Pre-Summer Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmas50

PMI PMP - Project Management Professional (PMBOK 7th Version)

Page: 13 / 13
Total 2191 questions

A project manager works in an organization that embraces using different project approaches. The project manager's current project uses a

predictive approach with clear requirements. A few months following the kickoff, the project manager notices that the virtual development teams

are not communicating enough, and coordination is becoming an issue. The teams are not aligned on the tasks being done or the current

impediments.

What should the project manager do?

A.

Ask the members to be more proactive and share ideas with each other.

B.

Set up a daily virtual meeting with the development team.

C.

Plan a monthly virtual meeting to align and to review the plans.

D.

Review the issue with the project sponsor and ask for support.

A project's business case was just approved and the project manager is creating the benefits management plan. It is unclear how the benefits from the project align with the organization's vision.

What should the project manager do first to verify alignment?

A.

Ask the project team to delay the kick-off while resolving the concern.

B.

Request a copy of the project assumptions log for more insight.

C.

Meet with the project sponsor to obtain more information.

D.

Consult with the project team members to gain their opinions.

During the implementation phase of a project, functional managers are adding new requirements, which may impact cost and schedule baselines. The project manager

notices that some of the team members are communicating with their managers directly to fulfill their requests. This will lead the project to go beyond the agreed baselines.

How should the project manager handle this situation?

A.

Set up a proper governance structure to ensure functional managers’ requests are processed correctly.

B.

Modify the communications management plan to enable functional managers to add changes to the project.

C.

Follow the project constraints and move forward with the agreed schedule baseline and the cost baseline.

D.

Ask the functional managers to communicate with their peers and emphasize the impact of their requirements.

An organization imports many of the materials for a product build. Due to global shipping delays, some of the essential materials have yet to arrive, resulting in the inability to finish building the product for the upcoming release. The project manager is meeting with stakeholders to discuss options.

What should the project manager recommend?

A.

Request marketing to launch an advertising campaign for the product that is currently in stock.

B.

Update the project management plan, factoring in furloughs of the assembly team to reduce expenses.

C.

Explore if the materials could be supplied locally and obtained on time.

D.

Meet with the engineering team to manufacture the materials in-house.

A project manager's new employer decided to use an agile delivery approach to implement a new accounting system. The chief financial officer (CFO), who is also the

project sponsor, is committed to a new way of working but does not have experience as a product owner. The project manager's background includes a couple of years’

experience as an agile practitioner working as a scrum master.

What should the project manager do at the start of the project?

A.

Collaborate with the development team to help the project sponsor acquire the relevant skills.

B.

Assume the product owner role until the project sponsor is ready to take over the product owner role.

C.

Delay the build of the system until the project sponsor is ready to take over the product owner role.

D.

Work with and assist the project sponsor in building and prioritizing the product backlog.

During the execution of a project to develop a prototype, the customer asks the project manager to stop the prototype line and purge a specific

component based on recent reliability tests that have deemed the component to be deficient. The project manager checked the quality

management plan and there is no reference to this component.

What should the project manager do next?

A.

Inform the project sponsor of the situation and wait for the sponsor to provide further directions.

B.

Call a technical meeting with the customer to agree on a specification for the component and document it in the quality management plan.

C.

Submit a change request to proceed with the replacement of the component and wait for further customer instructions.

D.

Keep running the manufacturing line because there are no quality specifications for this component.

During the last iteration of a hybrid project, one of the key members of the team wants to leave the project. What should the project manager do to address this concern?

A.

Keep activities as planned regardless of the resource change.

B.

Update the burndown chart to reflect this resource's absence.

C.

Have a meeting with the resource to understand the issue.

D.

Request an additional resource to finish the project.

A company is transitioning from a predictive approach to an agile approach. A project manager is assigned to the first pilot with an inexperienced team. Due to an unexpected event, the whole team is asked to work remotely. During the second sprint, the project manager starts to notice a lack of commitment from the team members.

What should the project manager do in this situation as a servant leader?

A.

Request an exception to allow the team to return to work on-site

B.

Allow the team to address the problem as a self-organized team

C.

Coach team members to increase their engagement and collaboration

D.

Force the team to attend the daily standups to gather the project status

Due to unforeseen circumstances, a contractor was unable to mobilize the project team, which was necessary to conduct face-to-face meetings and discussions. Virtual meetings were subsequently put in place, but the local project team and end users now face a communication gap that is causing the team's low performance.

What should the project manager do?

A.

Ask the contractor to solve this problem because this is a contractual obligation.

B.

Terminate the contract and initiate a new one with a local contractor.

C.

Implement key performance indicators (KPIs) and convince the contractor to engage the team.

D.

Reassess continually to remove blockers for the team.

A project team member was unhappy with a new change in project governance and complained to one of the project sponsors. The project sponsor challenged the project manager.

How should the project manager resolve this conflict?

A.

Arrange a meeting with the project team member and project sponsor to discuss the change and obtain consensus.

B.

Discuss how to manage this conflict with the project management office (PMO) and let them decide how to resolve the issue.

C.

Explain to the sponsor why the change is required and get their support in forcing the project team member to accept the new change.

D.

Schedule a meeting with the project team member's functional manager and request the functional manager's support.

A project manager is leading a project that is at 90% completion. One of the key stakeholders requests a certification program to be included as part of the project. Another stakeholder disagrees and informs the project team that there should be no change to the project management plan since the project is nearing completion.

What should the project manager do?

A.

Update the project management plan and adjust the project budget with this change request.

B.

Raise a change request to the change control board (CCB) and inform the project sponsor about the change.

C.

Ask the key stakeholder to take the lead in handling the request since they are more knowledgeable.

D.

Request a meeting with the stakeholders and their team members to inform them about this change.

A company changed the product owner on an existing project. The new product owner has less knowledge of the product than everybody else on the team. Due to the product owner's lack of knowledge, the team does not consider the opinions of the product owner seriously and mostly relies on the project manager's opinion.

What should the project manager do?

A.

Assume the role of the product owner while the product owner gets familiar with the product.

B.

Schedule time to share insights with the new product owner about the product and project information.

C.

Work with the project management office (PMO) manager to generate an onboarding plan for the new product owner.

D.

Organize a team-building activity and ask the team to respect the opinions of the new product owner.

A project manager is working with a colocated agile project team that has worked together long enough to be in the performing phase of team development. An unforeseen event has caused the team to be dispersed and they are now unable to colocate.

What should the project manager do to keep the team performing as effectively as possible?

A.

Ask the project sponsor and executive stakeholders to encourage the team to maintain their performance,

B.

Transition the team from an agile approach to a predictive approach for better performance cantral.

C.

Provide the team with virtual collaboration software and training on the software to minimize disruption,

D.

Evaluate project performance and step in if performance decreases to. an unacceptable level,

A project team is working on a product that is planned for multiple iterations. They are delivering incremental value.

When should the value be demonstrated?

A.

After full development is completed

B.

When a major feature is completed

C.

At the end of each and every iteration

D.

When the sponsor approves the increment

A project manager is overseeing a project as part of a program geared toward a major technology disruption. The team is comprised of brilliant young professionals who have worked on different projects for the organization in the past. However, the team complained that they previously experienced a lack of direction during project execution and are a traid of the same issue in this project.

Which two actions should the project manager take to ensure that this issue does not occur in this project? (Choose two)

A.

Keep the team engaged and focused on the project's direction.

B.

Encourage the team to do a brainstorming session and provide a mitigation plan.

C.

Focus on the resource management plan and track project progress,

D.

Set a clear vision for the project and ensure it is visible to all stakeholders.

E.

Organize a team-bonding activity and invite an external manager to speak to the team.

A project manager is leading three projects in a program focused on starting product commercialization. Once the three projects fareket, the project manager stops attending the recurring team meetings. The program manager asks the project manager to continue attending these meetings to maintain those team touchpoints.

This request does not match the project manager's expectation, since a program manager is overseeing the remaining work

How should the project manager approach the situation?

A.

Attend only the program meetings where the market launch is being monitored

B.

Provide an answer via email recommending a division of tasks between both roles.

C.

Politely inform the program manager that attending these meetings is no longer required.

D.

Schedule a meeting to discuss the different perspectives and agree on a decision.

A project team is globally distributed with team members living and working in different time zones. The project manager is trying to get the team

to collaborate effectively.

Which three actions should the project manager take to accomplish this goal? (Choose three)

A.

Require the team to have daily mandatory meetings with the project management office (PMO).

B.

Recommend the use of formal written documentation in all project communications.

C.

Review the communications strategy with the team regularly with a view for continuous improvement.

D.

Send out a survey to review the preferred method, time frequency for communications.

E.

Compile a communications management plan with input from all stakeholders and distribute for review and approval.

A project sponsor has approved the project charter and business case. The project manager has reviewed the artifacts to initiate the project and is unclear if the intended benefits of the project align with the strategic objectives of the business.

What should the project manager do first?

A.

Start executing the project since leadership is responsible for the business strategy.

B.

Meet with the project sponsor to better understand the strategic benefits of the project.

C.

Propose an updated business case and project charter that are more aligned with the business strategy.

D.

Conduct qualitative and quantitative risk analysis and record the results in the risk register.

While following up on a deliverable, a team member expresses concern to the project manager about working with another team member. This team member states that the other team member, who is a functional manager, is often defensive and aggressive during meetings.

How should the project manager handle this situation?

A.

Suggest that the team member ignore the disruptive team member and focus only on the work.

B.

Encourage both team members to meet as soon as possible and resolve the problem

C.

Monitor the situation for a few weeks to determine if the disruptive team member's attitude changes.

D.

Report the disruptive team member to the human resource (HR) department.

A project manager is in the middle of handling a major upgrade to an existing product. The project manager learns that the resources initially promised as part of the project are being moved to another priority project.

What should the project manager do?

A.

Retrieve the documentation that shows the resource allocation.

B.

Examine ways of modifying the scope of the project.

C.

Adopt a resource leveling procedure to level the resources.

D.

Perform an impact analysis to see the effect on the project.

A project manager who is experienced in predictive and adaptive approaches has been assigned to a new project. Most of the project

stakeholders have only worked on predictive projects, and only a few have been exposed to adaptive projects.

What should the project manager do?

A.

Propose a hybrid approach and determine which stakeholders will be engaged in each phase of the project.

B.

Follow a predictive approach to reduce the training effort, even though there are incremental deliveries in the project.

C.

Use an adaptive approach, engage the stakeholders who have been exposed to adaptive projects, and train those who have not.

D.

Understand the scope complexity and project magnitude prior to determining which approach to use.

A project manager is assigned to a large construction project with more than 100 project team members. The project manager is having a hard time keeping the project on track and deriving the planned benefits. The project manager wants to make sure that each requirement is linked to the business and project objective.

What should the project manager do?

A.

Review the requirements on a weekly basis.

B.

Implement a requirements traceability matrix.

C.

Add the requirements to the project charter.

D.

Understand the project management plan.

A project manager is assigned to a project with a long timeline and complex scope. The client requires a high-level, long-term plan as well as

something that will work immediately, adding features to the product as the project progresses.

How should the project manager plan and deliver this project?

A.

Plan the project with a predictive approach with a work breakdown structure (WBS) and then execute it using an agile approach to delivervalue incrementally.

B.

Plan the project with a predictive approach and a work breakdown structure (WBS) following the plan and deliver value at the end of theproject.

C.

Agree on a minimum viable product (MVP) first to be delivered immediately with the client and then release the rest of the scope at the endof the project.

D.

Select an agile approach and manage the project according to best practices to ensure value is delivered to the client.

During a system demo, a project stakeholder rejects the features completed from the most recent user stories. According to the stakeholder, the product does not meet the

quality standards required by regulations.

What should the project manager have done to avoid this?

A.

Reviewed with the product owner that all the stories worked on in the iteration were in the project backlog

B.

Ensured that the project sponsor understood the scope of the project to avoid any future complaints

C.

Reviewed with the product owner that all acceptance criteria were met for the stories worked on in the iteration

D.

Ensured the stakeholder concerns were properly addressed in the iteration to avoid future setbacks

During the last two iterations of a project, one of the team members had low performance. The project manager conducted two feedback sessions with the team member and escalated the issue to the resource manager and project sponsor, but there has been no improvement.

What should the project manager do next?

A.

Escalate the situation again to the project sponsor.

B.

Review this obstacle during the daily standup meeting.

C.

Request a new resource to execute the activities.

D.

Provide feedback to the resource at the sprint review.

During an agile team retrospective, a project team member mentions that the code quality is degrading, which might result in future rework that

could become unmanageable with time. What should the project manager do?

A.

Help the team create the definition of done (DoD) to improve delivery quality.

B.

Add testing items to the backlog to assess quality periodically.

C.

Expand the team in order to improve the quality of the project.

D.

Compare the cost of improving quality against the cost of failure and adjust the budget.

An insurance company is planning to make a big change to its core application. The project manager realizes there is resistance to change from the sales agents since they

are accustomed to taking orders manually and entering them in the system at the end of the day. With the new change, they will use point-of-sale devices to take orders online.

What should the project manager do to get commitment from the sales agents?

A.

Use a business case to model a sales pitch and gain consensus from the sponsors.

B.

Request help from the project sponsor to get support from the sales agents.

C.

Escalate the issue to senior management to gain team buy-in

D.

Explain the change benefits to the sales agents' manager to get their support.

A project manager is working on a project with three virtual teams. Team A is in a different time zone than teams B and C. The project was going

well, but recently team A has started feeling left out. Information reaches team A late or is sometimes missed, and teams B and C give preference

to each other's problems over team A. The project manager has already set project guidelines, but realizes they need to be improved.

Which two things should the project manager do to help the teams collaborate better? (Choose two)

A.

Schedule weekly progress meetings with all three teams and have them take turns as key players.

B.

Plan for team members to temporarily work at each other's locations to better provide a sense of community.

C.

Update the communications management plan and encourage the teams to review it promptly and proactively.

D.

Create a status reporting template and share it with all team members before the day ends.

E.

Schedule daily meetings with each team to understand their progress and concerns in detail.

A construction project for a nuclear power plant will reduce the region's energy dependence on external electricity supplies. The project manager has received support for

the project from several leaders in the region. However, some people from the government want to stop this project to focus on developing renewable energy sources.

Which stakeholders should the project manager include in the stakeholder engagement plan?

A.

Stakeholders who have been identified and who have needs and a potential impact on the project.

B.

Stakeholders who are selected by the project sponsor who have a potential impact on the project.

C.

Stakeholders who disagree with the project so as to proactively manage their expectations.

D.

Stakeholders who are supporting the project in order to obtain additional resources.

A project manager implementing a hybrid project is dealing with multiple stakeholders in a rapidly changing business environment. How should the

project manager ensure that the needs of stakeholders are consistently met?

A.

Assign one team member to one stakeholder to ensure that the responsible team member is conversant with the needs of the stakeholder.

B.

Add more iterative techniques to improve stakeholder learning.

C.

Identify all the critical stakeholders during the project initiation.

D.

Use iterative life cycles involving stakeholders to enable the team to improve the product end result through successive prototypes.

A team is working on a project with three iterations. The project manager is reviewing the burndown chart What is the point where the chart shows that the team is performing below the plan?

A project manager identifies a risk that has a high probability of occurring. How should the project manager manage this risk?

A.

Submit a change request to transfer the risk to a third party in case it becomes an issue.

B.

Remove the user stories associated to that risk and avoid the impact to the project deliverables.

C.

Assign a qualified team member to be the risk manager for the project.

D.

Ask the team to monitor the risk and provide an alert if it becomes an issue.

A project manager is managing a new development program to automate some technical functions. During project kickoff, the project manager

expresses the need for a technical architect to support the project for a moderate amount of time. The project sponsor informs the project

manager about an existing technical architect who possesses valuable knowledge but is already assigned at the portfolio level.

What engagement model should the project manager use for the technical architect role to ensure project success?

A.

Hire a new technical architect who would be solely dedicated to the current project.

B.

Share the existing technical architect so they can be allocated to the current project and other projects.

C.

Hire a new technical architect who would be shared between the current project and other projects.

D.

Assign the existing technical architect to solely be dedicated to the current project.

A project manager's customer is new to agile approaches. When the customer found out that the project was going to use an agile approach, the customer became

concerned that the product quality will be sacrificed.

What should the project manager do?

A.

Ensure that the customer and the delivery team agree on the definition of done (DoD) in the beginning of the project.

B.

Invite the customer to join the daily standup meetings to better understand the product design and progress.

C.

Ensure the team demonstrates product features to this customer regularly to collect feedback and improve as needed.

D.

Invite the customer to join the regular sprint planning sessions to better understand the project's progress.

A project manager is leading a hybrid project for the development of denial equipment with live team members A dentist, who is also one of the major investors attends a sprint review meeting and raises questions and doubt about the concept and expected performance of the equipment

What should the project manager do?

A.

invite the investor to a sprint retrospective meeting to discuss the improvements of the concept and expected performance of the equipment with the team

B.

invite the protect sponsor to the sprint review meeting and nave a QSA session about the concept and expected performance of the equipment

C.

invite the product owner and the team to a discussion about the concept and expected performance of the equipment

D.

invite the investor to the design review meeting to present the concept and expected performance of the equipment and include a QSA session m the meeting

A project manager has been assigned to an important project that will help set the future of the company. Meanwhile, the project management office (PMO) is implementing

adaptive tools in a mostly predictive environment and has requested that the project manager follow this process as well. However, the functional manager has expressed concerns about the use of new tools on such an important project.

What should the project manager do?

A.

Review the adaptive tools' impact and obtain agreement from the functional manager.

B.

Follow the functional manager's recommendation to implement only predictive tools in the project.

C.

Make the decision on which project approach to use that would best fit the project.

D.

Follow the project management office's (PMOs) request to implement the adaptive tools in the project.

A project manager was recently assigned to a project that is in the execution phase and is experiencing roadblocks. During a review of the

processes and procedures, the project manager notices similarities to a previous project that experienced similar roadblocks. The project manager

reviews the task schedule and finds that certain tasks are well behind expectations. In speaking with the project team, the project manager

confirms that the team is following the processes exactly.

What should the project manager do?

A.

Update the schedule to account for the unexpected delays in the project tasks.

B.

Review the resources allocated to the project and change accordingly.

C.

Review and amend the processes to ensure only value-adding activities are present.

D.

Update the variation register to account for the extended project time.

A project manager is working for an organization in country A and has been tasked with opening the first brick-and-mortar store in country B. The sponsor has identified the city for the store and wants to minimize any potential issues with the local government.

Which action should the project manager take to address the sponsor's request?

A.

Work with the organization's real estate department and reach out to the local government to identify the best location for the store.

B.

Work with the local government to build the profiles of employees that will be working in the store.

C.

Work with the organization's legal department to identify local regulations to ensure project compliance.

D.

Work with the organization's project management office (PMO) to build a project team of residents located in the city.

A team member has very strong technical skills and is interested in a leadership role. A leadership position opens up outside of the team in the organization. The project manager has observed that the team member has a major gap in communicating in a professional manner.

What should the project manager do?

A.

Suggest the team member focus on positions with technical aspects and possible technical career opportunities.

B.

Recommend the team member for effective communication training and support their career development interests.

C.

Encourage the team member to stay in their current role as they are important to the project.

D.

Ask the team member to refrain from pursuing new opportunities as they are not a suitable fit for a leadership position.

One of the team members is always late to the daily standup meeting. What should the project manager do?

A.

Schedule the meeting at the end of the day to accommodate everyone.

B.

Ignore the situation since the team member is accomplishing their deliverables.

C.

Reinforce the ground rules for standup meetings with the entire team.

D.

Speak with the team member directly to reinforce the ground rules.