PMI PMP - Project Management Professional (2025 Version)
At the end of a meeting a functional manager takes the project manager aside to raise some concerns on behalf of a project team member who is unclear about their role and responsibilities for the project What should the project manager do in this situation?
During project execution, the project manager discovered that a key deliverable was missing from the scope of work After investigation, the project manager and the team discovered that the missing deliverable will impact the critical path
What should the project manager do to avoid future delays?
A project manager has received an updated earned value analysis report The following are the key findings from the report
•Budget at completion = USS1 million
•Earned value = US$0 7 million
•Actual cost = US$0 75 million
•Cost performance index = 0 933
Based on this information, what should the project manager conclude about project performance'?
A company's project management office (PMO) has been trying to implement an adaptive approach in the project management framework and a project manager has been asked to use adaptive tools in their next project This is not the first time the request has been made and the previous project failed when adaptive tools were implemented
What should the project manager do?
A project team is experiencing delays in completing a task that turned out to be more complex than initially estimated. This is a critical task that could impact current iteration goals
What two options will help the team initially address this obstacle? (Choose two)
A project for a new product launch is in a very initial stage and the requirements are evolving Due to stiff competition in the market, the customer would like to launch the product keeping the scope flexible. The project team intends to start the work based on the forecast of a similar project delivered last year
Which project approach suits the scenario?
During the course of a project, a junior team member approaches the project manager for some direction and advice on risk mitigation How should the project manager respond?
A project manager realizes that a project is becoming delayed because some key decisions are affected by contradicting views between the organization's senior management and external stakeholders. What should the project manager do?
A project manager for a strategic initiative realizes a new stakeholder is interested in the project and wants to ensure the stakeholder is fully aware of the goals, objectives, benefits, and risks of the project. What should the project manager do to enhance the success of the project?
A project manager is acting as a scrum master in a hybrid project and is dealing with a conflict between team members What strategy should be used to handle this conflict?
Two weeks after the approval of the project management plan for a global project, the project manager noticed that it was approved based on a different level of understanding by international stakeholders and is not what the project manager presented for approval What should the project manager have done to prevent this from happening?
A new project manager for an agile project is reviewing with an established team, some of the roles to avoid confusion on what to expect. Drag the description on the left to the role on the right
According to a new product development process, the marketing department will begin adding business and user requirements directly into agile project documents. Drag the product information on the left to the correct documents on the right
A project manager is leading a project that is in an advanced stage. All high-level risks identified in the risk management plan have been resolved or are no longer a risk for the project. Only low-level risks remain
What should the project manager do now?
A new agile team is forming and the project manager notices that the team is struggling in many areas The team is experiencing both the inability to meet iteration commitments and team member conflicts
What should the project manager do next?
A project manager has a team of shared resources from other projects who are working on a client project Three days before the project is due. The team informs the project manager that the project will be delayed because a component was not delivered on time Competing priorities of the shared resources are delaying delivery of the component
What should the project manager have done to prevent this delay from happening?
A team member misses a project meeting without it being approved and has been penalized as defined in the ground rules. This team member, as well as other team members, insist that it is the first time they have seen this rule regarding the project and they do not agree with the penalty
What should the project manager have done to avoid this situation?
A large project is affecting the neighborhood in which it is located The neighbors are not satisfied with the project and their resistance to the project may affect the project deadline
What two actions should the project manager take'? (Choose two)
Drag the organizational characteristics on the left to the correct scenario on the right
The project sponsor on an agile project informed the project lead that an executive would like an update on the project’s progress What should the project lead do?
In a hybrid project, the customer has issued a contract that specifies the deliverables for each quarter The customer wants to show their stakeholders a tangible outcome in the first quarter and wants to move the second milestone to the first quarter The project manager explains to the customer that it is not feasible unless the requirements for the second milestone are changed
Which two actions should the project manager take? (Choose two)
A project manager is managing a complex research project with a high level of uncertainty A request is made to implement a mechanism to measure the quality of the deliverables.
Using a hybrid approach, what techniques can be used to achieve this goal?
A project manager is responsible for building a bridge The high-level elements of the project are handled using a predictive approach The software responsible for retracting the bridge has been developed based on agile principles During software development, the workflow is often interrupted by various delays or impediments due to lack of information
How should the project manager handle this situation?
The product owner decides to launch a product after a couple of releases knowing that the minimum viable product (MVP) lacks some features One of the key stakeholders the marketing vice president is not happy with the results and questioned the release decision.
What should the project manager do?
A learn has been working for two months and has consistently missed planned user stories How should the project manager address this issue?
The change control board (CCB) has approved a change request to add a new
component within a product. The operations manager discovers the change after its approval
and complains that the implementation of the change will cause significant disruption to the
production line.
What should the project manager do first?
A project manager working on a large-scale network implementation is frustrated
with the hardware supplier. Their deliveries have been consistently late and frequently do not have vital components. The project manager's company has decided to cancel the contract and move to a new supplier, but the only other option is an overseas company.
What should the project manager do first to proceed with this change?
A protect manager is struggling to obtain participation from key stakeholders who do not usually attend project meetings What should the project manager do1?
A project team is identifying project risks for a bridge to be built across a river. The team needs to send out invitations for a risk workshop to better understand the risks involved.
Which distribution list should the project manager use when sending out invitations?
A project manager submits several requests to purchase required hardware and
knows from previous experience that this kind of procurement usually results in disputes
between the company and its suppliers. How can the project manager mitigate this risk in the
request for proposal (RFP) with suppliers?
A project manager finds that there are knowledge gaps in the project team relating to the core competencies required to deliver the desired results. What should the project manager do to achieve the desired results?
A team shared a complaint regarding the scrum master during the last sprint review. The team expressed that they were delayed because the
scrum master did not remove impediments, such as scheduling some meetings with external teams and obtaining a room to work collaboratively,
among other critical blockers.
What should the project manager do?
A project is on its second iteration out of six. The team realizes that a key deliverable will depend on the acquisition of a new device.
What should the project manager do?
A company plans to initiate a project involving a new technology. Approval for the project is required. What should the project manager do?
An insurance company is planning to make a big change to its core application. The project manager realizes there is resistance to change from the sales agents since they
are accustomed to taking orders manually and entering them in the system at the end of the day. With the new change, they will use point-of-sale devices to take orders online.
What should the project manager do to get commitment from the sales agents?
A geographically distributed project team working on an iterative project adopts a new mode of communication following changes in health protocols. The colocated team members are finding themselves challenged with understanding verbal communication and collaboration methods.
What should the project manager do?
During the development of a project in a dynamic market environment, new unforeseen legal requirements have come into effect. The project
manager is not sure if some of the project deliverables will be fully compliant with the new requirements.
What should the project manager do?
A project manager is working on a project with three virtual teams. Team A is in a different time zone than teams B and C. The project was going
well, but recently team A has started feeling left out. Information reaches team A late or is sometimes missed, and teams B and C give preference
to each other's problems over team A. The project manager has already set project guidelines, but realizes they need to be improved.
Which two things should the project manager do to help the teams collaborate better? (Choose two)
A team is entering into a forming stage after kickoff, with project objectives identified and team members assigned with roles and responsibilities. However, during the team meetings, a team member does not agree on project documents and makes comments that could affect the performance of other team members.
What should the project manager do?
A project manager is assigned to a new project team that has several stakeholders who can have significant influence over the project outcomes.
The project manager categorized the stakeholders into four different groups and wants to define the communication strategy.
How should the project manager handle communication?
A company has decided to initiate a project to eliminate a sales channel that has been unprofitable for the past 3 years. Some members of the project team are pessimistic about the project.
What should the project manager do in this situation?
A prefeasibility study for a new renewable energy project is nearing approval. To ensure that the project time lines are maintained, activities associated with the feasibility study must continue while the prefeasibility study is being approved.
How should the project manager proceed?
In the planning phase of a software implementation project, two of the team members disagree on how to approach end-user training. The
discussion has intensified and the team members are not able to agree.
What should the project manager do next?
A project manager is closing a project and preparing to hand it over to the operations team. During handover, a delayed invoice was submitted with a higher-than-planned
cost against the project work. Consequently, project handover was delayed and the project's reported completion costs were increased.
What should the project manager have done to avoid this situation?
A project manager has been assigned to a hybrid project. The project manager needs to ensure all team members are collaborating and are aware of the project's ongoing changes.
What should the project manager do?
A medium-sized company has been exploring new marketing tactics with regard to launching a new product. New product creation is no small task. In the end, it was too big
of an expenditure for the company to undertake.
What should the project manager do in the future when working on new product projects?
A project manager is leading a hybrid project for the development of denial equipment with live team members A dentist, who is also one of the major investors attends a sprint review meeting and raises questions and doubt about the concept and expected performance of the equipment
What should the project manager do?
A major issue about conflicting priorities has been highlighted by the project team with regard to a few stakeholder requirements. What should the project manager do?
A company is engaged in a transformation journey, and the project manager for this endeavor is new to this project. During one of the project status update meetings, a key stakeholder, the project manager's functional manager, is dissatisfied with the work in progress, and points to the project manager.
What should the project manager do?
A project team member raised a risk that the threat of country-wide power cuts may affect the project time line for a software development project. In the last month, this risk
materialized and the project time line had to be extended by 2 months.
Which two actions should the project manager take? (Choose two)