Weekend Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmas50

PMI PMP - Project Management Professional (2025 Version)

Page: 2 / 11
Total 1704 questions

During the last two iterations of a project, one of the team members had low performance. The project manager conducted two feedback sessions with the team member and escalated the issue to the resource manager and project sponsor, but there has been no improvement.

What should the project manager do next?

A.

Escalate the situation again to the project sponsor.

B.

Review this obstacle during the daily standup meeting.

C.

Request a new resource to execute the activities.

D.

Provide feedback to the resource at the sprint review.

An agile team wants to maximize the work delivered for the upcoming project that involves considerable product complexity. What should the

project manager do to help improve the team's collaboration approach?

A.

Meet with the human resources (HR) department to ask for team support.

B.

Follow the process of the most successful team in the organization.

C.

Compare the team's velocity with other teams in the organization.

D.

Focus on the team's engagement during the next retrospective meeting.

During execution of an agile project, a project manager realizes the budget is almost completely used, but the project is not close to being completed. What should the project manager do to address this concern?

A.

Review the project time line and find opportunities to reduce the project schedule.

B.

Review the budget with the project sponsor and ask for an increase to the budget

C.

Review the backlog and find opportunities to reprioritize the work and reduce the project scope

D.

Review the resource management plan and find opportunities to reduce project costs.

A project manager is managing a large project. A stakeholder has just discovered a new risk that has not been identified in earlier stages.

What should the project manager do?

A.

Communicate the risk to the steering committee and request a mitigation plan from senior management.

B.

Perform a risk analysis directly with the stakeholder who raised the risk and update the risk register.

C.

Confirm to the stakeholder that the risk register has been completed and validated by all stakeholders.

D.

Add the risk to the risk register and reevaluate the register with help from the project team and stakeholders.

The current incremental revenue expected by a project deliverable is not fulfilling the business case requirement The deliverable was already closed and handed over to the operations team

Which two actions should the project manager take? (Choose two)

A.

Review the issue with project sponsor and submit a change request

B.

Report the issue to the product manager and business segments

C.

Analyze the business benefits criteria and assumptions

D.

Discuss the issue with the operations team to assess expense overruns

E.

Schedule a project review meeting to analyze the root cause

A project manager is managing a new development program to automate some technical functions. During project kickoff, the project manager

expresses the need for a technical architect to support the project for a moderate amount of time. The project sponsor informs the project

manager about an existing technical architect who possesses valuable knowledge but is already assigned at the portfolio level.

What engagement model should the project manager use for the technical architect role to ensure project success?

A.

Hire a new technical architect who would be solely dedicated to the current project.

B.

Share the existing technical architect so they can be allocated to the current project and other projects.

C.

Hire a new technical architect who would be shared between the current project and other projects.

D.

Assign the existing technical architect to solely be dedicated to the current project.

A project sponsor has approved the project charter and business case. The project manager has reviewed the artifacts to initiate the project and is unclear if the intended benefits of the project align with the strategic objectives of the business.

What should the project manager do first?

A.

Start executing the project since leadership is responsible for the business strategy.

B.

Meet with the project sponsor to better understand the strategic benefits of the project.

C.

Propose an updated business case and project charter that are more aligned with the business strategy.

D.

Conduct qualitative and quantitative risk analysis and record the results in the risk register.

A product owner has returned from a meeting with a few key stakeholders, who expressed interest in learning more about the project progress. The product owner is

seeking the project manager's recommendation on how to approach this request.

What should the project manager do to help the product owner?

A.

Provide an overview of the completed functionalities and release plan, and capture expectations for future stakeholder involvement.

B.

Invite the product owner to future demonstrations where they can provide feedback.

C.

Provide access to the latest user acceptance test (UAT) environment so they can see the solution.

D.

Remind the product owner of stakeholder accountability, and ask the product owner to determine the appropriate next steps.

A project team is performing extremely well when it comes to delivering the value-added features to the customer in each sprint. However, they are missing the

documentation portion and the project manager must find a way to make sure the documentation is kept current.

Which action should the project manager take?

A.

Create a specific sprint to deliver the project documentation.

B.

Assign a dedicated resource to work on the documentation during the project.

C.

Make documentation a standard part of the definition of done (DoD).

D.

Focus on the documentation after the features are delivered.

A product owner has added new high-priority work to the backlog, A project manager is working with a dedicated agile team that does not specialize in this specific area of work. The team reviewed the work and wants to accept it but acknowledges it may not have the same level of efficiency as another team having specialization in this area.

What should the project manager do In this scenario?

A.

Add temporary members with the specialized skill set to the team to accomplish the work with a high level of confidence.

B.

Assess the impact of a possible delay to the project and encourage the team to take the work if the impact is tolerable.

C.

Accept the work and outsource it to another team that has the specialized skill set; then integrate the solution,

D.

Reject the work from this team's backlog and ask the product owner to add It to another team's backlog.

The investment committee is the authority for the approval of funding required for a business improvement project. The investment committee approved funding to complete

the preliminary feasibility study. The project is on an expedited schedule, and the project manager requires interim funding to continue with the preliminary feasibility

activities that must commence immediately.

How should the project manager get these funds approved?

A.

Wait until the next investment committee meeting to submit the request and include the delay in the schedule due to work that could not start.

B.

Continue with the preliminary activities and inform the investment committee at the next monthly meeting.

C.

Exclude the preliminary scope from the full project scope and continue it as a new project that does not require investment committee approval.

D.

Submit the request to the project director for interim approval and include this approval for discussion at the next investment committee meeting.

A project manager wants to ensure that the project acceptance criteria are met for all project deliverables. What should the project manager do to accomplish this?

A.

Schedule regular meetings with project stakeholders to make sure they are satisfied.

B.

Include project stakeholder expectations and needs while creating project acceptance criteria.

C.

Create a statement of work (SOW) and ensure it remains unchanged during the project life cycle.

D.

Discuss project acceptance criteria with the project sponsor before the execution phase.

A project manager is assigned to an organizational transformation project. The company typically defines individual performance plans at the beginning of the year, and functional managers conduct feedback reviews at the end of the year. The transformation project team members are concerned that the work they are doing for this project is not aligned with the work included in their individual performance plan for the year.

What should the project manager do?

A.

Meet with the functional managers to align the expected frequency and results reporting for the team members.

B.

Provide performance feedback to the learn members' functional managers at the end of the year.

C.

Assure team members that this project is a high priority for the company and they will be evaluated accordingly.

D.

Request to be made responsible for the performance plans of those on this project team

When defining the ground rules for a project team, the project manager observed that only two team members contributed to the discussion. As a

result, the team ground rules favor these two team members.

What should the project manager have done to avoid this situation?

A.

Come to the meeting with suggested ground rules

B.

Ask all team members to send new ideas prior to the meeting

C.

Extend the meeting to allow everyone to speak

D.

Set expectations for contributions ahead of the meeting

A project manager holds meetings every Monday to review the team members' progress. The project sponsor is insisting on daily updates to ensure improved delivery on products developed by all of the teams, including this one. Some learn members indicate they are on a very light time line and would attend me Monday meeting, but not the daily update meetings.

What should the project manager do to ensure all team members participate in daily meetings?

A.

Analyse the team members' influence levels and schedule a training on the importance of daily standups and the time-bound feature of the meetings.

B.

Require all team members to attend the daily review meetings as they ate requested by the project sponsor.

C.

Inform the functional manager and replace (earn members who cannot join the daily progress meetings.

D.

Review the influence of each team member, call the team members with the highest influence to a meeting, and convince them to join the daily standups.

A project is about to start. The project manager has found that the client does not have an appropriate knowledge management system and does

not have a requirement for it.

What should the project manager do?

A.

Ask the team to collect the knowledge locally and share it at the end of the project.

B.

Utilize the cloud wiki to collect the necessary knowledge.

C.

Coordinate with the team and the project stakeholders to collect the knowledge.

D.

Provide just-in-time knowledge to the client, upon request.

A human resources (HR) cost report was disclosed, by error, to all members of the project team. This situation generated a conflict between the team members about differences in their salaries.

What should the project manager have done to avoid this situation?

A.

Ensured reports with significant information were not included in the communications management plan

B.

Defined the appropriate recipients for the report in the communications management plan

C.

Included noncompliance punishment measures in the communications management plan

D.

Validated the information and the appropriate recipients per the communications management plan

An experienced project team member always points out the issues of other team members during meetings. The other team members feel that

the experienced team member is deflecting their own issues in meetings.

What should the project manager do?

A.

Arrange separated group meetings to allow everyone to express their opinions.

B.

Review the communications management plan with the team and enforce its implementation.

C.

Prepare an agenda for all future team meetings and facilitate the discussion.

D.

Speak with the experienced team member to discuss the issues in a supportive way.

While following up on a deliverable, a team member expresses concern to the project manager about working with another team member. This team member states that the other team member, who is a functional manager, is often defensive and aggressive during meetings.

How should the project manager handle this situation?

A.

Suggest that the team member ignore the disruptive team member and focus only on the work.

B.

Encourage both team members to meet as soon as possible and resolve the problem

C.

Monitor the situation for a few weeks to determine if the disruptive team member's attitude changes.

D.

Report the disruptive team member to the human resource (HR) department.

An agile team is facing a challenge with the quality of its deliverables. Every time a feature is promoted to production, many defects arise, preventing the customers from properly using the solution.

What should the project manager do to avoid this situation in the future?

A.

Create a team incentive program with prizes, allowing the team members to work overtime to find defects.

B.

Reduce the release cycle and invest more time on stabilizing the current features instead of releasing new ones.

C.

Hire a quality assurance specialist and integrate a second phase of testing into the current project life cycle.

D.

Use the next retrospective to understand the root cause of the quality issues and have the team come up with an action plan.

A project manager is working on a time and materials (T&M) project using a hybrid approach. The milestones and outcomes are defined for the first 6 months with

incremental releases every month. After the first 2 months, the client communicates their dissatisfaction with the results and asks to change the course of the project. The project manager held a face-to-face meeting with the client and now has a better understanding of the newly desired milestones and outcomes.

What should the project manager do first?

A.

Forward the client's request to management as a change request to get formal approval.

B.

Document the information in the meeting minutes and share it with the project stakeholders.

C.

Draft a contract change with the desired scope changes and send it to the client for approval.

D.

Finish the current monthly release as it was planned and replan for the future months.

A project team is executing a large regulatory project comprised of a multitude of internal and external stakeholders. An initial impact analysis revealed several systems, including an enhancement to existing modules as well as new builds. After completion of the initial design workshop, the team conducted a brainstorming session to better understand the types of likely users.

Which technique will best serve this purpose?

A.

Personas

B.

Power influence grid

C.

Power user grid

D.

Salience model

A risk was identified at the beginning of a project, and a response plan was established. Unforeseen consequences resulted in a higher level of

risk. The project manager has an idea that could address the new risk in an efficient way, but the response is different from the original risk

mitigation plan.

What should the project manager do?

A.

Submit the new response plan to the stakeholders for their review.

B.

Obtain management approval prior to implementing the new risk response.

C.

Use the management reserve to mitigate the risk.

D.

Implement the new response to address the risk.

During an agile project a project manager lost one of the resources, and at the same lime, uncovered new requirements, which were added to the backlog What should the project manager do next?

A.

Reevaluate the project schedule as the velocity will be impacted by the loss of resources

B.

Reevaluate the backlog priority with the product owner since the velocity has been impacted

C.

Reevaluate the scope of the current iteration to keep the same velocity and timeline

D.

Reevaluate the velocity as the iteration duration will be impacted by new requirements

A project manager is managing a technical project that requires intensive documentation as part of the key deliverables. Ina project review meeting, a key stakeholder reports that the latest documentation provided by the project manager includes a reference to unrelated products.

What should the project manager do?

A.

Ask the project management office (PMO) to support and review all deliverables.

B.

Log the issue in the risk register and the issue log.

C.

Assign a technical writer to the project.

D.

Develop a standard for document quality control.

A project manager is newly appointed to an ongoing project that will develop a new solution using an affiliate of the company. The deploying

resources will come from another entity of the company. When asked to confirm the availability of the deploying team, the deploying manager declined.

What should the project manager do first?

A.

Reschedule the project taking this new information into account.

B.

Refer to the project's resource management plan.

C.

Ask the project sponsor for external resources.

D.

Create a change request to be validated by the project sponsor.

Midway into a project, the project manager is concerned with the lack of responsiveness from a vendor. What should the project manager do to

ensure the project is delivered successfully?

A.

Ask the vendor to communicate via the established channels.

B.

Invite the vendor to a meeting to discuss the concerns.

C.

Escalate the vendor's lack of responsiveness to the project sponsor.

D.

Proceed with other tasks while awaiting a response from the vendor.

A company is transitioning from a predictive approach to an agile approach. A project manager is assigned to the first pilot with an inexperienced team. Due to an unexpected event, the whole team is asked to work remotely. During the second sprint, the project manager starts to notice a lack of commitment from the team members.

What should the project manager do in this situation as a servant leader?

A.

Request an exception to allow the team to return to work on-site

B.

Allow the team to address the problem as a self-organized team

C.

Coach team members to increase their engagement and collaboration

D.

Force the team to attend the daily standups to gather the project status

A project has come to the closing stage. The work is generally finished, and the project manager wants to commence the closure process for the project. What should the project manager ensure is in place prior to the closing process?

A.

The organizational process assets (OPAs) have been updated.

B.

The contractual deliverables of the project have been accepted.

C.

It The handover and deliverable acceptance have been completed.

D.

The lessons learned sessions have been conducted.

A project manager is made aware that there are defects in the parts provided by a supplier, which are causing delays in the testing phase. The supplier claims that all parts have been delivered as per the contract. If the defects are not fixed by the supplier within one week, the product release will be impacted.

What should the project manager do?

A.

scalate this issue to senior management, as the supplier is not following the procurement contract.

B.

Request a revision of the procurement contract to include specifications for the parts.

C.

Request a cancellation of the procurement contract with the supplier and impose a penalty.

D.

Review the procurement contract and ask the supplier to negotiate a solution.

A project manage is in the middle of an angle project comprised of 100 user stories broken down into five iterations. Each user story is worth U$$50. The actual expenditure is U$$2,00 and 50 user stories have been delivered.

Which statement is true?

A.

The project is over budget and behind schedule.

B.

The project is under budget and on schedule.

C.

The project is under budget and behind schedule.

D.

The project is on budget and on schedule.

A project manager is assigned to a project team midway through execution. Several dependencies are impacting the project, and the project manager feels the team is not adequately informed of the impacting changes.

What should the project manager do first?

A.

Convene an impact analysis meeting.

B.

Escalate the issue to the product owner.

C.

Consult the communications management plan.

D.

Review the stakeholder register.

A project manager is managing an internal project with a tight budget and schedule. While executing the project, the project manager realizes that

some stakeholders are working against the success targets of the project.

What should the project manager do to ensure successful project delivery? (Choose two)

A.

Update the project stakeholder analysis and methods to satisfy the stakeholders’ requirements.

B.

Escalate the issue to the functional manager and ask for support.

C.

Involve all stakeholders in the project by distributing status reports.

D.

Focus on the supportive stakeholders and minimize involvement of unsupportive stakeholders.

E.

Engage all stakeholders in the project including the unsupportive stakeholders.

At a recent steering committee meeting, the project sponsor asked the project team to add a major feature to the final product. After consulting

with the project team, it is determined that the change will cause significant impacts to the original project delivery date and budget.

What should the project manager do to assess the priorities and meet the new objective?

A.

Submit a change order request with the new project objective to the project management office (PMO).

B.

Initiate a crashing routine to gain extra time for the added feature.

C.

Communicate the results and negotiate the needed resources and time with the stakeholder.

D.

Ask the project team to work overtime in order to accommodate the new changes.

Within a project, senior management is requesting project information so they can analyze the data to make project decisions. What information

should the project manager provide so that senior management can get a broader view of the project?

A.

Risk register information

B.

Higher-level activities completed

C.

Milestones status report

D.

Resource breakdown structure (RBS)

In a highly politicized organizational environment, the stakeholders are driven by their own operational or business goals, which results in

conflicting interests regarding the project. What should the project manager do to steer the stakeholders toward the collective project goal?

A.

Anticipate, alert, and follow the risk management process.

B.

Detect, track, and follow the issue management process.

C.

Promote, inspire, and follow the stakeholder engagement process.

D.

Discuss, educate, and follow the communications management process.

A project manager has recently taken over a project and notices that a client team member often halts progress due to a lack of understanding of some project elements.

The former project manager gave the new project manager a complete list of people to communicate with, and this client team member is not on it.

What should the project manager do?

A.

Update the communications matrix to ensure that client team member is included.

B.

Submit a change request to cover extra hours associated with project meetings.

C.

Increase the project meeting frequency and duration to allow for the extra work required.

D.

Speak with the client team member about the continuous delays during project meetings.

A project manager is working for an organization in country A and has been tasked with opening the first brick-and-mortar store in country B. The sponsor has identified the city for the store and wants to minimize any potential issues with the local government.

Which action should the project manager take to address the sponsor's request?

A.

Work with the organization's real estate department and reach out to the local government to identify the best location for the store.

B.

Work with the local government to build the profiles of employees that will be working in the store.

C.

Work with the organization's legal department to identify local regulations to ensure project compliance.

D.

Work with the organization's project management office (PMO) to build a project team of residents located in the city.

A project manager was recently assigned to a project that is in the execution phase and is experiencing roadblocks. During a review of the

processes and procedures, the project manager notices similarities to a previous project that experienced similar roadblocks. The project manager

reviews the task schedule and finds that certain tasks are well behind expectations. In speaking with the project team, the project manager

confirms that the team is following the processes exactly.

What should the project manager do?

A.

Update the schedule to account for the unexpected delays in the project tasks.

B.

Review the resources allocated to the project and change accordingly.

C.

Review and amend the processes to ensure only value-adding activities are present.

D.

Update the variation register to account for the extended project time.

A company is undergoing a digital transformation and is changing its project portfolio to an agile approach. As a result, the leadership is looking to update the performance measuring system for the workforce.

What should the project manager propose?

A.

Keep the performance management as is and focus on the achievement of scope, cost, and schedule indicators.

B.

Propose an approach based on value measurement, such as the use of objectives and key results.

C.

Maintain focus on cost indicators, but remove scope and schedule as they are flexible with an agile approach.

D.

Maintain the focus on schedule indicators, but remove scope and costs as they are flexible with an agile approach.

A project manager for an iterative project noticed that retrospective items indicate that the team is not fully conversant with the principles of iterative development. The team meets to analyze the gaps in the training that recently concluded with a third-party trainer.

What should the project manager do next?

A.

Initiate hybrid development as an interim approach.

B.

Let the project team self-organize and develop their skills.

C.

Mentor and coach the team to meet the project needs.

D.

Review the training contract to determine the next steps,

The first task a project manager needs to complete on a new project is improving stakeholder engagement. How should the project manager complete the power/interest grid based on the following scenario:

• The marketing director is the key stakeholder. as the project will create a new product for the company.

• The finance director is providing funding and does not have much time to follow the tracking of the project.

• The sales representatives assigned to the team provided some negative feedback on the requirements

• The human resources (HR) intern assigned to the team was satisfied with the new product interlace.

A project's business case was just approved and the project manager is creating the benefits management plan. It is unclear how the benefits from the project align with the organization's vision.

What should the project manager do first to verify alignment?

A.

Ask the project team to delay the kick-off while resolving the concern.

B.

Request a copy of the project assumptions log for more insight.

C.

Meet with the project sponsor to obtain more information.

D.

Consult with the project team members to gain their opinions.

A team member has very strong technical skills and is interested in a leadership role. A leadership position opens up outside of the team in the organization. The project manager has observed that the team member has a major gap in communicating in a professional manner.

What should the project manager do?

A.

Suggest the team member focus on positions with technical aspects and possible technical career opportunities.

B.

Recommend the team member for effective communication training and support their career development interests.

C.

Encourage the team member to stay in their current role as they are important to the project.

D.

Ask the team member to refrain from pursuing new opportunities as they are not a suitable fit for a leadership position.

A project manager is working with a colocated agile project team that has worked together long enough to be in the performing phase of team development. An unforeseen event has caused the team to be dispersed and they are now unable to colocate.

What should the project manager do to keep the team performing as effectively as possible?

A.

Ask the project sponsor and executive stakeholders to encourage the team to maintain their performance,

B.

Transition the team from an agile approach to a predictive approach for better performance cantral.

C.

Provide the team with virtual collaboration software and training on the software to minimize disruption,

D.

Evaluate project performance and step in if performance decreases to. an unacceptable level,

A company's project management office (PMO) has started to implement iterative tools. The project manager is starting a new project and has

identified an opportunity to use the new tools. There is disagreement among stakeholders about the use of the adaptive tool.

What should the project manager do first?

A.

Investigate the reasons for the disagreement to understand the gap among the stakeholders and search for consensus.

B.

Discuss the situation with the stakeholders to evaluate other adaptive tools for the project.

C.

Schedule training sessions for the stakeholders on the benefits of the adaptive tools.

D.

Update the risk register and escalate the disagreement to the project sponsor and distribute the status to the team.

A project manager is leading a multiyear project that involves internal and external stakeholders. As the project manager begins to gather requirements, additional business stakeholders express interest in being involved.

Which three actions should the project manager take to ensure proper stakeholder involvement? (Choose three)

A.

Prioritize stakeholders based on the project phase and need.

B.

Develop a stakeholder impact influence matrix to determine the level of engagement

C.

Perform a stakeholder assessment to align with the project objectives.

D.

Include all stakeholders in the stakeholder engagement plan and provide the same level of communication.

E.

Classify and rank stakeholders based on their positions in the organization.

A project manager has established daily standup meetings with the team during the execution phase of the project. The project manager has been successful in removing 75% of the

obstacles reported, but the timeline continues to deviate further each day with no signs of improvement.

What should the project manager have done to avoid this issue?

A.

Prioritized blockers on the critical path

B.

Distributed the daily standup meeting agenda beforehand

C.

Followed the quality control measurements

D.

Developed the team members’ competences:

A project manager is leading a fast-moving project with strict deadlines and minimal time to deliver each milestone. The project manager

discovers that one of the remote team members, who puts alot of effort into delivering the project, has confided in an on-site team member. The

remote team member feels they are not being adequately rewarded and recognized for their job.

What should the project manager do?

A.

Inform the human resource (HR) manager of this situation and ensure this news does not spread.

B.

Make arrangements with the resource's functional manager to relocate the team member to another existing project.

C.

Send a copy of the engagement contract to the remote team member and indicate that the team member is entitled to what is included in the

contract.

D.

Engage the remote team member, empathize with them, and let them know their contribution is appreciated regardless of their remote work status.

During the execution phase of a project, a project manager notices that the project team is not motivated and performance is decreasing. The decision is made to invest in financial rewards for all of the Key team members. After the rewards are distributed, the team is still underperforming.

What should the project manager have done to avoid this situation?

A.

Determined the appropriate type of incentive for key team members

B.

Conducted frequent monitoring on key team members’ performance during project execution

C.

Distributed the monetary incentive according to the team members’ individual performance

D.

identified the underperforming team members and asked the human resources (HR) department to replace them