Summer Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: ecus65

PMI PMP - Project Management Professional (2025 Version)

Page: 2 / 12
Total 1988 questions

A new project manager is planning an information security project for a company that resides in different countries. What is the first step the project manager should take to gather customer requirements?

A.

Conduct a stakeholder analysis to identify how regional policies may influence needs

B.

Request relevant stakeholders to conduct an analysis and reach consensus independently

C.

Conduct a project scope review workshop with relevant stakeholders.

D.

Conduct project planning meetings in one location with relevant stakeholders

A project team with members from many different countries is struggling to cooperate The project manager accepted these difficulties during the storming phase of team development, but the team has not moved to the next phase The project is beginning to fall behind schedule

What can the project manager do to move the team to the norming phase?

A.

Plan social activities to help foster stronger interpersonal relationships and identify shared goals.

B.

Speak with the project sponsor about changing the team composition

C.

Figure out who is behind the issues and apply progressive disciplinary techniques.

D.

Show the team the schedule impact of their communication issues and encourage them to put their differences aside

Which two actions should a project manager consider while launching a new virtual team? (Choose two)

A.

Recruit the best resources within the organization to be part of the virtual team

B.

Evaluate the project manager’s own strengths and weaknesses as a virtual team leader to identify avoidable pitfalls

C.

Identify the types and quantities of resources required for each work package or activity

D.

Establish in the beginning, how progress will be monitored and the best means for communicating progress

E.

Verify if team members are on more than one team and cannot devote enough time to this team

A project manager is managing a project which has a very complex and long execution period Although the project is mostly predictive, the team was able to break the design and execution into smaller packages using a hybrid framework The business wants to keep track of the value delivered by this framework application but there is no defined set of measurable items for the framework.

What should the project manager do first?

A.

Work with the stakeholders to determine which measurable benefits can be tracked and assign an accountable person to monitor and report them

B.

Create a report based on the work breakdown structure (WBS) and update it on a regular basis.

C.

Use the same benefits tracking process from the last predictive project and add this to the monthly status report

D.

Research which templates of reports were used the most for this framework and incorporate them into the project

A key project stakeholder who was a big supporter and motivator for the project team is leaving the organization The project team is experiencing low morale and poor teamwork

What should the project manager do to improve morale?

A.

Identify the wants and aspirations of the team

B.

Build team connections and emotional bonds

C.

Forge consensus through team participation.

D.

Set goals and push the team to achieve the goals

An integrated project involves the interaction of both hardware and software and the sponsor has approved the schedule management plan The project team evaluated the product's feasibility of functionality and accelerated testing What should the project manager do as a servant leader?

A.

Support the team as necessary to find the minimum viable product (MVP).

B.

Amend the project budget to include MVP testing

C.

Submit a change request to the project sponsor for accelerated testing.

D.

Develop the product as per the schedule to perform integration and testing

A new resource has joined an iterative project team The project manager notices that the resource is unable to complete the deliverables on time

How should the project manager address this situation?

A.

Address the lack of performance by coaching the new team member

B.

Discuss options to improve performance with the resource manager

C.

Provide performance feedback as part of the retrospective ceremony.

D.

Request a more efficient replacement resource from the project sponsor

In a newly formed project team one experienced team member is overwhelmed by the complexity of the tasks and is not happy with the project team. What should the project manager do?

A.

Ask the team member to enter this potential schedule delay in the risk register.

B.

Explain that the tasks are unavoidable and ask the team member to find a solution to overcome the challenges

C.

Actively listen to the team member and identify ways to support their needs in completing the tasks.

D.

Set up team-building activities with the project team members to reduce tension

for a project has reported the potential for a delivery delay due to a technical issue with the sub-supplier To stay on schedule, the vendor proposed replacing the sub- supplier's component with a similar part that is different from the one that is stipulated in the project specifications.

What should the project manager do next?

A.

Accept the proposed replacement in order to keep procurement activities on track

B.

Insist on using the component per the project specifications and air freight the equipment to mitigate the delay

C.

Instruct the vendor to use the part that is compliant with the project specifications and update the schedule

D.

Consult with a subject matter expert (SME) to see if the proposed change is

acceptable

At the end of a meeting a functional manager takes the project manager aside to raise some concerns on behalf of a project team member who is unclear about their role and responsibilities for the project What should the project manager do in this situation?

A.

Develop a work plan for the project team member with the help of the resource manager

B.

Advise the functional manager and the project team member to review the resource management plan

C.

Tell the functional manager and the project team member to review the project

charter

D.

Ask the functional manager to create a specific responsible, accountable, consult, and inform (RACI) chart for the team member

During the course of a project, the team develops negative group behaviors and becomes unmotivated and unproductive. What should the project manager do to improve the project team's performance?

A.

Define and analyze performance metrics

B.

Escalate poor performance to functional managers

C.

Update the stakeholder engagement plan

D.

Conduct a root cause analysis session

In a hybrid project, the customer has issued a contract that specifies the deliverables for each quarter The customer wants to show their stakeholders a tangible outcome in the first quarter and wants to move the second milestone to the first quarter The project manager explains to the customer that it is not feasible unless the requirements for the second milestone are changed

Which two actions should the project manager take? (Choose two)

A.

Convince the customer to leave the second milestone in place and not change it.

B.

Escalate the issue to upper management to resolve the problem and suggest a plan.

C.

Go back to the development team and discuss which second milestone requirements can be performed in the first quarter.

D.

Ask the customer for their priorities regarding the requirements for the second milestone

E.

Tell the customer that moving the milestone has a very high impact on the cost of the project

A project manager meets with external stakeholders to explain the objectives and outline expectations for a new project. A key stakeholder appears to support the project, with the condition that other unrelated projects will receive financial support Due to cultural sensitivities the project manager is reluctant to be direct with the key stakeholder on this matter The project cannot proceed without the support of this stakeholder.

What should the project manager do?

A.

Proceed with the project without allowing scope creep to occur

B.

Use the contingency funds to provide support for the requested projects

C.

Cancel the project since the stakeholder's request is out of scope

D.

Inform the sponsor and document the request in the stakeholder engagement plan

A project manager has been moved to a new division and is in charge of an existing project in an unfamiliar domain When attempting to gain an understanding of the risks for this agile project what is the primary tool the project manager should employ?

A.

Probability assessments

B.

Collaborative discussions

C.

Workshops for risk avoidance

D.

Interview with the project champion

A new regulation has been approved that will impact the deliverables in the fourth phase of the project The delivery is following an iterative approach and is currently completing the second phase.

What should the project manager do next?

A.

Consult with the project sponsor to discuss a cost increase

B.

Acquire approval for an exception to the implementation of the new regulation.

C.

Get approval for the additional budget from the steering committee

D.

Meet with subject matter experts (SMEs) to assess the impact to objectives

A project manager is approaching the end of a project, and several tasks are now practically complete and ready for handover to the client How should the project manager proceed?

A.

Update the quality management plan for the overall project

B.

Ask the client to verify and accept the tasks that have been completed

C.

Close out the project tasks that have been completed

D.

Update the communications management plan for the overall project

During the daily meetings with the team the project manager notices that a new team member is not making the expected progress on an assigned task What should the project manager do?

A.

Ask the new team member to follow the team ground rules.

B.

Ask an experienced team member to identify a replacement

C.

Ask the new team member to reassess their own capabilities

D.

Ask an experienced team member to coach the new team member

Early in the execution phase, a project manager discovers that recent changes in enterprise environmental factors (EEFs) will severely reduce the implementation cost and shorten the project schedule. How should the project manager address this situation?

A.

Meet with the project team to decide how the remaining budget will be spent.

B.

Keep the extra budget as management reserve until project closeout

C.

Give the team extra time to finish tasks within the original timeline

D.

Follow the project escalation policy and communications management plan

A project manager is appointed to simultaneously deploy a new solution to branches located in different countries Deployment teams in each country will integrate and deploy the solution The project manager discovers that the deployment teams each encounter similar issues However, each team addresses the issues separately

What should the project manager do to help ensure more collaboration between the teams?

A.

Organize regular meetings with all of the deployment teams to share issues and solutions

B.

Propose that some of the teams delay deployments in their countries

C.

Ask the project sponsor to appoint new managers for the deployment teams

D.

Ask each deployment team to provide a very detailed schedule and action plan

A large multi-year project requires highly skilled staff for successful deployment The management team and the project sponsor have analyzed the resource requirements and agreed to have permanent staff hired for the project to avoid potential budget overrun However there is a risk of staff turnover during the course of the project, which may have an impact on the delivery

Which two actions should the project manager take to mitigate this risk? (Choose two)

A.

Introduce a recognition program to motivate and reward resource performance

B.

Enhance the competencies of the project team through training, mentoring and coaching.

C.

Increase the trained staff to create back-up for resources

D.

Meet with management to discuss dividing the project into smaller projects

E.

Convince senior management to hire third-party staff

During the execution of a project within an operations function the project manager encounters scope changes and a delay in the delivery of critical tasks How should the project manager address this situation?

A.

Communicate the concerns to the project management office (PMO) during the weekly project reports

B.

Call for a team meeting to decide if the changes should be included

C.

Initiate the change request to modify the scope and adjust the timelines

D.

Conduct an impact analysis and present the results to the steering committee for approval

A company's project management office (PMO) is incorporating more adaptive technologies and has hired a new project manager with hybrid project management experience The team is slow in adopting the new methodology and has not been updating project artifacts in a timely manner.

Which action should the project manager take to improve the team's performance?

A.

Set up a training session for all project team members

B.

Reach out to the functional managers for support

C.

Speak individually with each project team member about making the needed updates

D.

Send an email asking all project team members to complete updates at the end of the day

During the execution of a maintenance project the contractor submits an offer for additional work The project manager realizes that the activities billed are included in the initial scope of work.

What should the project manager do next in this situation?

A.

Review the project scope and negotiate with the contractor

B.

Refuse the offer as it is included in the initial project scope

C.

Review the project costs and communicate this to the project sponsor

D.

Submit a change request to approve the offer

Due to delays on some activities one of the project team members has increased the scope without any approval What should the project manager do next?

A.

Remove the changes to match the original requirements.

B.

Add team members to the project to avoid more schedule delays.

C.

Evaluate the impacts of the changes that were made to the project

D.

Update project documentation with the new scope

A project has a very tight delivery schedule. The project is approaching the delivery date, and the project sponsor often sends the project manager alerts to avoid any schedule slippage . The project team has performed at an acceptable level until new, but the project manager wants to ensure that team’s performance level is performance is maintained until the end.

What action should the project manager take to motivate the project team's performance?

A.

Award certificates of appreciation to encourage the team

B.

Inform the team about the delivery pressure from the project sponsor

C.

Send a formal notice to team members instructing them to maintain performance

D.

Hire a few temporary team members to help with the additional work.

A project manager is leading a meeting with key stakeholders, the project sponsor and the product owner to define the features that will be released after the next iteration. The purpose of the meeting is to review the product backlog prioritization, considering that during the past iteration some deliverables were not completed.

Which two items should be taken into account first to review and update the product backlog priorities during the meeting? (Choose two)

A.

Complexity and the cost of development

B.

Industry trends and the technical approach

C.

Cost of delaying some features against business value

D.

Reusing components from another product

E.

Length of time each feature has been on the backlog

A project manager who is new to an organization observes that an approaching deadline is likely to be missed because there have been some delays on the project due to a lack of resources. What should the project manager do next?

A.

Review the milestone list to determine which tasks can be fast-tracked

B.

Review the risk management plan to identify the response strategy

C.

Escalate the issue to the sponsor and debrief them about the situation

D.

Organize a team meeting to discuss the next course of action

Project A is critical for the company and must be completed within nine months. The project charter has been signed but the project scope statement has not been prepared Management asks the project manager to move forward with the project without an approved project scope statement

What should the project manager do next?

A.

Escalate the issue to the project sponsor and add it to the risk register

B.

Refuse to work on the project because management is not following standard project management practices

C.

Meet with management to explain the potential problems with running a project without a project scope statement

D.

Start the project with inputs from the project charter to save time

A project manager has been appointed to a multimillion-dollar project The project is considered to be high risk since no similar projects have been undertaken before and there is no historical data Some external stakeholders are reluctant to provide support

What approach should the project manager take?

A.

Examine the plans, processes, policies, and knowledge that are specific to the organization undertaking the project

B.

Establish dialogue with stakeholders on the project constraints, assumptions, and critical inputs

C.

Convince senior management to close the project since the project lacks sponsorship and is considered to be high risk.

D.

Host a project team meeting, then update the risk register and the project management plan

A project manager for a strategic initiative realizes a new stakeholder is interested in the project and wants to ensure the stakeholder is fully aware of the goals, objectives, benefits, and risks of the project. What should the project manager do to enhance the success of the project?

A.

Add the new stakeholder to the communications management plan

B.

Share the project status reports with the new stakeholder.

C.

Update the stakeholder engagement plan

D.

Schedule a meeting with the new stakeholder

During the execution phase of a healthcare IT project, stakeholders made a change request regarding user requirements There is no remaining budget available to cover that change request.

What should the project manager do next?

A.

Discuss approval of the change request in the next project meeting

B.

Perform a risk assessment on the required change request.

C.

Evaluate the change request against the project scope statement

D.

Ask the sponsor for more funds to cover the change request

A project manager has a team of shared resources from other projects who are working on a client project Three days before the project is due. The team informs the project manager that the project will be delayed because a component was not delivered on time Competing priorities of the shared resources are delaying delivery of the component

What should the project manager have done to prevent this delay from happening?

A.

Updated the risk management plan and registered lessons learned for the project

B.

Reorganized the team for the project based on the work breakdown structure (WBS)

C.

Maintained constant communication with the stakeholders of the other projects

D.

Used the resource management plan to identify the impacts of the other projects

A project manager has team members around the world in many different time zones Project work frequently stalls because people in one office need to wait until another office is awake to have questions answered.

What should the project manager have done to avoid this?

A.

Used communication tools, such as video conferencing so different offices could communicate.

B.

Learned more about how each team member prefers to communicate before assigning project work

C.

Planned and scheduled tasks and work packages to overcome geographical and time zone challenges

D.

Ensured that the project would be the highest priority for all team members

A company is implementing a new system The project manager has identified that it is best to complete this project using a mix of Scrum and Kanban methodologies The product owner is confused as to how to start delivering the functionalities required

How should the project manager assist the product owner?

A.

Coach the product owner on how to create a product backlog

B.

Encourage the team to subdivide the project tasks

C.

Create a work breakdown structure (WBS) and explain the deliverables to the product owner

D.

Discuss the product owner's responsibilities within the project team

A project has a very tight delivery schedule The project is approaching the delivery date and the project sponsor often sends the project manager alerts to avoid any schedule slippage The project team has performed at an acceptable level until now but the project manager wants to ensure the team's performance level is maintained until the end

What action should the project manager take to motivate the project team’s performance?

A.

Send a formal notice to team members instructing them to maintain performance

B.

Hire a few temporary team members to help with the additional work

C.

Award certificates of appreciation to encourage the team

D.

Inform the team about the delivery pressure from the project sponsor

During a daily standup meeting, a roadblock was raised that is preventing one of the team members from proceeding with work The project manager figures out that it is due to a technical issue.

What should the project manager do to prioritize this critical impediment?

A.

Solve the issue for the team member.

B.

Perform a brainstorming session to address the issue and add the solution to the sprint.

C.

Escalate the issue to the software vendor for technical resolution

D.

Coach the team to come up with their own solution and add it to the next sprint

A team is holding the first demonstration of the software built to date on a medium-sized project The product owner has uncovered a number of issues they would like to be addressed before providing approval

How should the project manager approach this problem?

A.

Plan to address the issues through backlog grooming and incorporate them into the next sprint

B.

Refer the product owner to the change management plan, then escalate to the steering committee

C.

Refer the product owner to the signed business requirement document and explain that the current plan cannot facilitate these changes

D.

Tell the product owner the issues will be addressed in the second version of the software

The customer is reviewing the new reporting system and informs the project manager that one of the components in the printing module is not complete The project manager reviews the work breakdown structure (WBS) and confirms that the component Is included.

What does the project manager need to do first?

A.

Raise a change request to immediately implement the printing module component.

B.

Escalate this issue to the project sponsor immediately

C.

Ask the project team to conduct a quality audit of the printing module components.

D.

Meet with the project team to understand the issue and define actions.

A learn has been working for two months and has consistently missed planned user stories How should the project manager address this issue?

A.

Ensure the sprint size is appropriate for the iteration duration.

B.

Promote changing the iteration duration in order to commit as planned.

C.

Engage in recruiting a highly skilled resource to reinforce the skills.

D.

Consider using a reward system to encourage timely delivery

A global petroleum crisis has affected the distribution of crude oil in the region where the construction project is underway Materials are not being delivered on time and this phase of construction is already behind for what was initially planned.

What should the project manager do first to prevent the project from going further off track?

A.

Perform a risk assessment and define a risk response action plan.

B.

Proceed with the project using management reserves to cover any delays or losses.

C.

Propose a pause in this phase to save labor costs and asset depreciation.

D.

Establish new partnerships with other suppliers in anticipation of any delays.

A project manager of a large company needs to categorize the stakeholders' involvement at the beginning of a project initiated by the board of directors. The sales and delivery teams are internal teams.

Drag each stakeholder scenario on the left to the correct engagement level on the right.

A team has different ideas on how to address a feature of a product under construction and; although the sprint began two days ago, they have still not reached a consensus. What should the project manager do?

A.

Ask the product owner, who is the key stakeholder, to choose among the different ideas.

B.

Propose ideas to the group, ask everyone to vote, and then choose the most popular idea

C.

Schedule a session to give everyone the chance to express their opinions about each idea, then vote and decide.

D.

Offer an opinion about the pros and cons of each idea and try to reach a consensus in a facilitated meeting

A project team has recently completed the initial sprint for developing an automated payroll system for a company The project manager has scheduled a sprint planning meeting with the product owner and team members to discuss which features should be worked on next

Which two pieces of information does the project manager need in order to make this meeting productive and effective? (Choose two)

A.

Sprint charter

B.

Burndown chart

C.

Company mission and vision

D.

Product backlog

E.

Sprint goal

A software project using an agile approach is facing quality issues with every release, generating many production problems. What should the project manager do to fix the problem and improve the quality?

A.

Seek extra funding approval with the sponsor to replace junior team members for more experienced ones

B.

Create a reward system granting incentives to the team members who are able to catch more defects

C.

Hire an external company to add an additional layer of testing, making sure that the final product is well inspected before releasing.

D.

Use the retrospective meeting to better understand the root cause of the quality problems and put together a plan with the team to address the problems

While reviewing prototypes, the quality team found some deviations that do not affect the mam functionality but have the potential to be an issue in the future To avoid major problems in the future, the team recommends corrective actions that will require additional funds The project is already struggling to stay on budget and has even used some of the contingency reserves

What should the project manager do?

A.

Ask the product designer why the deviation was not considered in the design phase

B.

Report to the project sponsor that the product is working and the project is struggling with the budget.

C.

Evaluate and initiate the change request process with the stakeholders

D.

Ask the quality team to discard the sample and test again with a new sample

A new project manager is assigned to lead an agile project The project manager wants to use motivation to encourage the team to perform well throughout the project

What should the project manager do?

A.

Use the management reserves to fund some team-building activities

B.

Inflate project estimates to provide a financial buffer for team activities.

C.

Find another method to increase the team's performance

D.

Implement a reward system aimed to keep the team engaged and motivated

A project manager is leading an in-house company project in its very early stages This current project is similar to another project that ended a year ago

What should the project manager do to analyze the involved stakeholders?

A.

Lower the priority of stakeholder engagement as the stakeholders already have knowledge of this kind of project

B.

Use lessons learned from the previous project as a guide for the current project's stakeholder register

C.

Refer to the stakeholder register from the previous project as it was similar to the current project

D.

Document in the risk register that the current project may have different

stakeholders than the previous project

A multinational company has a plan to expand their business into a new country where they currently have no presence A project manager is assigned to initiate this project

After reviewing the business case, what should be considered first when developing an appropriate implementation strategy?

A.

Acquire project resources from the new country to mitigate the risk of uncertainty

B.

Evaluate the environmental and regulatory factors and identify high-level risks and assumptions

C.

Identify and monitor the risks closely since the company does not have lessons learned for this country.

D.

Ensure that project sponsors are in agreement on the project deliverables and timeline during the project

A verbal announcement is made that the new team member joining the Scrum team has limited mobility The scrum master is aware that some team members are unsure how the dynamics of the team will change

What should the scrum master do?

A.

Create a stakeholder engagement plan

B.

Design a communications management plan

C.

Update the team charter accordingly.

D.

Set up a meeting to discuss accommodations the team will have to make

A project manager accepts a delivery at the project site but the items are of a poor quality The project manager gets the local vendor to fix the items but more deliveries from this vendor are expected

What should the project manager do going forward?

A.

Allocate extra time to inspect deliveries for quality assurance upon arrival at the site

B.

Review the contract requirements and ask for the applicable evidence for quality assurance

C.

Have the vendor issue the quality documentation prior to the next delivery.

D.

Call the vendor and have them verbally guarantee the quality of the next site delivery