division leaders in cybersecurity and operations before deploying code into production. The PMO director asks the project manager to develop a solution for this issue.

What should the project manager do to fix this problem?

A.

Establish a daily scrum meeting and invite division leaders to attend so they can be aware of upcoming code releases.

B.

Provide division leaders with a teleconference phone number to call if they have concerns after code is deployed into production.

C.

Create a new policy requiring project managers to email division leaders before deploying code into production.

D.

Launch an enterprise governance structure comprised of division leaders to establish policies for code releases.

A human resource (HR) acquisition process for a large project has recently changed. One major process change includes the approval of the financial manager and the recruitment manager. This change to the process implies longer processing. The project urgently needs new resources.

What should the project manager do?

A.

Adapt the resource management plan and ask for financial approval before sending it to the customer.

B.

Assess the impact of the change and review the project management plan for next steps.

C.

Ask the financial manager to delay implementation due to potential project delays and penalties.

D.

Review the project schedule to determine which technique will reduce impact on project duration.

An agile team is geographically separated across multiple continents, and the project manager is in the process of identifying the tools to manage the communication among the virtual teams. Drag the appropriate tool on the left to each project task on the right.

A project manager has just received communication from an operational functional manager to complete an additional scope item for a project that was formally closed a few weeks ago. The scope looks relatively small and simple to handle as part of the daily operations activity.

How should the project manager deal with this request?

A.

Submit a change request and allocate the budget and resources needed for execution.

B.

Confirm that the budget and resources are available to execute the work request.

C.

Check the alternative resources available in the organization for the request.

D.

Evaluate the nature of the request and plan communication accordingly.

A project has been reporting a declining schedule performance index (SPI) for the past four reviews. No corrective action is under development, and the project team does not seem concerned.

What should the project manager do first to address the SPI trend?

A.

Notify the project stakeholders that the scope needs to be reduced in order to hold the costs within budget.

B.

Engage with the project team to create a plan that will deliver benefits on a defined and incremental basis.

C.

Contact the project sponsor to let them know you require more resources to meet the schedule.

D.

Meet with the project scheduler to rebaseline the project using a more realistic schedule.

A project manager has been assigned to lead a project with limited funding and resources. During the requirements brainstorming session, several stakeholders request a long list of requirements for a new project, which exceeds the budget.

What should the project manager do first?

A.

Host a requirements workshop and ask the stakeholders to prioritize the requirements based on critical needs.

B.

Review the requirements and determine which of them can be removed, then advise the stakeholders of the changes.

C.

Meet with the sponsor to obtain their feedback regarding critical requirements in the view of senior management.

D.

Reach out to the sponsor and request additional budget and capacity in order to complete the project.

A project manager has been approached by the project sponsor about adding to the project scope How should the project manager accommodate this request?

A.

Update the project team about the change request

B.

Disregard the request since the project scope is finalized

C.

Adjust the project schedule to accommodate the new project scope requests

D.

Create a change request lor the change control board (CCB) to review

A project team member, who is inexperienced in system development work is not performing well. Currently, there are no other staff members

available who are qualified to complete the work.

What should the project manager do?

A.

Assess the team member's development requirements and arrange for the team member to receive training.

B.

Seek approval from the project sponsor to use some of the project budget reserve to hire a new resource.

C.

Work with the functional manager to determine an incentive for the team member to complete the project.

D.

Request a substitute for the team member with a new resource who is more skilled in system development work.

After the demo on a software project, one of the key stakeholders contacted the scrum master and complained that they were unaware of changes made to the project. After checking, the scrum master learned that the stakeholder's details were incorrectly entered into the register.

What should the scrum master do?

A.

Ask the product owner to update the stakeholders' contact information at every meeting to address any changes.

B.

Update the stakeholder's information and inform them that they must make the team aware of any changes.

C.

Consider it a loss since the stakeholder should have ensured the contact information was up to date.

D.

Check the stakeholder register and ensure that every stakeholder's information is correct and current.

A project manager is part of an organization that is assessing the use of agile delivery approaches. A new project management office (PMO) manager who had a bad experience with a Scrum approach recommended that the project board replace Scrum with a predictive approach.

What should the project manager do?

A.

Define a risk management plan (or the new approach, as needed.

B.

Review the benefits realization plan to include the cost of the change.

C.

Define a project management plan for the new approach, as needed.

D.

Review the communications management plan to identity new stakeholders.

A project manager is preparing to start a new project in which the team members are distributed geographically across different countries. The project manager is using the communications management plan to engage the team members and find a communication method that suits everyone.

How should the project manager continually evaluate the effectiveness of the virtual team's engagement?

A.

Collect feedback from the team to discuss alternatives to enhance the communication.

B.

Conduct individual meetings to create a trusting environment with team members.

C.

Establish periodic face-to-face meetings and address the communication topic.

D.

Hold meetings in accordance with the team members’ preferences and availability.

A project manager is working on a complex project with a high degree of change. What strategy should the project manager use to ensure a

successful project completion?

A.

Update the project management plan to reduce the possibility of scope creep.

B.

Schedule a regular risk review with the project management team.

C.

Increase the active engagement and participation of key stakeholders.

D.

Create a project change roadmap to keep track of all unforeseen changes.

A project manager is leading a project that has a dependency on the client's vendor management system for critical requirements. The vendor

management team will not derive any benefits from the project. However, the project requires support from the vendor management head.

What should the project manager do next?

A.

Get support from the sponsor to hire a subject matter expert (SME) from the vendor management team to work on the project.

B.

Review the terms of reference of the steering committee to include the vendor management head.

C.

Work with the sponsor on a communications management plan to obtain support from the vendor management head.

D.

Obtain help from the sponsor to highlight any nonfinancial benefits for the vendor management team.

Drag the items on left side to the matching term within the correct project approach on the right side.

There is a conflict on an agile project about following organizational processes, many of which do not add any value to the project. To resolve this, which one of the following

should be regarded with the highest priority?

A.

Needs of the customer

B.

Needs of the project manager

C.

Needs of the agile lead

D.

Needs of the organization

In a frequently changing project, the project manager discovers a customer requirement change during a daily meeting. What should the project manager do?

A.

Give the change to the scrum master to investigate how much additional effort the change will require.

B.

Tell the customer that the requirement change will be put into the next project phase if management approves.

C.

Validate the requirement change with the product owner and development team before redefining the scope.

D.

Escalate to management for approval since the change was not included in the original requirements.

Eight highly qualified experts have been assembled to work for a 6-month period on an a specific aspect of an organization's product development process. How should the

project manager support this team to succeed?

A.

Hand over control of specific aspects of their roles as experts and let them agree on their own timelines and targets.

B.

Bring in a senior colleague who is also an expert to ensure the team is on track to achieve the goals and objectives.

C.

Define roles and targets for all team members and regularly follow up with one-to-one meetings to review progress.

D.

Work with the team members to define the overall objective and support them to engage around the goal.

A project manager works for an organization that intends to begin using agile delivery, but there is a lack of support from some business units. The project manager needs to address the lack of trust in agile.

What should the project manager recommend?

A.

Implement and establish an agile framework for the project.

B.

Hire a team of contractors for agile project delivery.

C.

Define detailed work instructions for agile project delivery.

D.

Negotiate special arrangements for an agile pilot project.

There are two interdependent projects: the first project is in execution, and the second one is about to be deployed. The first project has been delayed, which is now affecting the second project due to the sharing of resources.

What should the project manager do in this situation?

A.

Ask for written commitment from the team manager assuring the deployment team can work on only one of the projects.

B.

Ask the procurement team to solicit offers from external providers in order to replace the internal resources for the deployment.

C.

Assess the issue with the deployment resources' availability and define a plan to deploy extra resources to the deployment team.

D.

Organize a meeting with the deployment team and explain that, due to a resource shortage, the project will be delayed.

A project scope statement has been approved, and the project manager and core team have been assigned to the project. Suddenly, the project

manager takes a temporary leave of absence due to a medical emergency. While the project manager is on leave, the team develops the project

schedule. When the project manager returns, a detailed schedule is almost complete.

What should the project manager do?

A.

Ensure that the schedule is aligned with the vision and objectives.

B.

Escalate the compliance issue to the project management office (PMO).

C.

Congratulate the team and move on to the execution phase.

D.

Develop a new detailed schedule with the team and project sponsor.

At the end of a project's initiation phase, the budget was developed and sent to the approval board. During the approval meeting, one of the key stakeholders asked how the budget was developed for future uncertainties.

How should the project manager reply?

A.

Recurrent team meetings are planned to control the budget against future uncertainties.

B.

Probabilistic analysis was used to develop the budget to address future uncertainties.

C.

The budget was developed by using the lessons learned from previous project data.

D.

Feedback from stakeholders will be addressed at each board meeting to adapt the budget.

During the early phase of a project, the requirements documentation was not approved. It was identified that the leader of a user party was not included in any of the requirements collection communications.

Which of the documents was likely missed or outdated?

A.

Business Documentation

B.

Stakeholder Register

C.

Risk Register

D.

Project Charter

A project team has developed the initial schedule using a network diagramming method and has arrived at the overall project duration. Upon examining the schedule, the project manager finds that there are several activities that may require buffers to mitigate or eliminate potential scheduling conflicts.

Match the following common terms with their explanations that evaluate the buffers or constraints.

A team decides to adopt an agile approach for their new project. During a sprint, the project manager realizes that there is a need to show progress and optimize the collaboration among teams.

Which tool should the project manager use?

A.

Retrospective meetings

B.

Daily meetings

C.

Kanban board

D.

Gantt chart

A project manager who recently joined the company has been assigned to manage a software project for a major recurring customer. What should the project manager do to

enhance the budget estimations for the project?

A.

Discuss the budget with the team during the daily standups to ensure the budget is under control.

B.

Review budget-related lessons learned from similar projects.

C.

Invite the client to the kick-off meeting and create the project budget during the meeting,

D.

Implement an agile approach to avoid using a fixed budget,

A project team is transitioning from a predictive to an agile approach. The project manager is trying to minimize the support issues that the product has had in production.

One particular pain point is the transition to operations, where the issues usually arise.

What should the project manager do to improve this scenario?

A.

Increase the focus on backlog items that cover support requirements, as well as product manuals and operation guides.

B.

Ask the support/operation team to participate in the daily standup meetings to contribute to the project's progress.

C.

Engage the operation teams in the retrospectives and demo sessions and incorporate their feedback on project activities.

D.

Foster stakeholder participation by engaging them early on the backlog discussions.

A project is comprised of team members who are not engaged and committed to project success. What should the project manager do to address this situation?

A.

Accept the situation knowing there is schedule slack available to release on an incremental basis when necessary.

B.

Call each team member to gain their perspective on the problem, then bring the whole team together to discuss a solution.

C.

Send each team member a direct email indicating that disciplinary action is likely if they do not change their attitude.

D.

Contact the project sponsor to request approval to release the current team and hire replacement personnel.

A project manager is leading a project in which the product requirements have not been fully met due to several uncertainties about customer acceptance. What should the project manager do?

A.

Gather a reduced number of approved requirements and add some extra features to fulfill the product specifications.

B.

Ask team members to research and collect data about the best features offered by similar products in the market.

C.

Stop all project activities until all requirements are set up front by the project sponsor and the key stakeholders.

D.

Gather enough requirements to produce a minimum viable product (MVP) with which to evaluate customer acceptance.

During a project's execution phase, two team members are having conflicts with other team members within the team on technical and interpersonal levels. Which two actions should the project manager take first to address this conflict? (Choose two)

A.

Ask human resources (HR) to intervene before it escalates and affects the team's performance.

B.

Arrange individual meetings with the team members who cannot work together effectively.

C.

Address the conflict during team meetings for the entire team to participate and find solutions.

D.

Discuss the conflict early among the affected team members using a direct, collaborative approach.

E.

Plan to resolve the team members' conflicts after the sprint and focus on achieving the goal.

A project manager was suddenly asked to take over an ongoing project without any handover. During the first meeting, the project sponsor raised concerns about whether the project was on track to deliver the intended benefits.

What should the new project manager do first?

A.

Review the business case to gather information about the project.

B.

Initiate a rebaselining of the project based on the project sponsor's concerns.

C.

Discuss the items in the requirements register with the project team.

D.

Meet with the project stakeholders to understand the project sponsor's concerns.

An agile team is developing a new content management system. Some of the team members are struggling to deliver certain features since they have never worked on this type of solution.

What should the project manager do?

A.

Replace the members with new members who understand the system.

B.

Encourage the team members to make changes directly in the system.

C.

Ask the team to read through all of the available system documents.

D.

Encourage the team to hold a knowledge-sharing session in each iteration.

A project manager manages a bridge construction project. The project manager has received a major change request from a regulatory stakeholder to add one branch of the bridge to the engineering design. The project manager prepared a change request, which was reviewed and accepted by the change control board (CCB).

What should the project manager do now?

A.

Notify the project team about the change request's approval.

B.

Include the new branch of the bridge in the design.

C.

Communicate the decision to the stakeholder who requested the change.

D.

Evaluate the adjustments to the project management plan.

A project team has finished its first iteration out of six. The iteration's delivery performance (velocity) was 50%.

During the iteration retrospective, the team realizes that the complexity of the work was underestimated.

What should the project manager do?

A.

Update the issue log and escalate it to the project sponsor.

B.

Meet with the team to review internal actions to resolve the situation.

C.

Ask the technical manager to help the team with the issue.

D.

Ask to replace some team members with more experienced ones.

A project manager is appointed to a project that has just been approved. The project manager has extensive experience in hybrid projects, and the project team has performed many projects within a predictive framework. However, the project sponsor believes that the project needs to be executed using agile approaches.

What should the project manager do to select the most effective project framework?

A.

Adopt an agile framework to agree with the project sponsor.

B.

Perform a market evaluation with key stakeholders and determine the best approach.

C.

Evaluate project characteristics with the project team and adopt the most suitable framework.

D.

Suggest using a hybrid approach to the sponsor for project execution.

A project manager is assigned to a regulatory project for their country. The deadline for delivering results in compliance with the new laws is very tight, and the project team members have not yet been assigned. One of the project manager's peers informs the project manager that a project with the same scope for a different country was completed 1 year ago.

What should the project manager do first?

A.

Register a new risk in the risk management plan.

B.

Ask for additional resources and review the project estimate.

C.

Review organizational process assets (OPAs) and perform analogous estimating.

D.

Complete a bottom-up estimation for the project activities.

An organization is about to start a multiphased project. Due to strict regulations, some of the phases must be completely planned in advance.

However, other phases allow for more flexibility and experimentation on scope and schedule. The sponsor wants to pursue the project objectives

as planned, but also wants to accommodate new information and changes as the project progresses.

Which project management approach should the project manager select for this project?

A.

Hybrid

B.

Incremental

C.

Agile

D.

Phased

An organization is embarking on the deployment of a new digital solution that will revolutionize purchasing services The project manager has created all the necessary plans and activities to ensure a successful integration and solution launch There is a risk of a partner’s system being unavailable which could impact the project negatively

What key activity is needed to ensure the project's success?

A.

Communicate to the project stakeholders that full integration may not be possible and that the project will potentially be delayed as a result.

B.

Eliminate the risk by mandating the partner to change the system settings to facilitate an easier integration with the new solution

C.

Continuously monitor the risk of the partner system's unavailability, and put the proper resolution plans in place in case the risk materializes into an actual issue

D.

Mitigate the risk by developing alternative plans to make the solution ready and available without full integration capabilities

A project manager is assigned to a new project to deliver a product at the end of the year. The project manager was informed by the vendor that a core component could not be shipped on time, which will impact the schedule.

What should project manager to do next to minimize the impact on the project?

A.

Schedule a meeting with all stakeholders to extend the project deadline

B.

Replace the vendor with a new vendor who can offer the component on time

C.

Add an item to the next status review to make stakeholders aware of the vendor issue.

D.

Review and update the issue log and determine if any alternative components can be offered