PMI PMP - Project Management Professional (PMBOK 7th Version)
A project manager is working on a project. A few months after the project has launched, the project manager starts receiving complaints from business unit managers about the lack of updated project information. What should the project manager do?
A project sponsor is transitioning their division to an agile environment and has emphasized that project team members and stakeholders should collaborate to achieve deliverables. On a few occasions, progress has been interrupted by one stakeholder who is unfamiliar with agile approaches. What should the project manager do first?
A project manager is assigned to a large complex project with cross-functional dependencies. The project enters a new phase requiring new stakeholders to be added with conflicting priorities. How should the project manager ensure successful engagement with the stakeholders?
A large corporation is transforming itself from a predictive to agile approach A project team with knowledge of agile practices is experiencing significant conflicts with the executives regarding the processes to be followed.
How should these conflicts be resolved?
A project manager is leading a meeting with key stakeholders, the project sponsor and the product owner to define the features that will be released after the next iteration. The purpose of the meeting is to review the product backlog prioritization, considering that during the past iteration some deliverables were not completed.
Which two items should be taken into account first to review and update the product backlog priorities during the meeting? (Choose two)
The execution stage of a construction project is beginning. There are many areas and phases to be built. The project team wants to review the relationships between the most important tasks to ensure that major items are executed properly during this stage. What project artifact should the project manager review with the team?
Near the closing stage, a project is delayed due to staff shortages. In order to meet the mandatory deadline, additional resources are necessary, but there is no additional budget. What should the project manager do first to obtain the funding to hire the needed resources?
A project manager notices a product owner has been unresponsive over the last few weeks. During one-on-one sessions, the product owner is unable to provide complete information, leading to rework of the project stories. What should the project manager do first?
A team is holding the first demonstration of the software built to date on a medium-sized project The product owner has uncovered a number of issues they would like to be addressed before providing approval
How should the project manager approach this problem?
An agile project is in its eighth iteration out of 16 After the last iteration review, the team members receive feedback from the security department about regulations with which the project must comply
Which two actions should the project manager take? (Choose two)
A technical subject matter expert (SME) identifies an occurrence that should be captured in the project's lessons learned The SME asks the project manager to write, document and include it in the lessons learned register
What should the project manager do?
At the end of a project with multiple suppliers, the project manager is reviewing the closing process and finds that an unexpected financial balance is remaining What will help the project manager understand why this has occurred?
A company's project management office (PMO) has started to implement iterative tools A project manager is starting a new project and has identified an opportunity to use the iterative tools One of the senior managers is concerned about this modified framework as it is fairly new to the company
What should the project manager do first?
A project manager is working on a software development project. A team member complains that since the project tasks are very simple, there is no reason to perform quality control The project manager understands that removing the quality management plan from the project will also help to save money, which is important to the customer
What should the project manager do?
A project manager has been assigned to an education project with the objective of training a workforce in application development One of the deliverables is to provide internships to the best students in the customer's active projects However the customer does not have enough projects in progress right now The project manager decides to create several internal projects in order to ensure the internships
Which three actions should the project manager take to fulfill this scenario without adding costs for the customer? (Choose three)
A company is using a predictive approach for the development of a particular component as defined in the scope management plan Due to regularly changing regulatory requirements, the development team has requested to utilize agile approaches
What should the project manager do about the development team's request"?
During the daily meetings with the team the project manager notices that a new team member is not making the expected progress on an assigned task What should the project manager do?
A project manager is in a learn meeting and the project team requires a decision to be made about a new suggested timeline due to an impact from a potential scope change What should the project manager do?
A team has different ideas on how to address a feature of a product under construction and; although the sprint began two days ago, they have still not reached a consensus. What should the project manager do?
A project manager who is managing a critical project in a multinational company is conducting a progress meeting with all team members. During the meeting, one of the team members states that they are facing a critical problem that will prevent them from completing their assigned task
What should the project manager do?
After gathering all the requirements for a project with dependencies on external stakeholders, the project team is finishing the second iteration At this point, the project manager learns about a possible change in regulations that would prevent the product launch
What should the project manager do to realize benefits?
After the project charter's approval the project manager needs to work on detailed project requirements, constraints and assumptions with stakeholders However, not all of the stakeholders are immediately available for a meeting in the short term.
What should the project manager do in order to gather the information needed from stakeholders?
A project manager is worried that a key stakeholder is not participating in the project and has concluded that the final product is not as good as it could have been if the stakeholder had been more involved Drag the scenario on the left to the correct risk response strategy on the right

An agile project is running activities to define the minimum viable product (MVP) During the session, the project manager identifies some mandatory regulations but there is no consensus to include these regulations in the MVP because it may extend the duration of the project
What should the project manager do?
A project manager leads a regulatory initiative with tight, non-negotiable timelines. During a status meeting, a key stakeholder asks if a critical milestone associated with the reporting functionality can be moved up by 4 weeks.
What should the project manager do first?
A global petroleum crisis has affected the distribution of crude oil in the region where the construction project is underway Materials are not being delivered on time and this phase of construction is already behind for what was initially planned.
What should the project manager do first to prevent the project from going further off track?
An agile project manager would like to convert the requirements document into epics, capabilities, features and stories In how many iterations should the project manager estimate the story duration?
The project is delayed due to the high amount of major changes requested by different stakeholders at different stages of the project If the project continues on the same path, it will consume twice the time and budget planned.
What two actions can the project manager take to be more cost effective? (Choose two)
A project manager is struggling to figure out the performance of the project teams in an agile environment for the same scope of work, team A has calculated 100 story points and team B has calculated 125 story points
Which team is performing better?
The team has reported the following impediments at the daily standup meeting Drag each impediment on the left to the action that the project manager needs to take on the right

A company's new communication system will include online dashboard reporting. The executive board might receive bi-weekly performance reports through the online dashboard What should the project manager do?
A team member misses a project meeting without it being approved and has been penalized as defined in the ground rules. This team member, as well as other team members, insist that it is the first time they have seen this rule regarding the project and they do not agree with the penalty
What should the project manager have done to avoid this situation?
An agile team is geographically separated across multiple continents, and the project manager of identifying the tools to manage the communication among the virtual teams Drag the appropriate tool on the left to each project task on the right

A verbal announcement is made that the new team member joining the Scrum team has limited mobility The scrum master is aware that some team members are unsure how the dynamics of the team will change
What should the scrum master do?
A project manager for a large multiyear industrial project has a project with diversified stakeholders from various geographical areas. Recently, the project manager encountered an issue with stakeholder engagement
Which two tools should the project manager use to determine the underlying reason for why engagement is not having the planned effect? (Choose two)
A project manager is responsible for building a bridge The high-level elements of the project are handled using a predictive approach The software responsible for retracting the bridge has been developed based on agile principles During software development, the workflow is often interrupted by various delays or impediments due to lack of information
How should the project manager handle this situation?
During project execution, a project manager is informed that most of the project team members have enrolled in the newly implemented work-from-home company policy. How should the project manager reflect this change in the project?
A company is changing their current business model The change requires implementing a complex project using multiple agile teams.
What three options should the project manager have the testing team adopt as testing mechanisms? (Choose three)
A new project manager for an agile project is reviewing with an established team, some of the roles to avoid confusion on what to expect. Drag the description on the left to the role on the right

A project manager is managing a complex research project with a high level of uncertainty A request is made to implement a mechanism to measure the quality of the deliverables.
Using a hybrid approach, what techniques can be used to achieve this goal?
The resource management plan is already done, and the team is located in different countries around the world Team members are in multiple time zones and they use different languages for communication The project manager needs to keep the team organized and avoid misunderstandings and miscommunication that may produce a negative impact to the project
What should the project manager do to reduce negative impacts to the project?
A project manager has been assigned to lead a project to deploy a new system. The stakeholders disagree on the project objectives and approach.
What should the project manager do?
A project manager is assigned to a project within a program. The high-level requirements of the project are known, but the priorities of some of the requirements are uncertain as they are interdependent on some other pipeline projects within the program.
How should the project manager prepare for the next steps of the project?
During project execution, the project manager discovered that a key deliverable was missing from the scope of work After investigation, the project manager and the team discovered that the missing deliverable will impact the critical path
What should the project manager do to avoid future delays?
Five agile teams working together on a product recently performed release planning Midway through the project, each team showed that their progress was on track When all of the teams integrated at the product level, many integration issues were observed The overall product release progress declined with predictions showing the committed content will not be able to be accomplished
What should the project manager have done differently?
A team has been working on a project for several months,, but the completion date is unclear because the scope is changing frequently as new knowledge is gained. Some deliverables have already been completed, but when new stakeholders join the team, they complain that project outcomes are not meeting business goals.
How can the project manager prevent this situation from happening in the future?
A team member shares with their functional manager some negative details about the performance of another team member that was discussed during the retrospective. The project manager finds out about this discussion
What two actions should the project manager take? (Choose two)
Two functional managers disagree on key features of one deliverable during the planning of a project The project manager discovers that each manager included requirements that contradict each other The functional managers do not want to meet with each other to find a solution This situation has been escalated to the sponsor who requests a meeting with them
What strategy should the project manager use to resolve this conflict in the meeting?
During the implementation phase of a project, a new regulation affects the project, and a critical status meeting discussing the scope changes is required. The project manager discovers that a key stakeholder cannot attend the scheduled meeting
What should the project manager do?
During the design phase of a project the project manager notices that the schedule performance index (SPI) is 1 8 and the cost performance index (CPI) is 0 1 In a weekly meeting with top management, the project manager reports concerns about these indicators However the most concerned person was the project sponsor who said that if the trend continues, they will be forced to prematurely close the project
What should the project manager do?




