Summer Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmas50

PMI PMP - Project Management Professional (PMBOK 7th Version)

Page: 4 / 14
Total 2196 questions

An information technology project manager works at an insurance company and is assigned to an infrastructure upgrade project. During the execution phase, a stakeholder approaches the project manager and informs them that a deliverable is not meeting the quality requirements.

What should the project manager do first?

A.

Acknowledge the stakeholder ' s concerns and work to correct the deliverable.

B.

Compare the stakeholder ' s assertion to the metrics in the quality report.

C.

Ask the project sponsor for additional funding for improved quality outcomes.

D.

Update the risk register with information on the noncompliant deliverable.

A project manager just completed a successful deployment and is preparing to transition the project to an operational state before starting closeout actions. What should the project manager do to ensure that the project is ready to move to an operational state?

A.

Meet with the project team to review the work breakdown structure (WBS) and confirm deliverables have been delivered.

B.

Develop a plan to repay the technical debt incurred during the project and ensure that the project sponsor agrees with the plan.

C.

Review the project approval requirements in the project charter and confirm who will be approving the project.

D.

Refer to the project’s work in progress (WIP) reports to ensure that there is no additional work in the backlog.

A primary stakeholder is unable to join the project status meetings consistently. The project manager has been communicating with this stakeholder informally and regularly

to ensure that the stakeholder is up to date on the project. However. the project manager has recently resigned and will not be meeting with the new project manager prior to

departure.

How should the project manager ensure that the new project manager continues to update this particular stakeholder?

A.

Update the communications management plan with specific information on stakeholder engagement.

B.

Update the stakeholder engagement plan with the specific communication needs for the stakeholder.

C.

Ensure that the project team has been provided guidance on the specific needs of this stakeholder.

D.

Ensure that the project documents contain specific instructions regarding the stakeholder.

A company has appointed a supplier to deliver software and has assigned an internal project manager. The supplier states that no technical development or testing is required from the customer. The project manager would like to confirm this with all of the stakeholders.

What should the internal project manager do first?

A.

Distribute the project plan to all of the interested parties.

B.

Host an alignment session with stakeholders to formalize the project requirements.

C.

Communicate to the supplier that customer testing is required.

D.

Develop a user acceptance testing plan to ensure the quality of the deliverables.

Due to contractual issues, a key team member cannot travel to the project location for a design review meeting.

What should the project manager do?

A.

Consider setting up a virtual meeting with the team for the design review.

B.

Ask the project sponsor if another team member can participate instead.

C.

Solve the contractual issues before continuing with the design review meeting.

D.

Inform the stakeholders and demand an immediate solution from the project sponsor.

An agile team is geographically separated across multiple continents, and the project manager is in the process of identifying the tools to manage the communication among the virtual teams. Drag the appropriate tool on the left to each project task on the right.

An agile team is in the early phases of the development cycle for a project; however, they have already begun to deliver functionality to the customer. The team has identified risks to the project and are working on developing the mitigation strategy.

What should the project manager do next?

A.

Incorporate and prioritize the risks in the risk register according to impact.

B.

Escalate the risk to the project sponsor and steering committee.

C.

Implement the risk mitigation strategy according to the highest impact.

D.

Determine if any of the new risks have any financial impact.

A protect team is working remotely on a solution The client wants the solution as soon as possible and is uncomfortable because the team members are not colocated In addition the client expressed concerns about the understanding of the project context and the team ' s decision-making process

What should the project manager do?

A.

Update the communications management plan to satisfy the client ' s request

B.

Request the client to attend the daily meetings with the project team

C.

Encourage the client to interact with the protect collaboration platform

D.

Ask the product owner to frequently communicate with the stakeholders

The project manager has finished all the tasks of the project and immediately starts on a new project. A few months after beginning the new project, the accounting manager asks for confirmation of previous projects because the budget is still open with no further cash flows.

What should the project manager have done?

A.

Conveyed task completion information to accounting

B.

Closed the procurement process properly

C.

Completed the transition process

D.

Performed administrative closure of the project

An agile project has just started, and the backlog is being prioritized. The

customer wants to prioritize business value over identified risks.

How should the customer’s request be managed?

A.

Accept risks as they decrease over a period of time.

B.

Create a risk value profile to track the relative importance of risks.

C.

Log and track risks separately as only business value is important.

D.

Assess risks together with business value during prioritization.

A project manager joins a startup and discovers that the chief technology officer (CTO) encourages the team to overlook some procedures in the interest of speed. What should the project manager do to ensure that all the procedures are followed in the future?

A.

Develop new procedures that are easy for the team to follow.

B.

Escalate the issue to the CEO and the board members.

C.

Instruct the team that the procedures should always be followed.

D.

Initiate a review of the procedures with the CTO and the team.

A sales learn working on an IT deployment project approached the project manager on several occasions and complained about nonpayment of their overtime pay The project manager realized that other team members are receiving their overtime pay

What should the project manager do next?

A.

Have a discussion with the sales team to find a solution to the issue

B.

Validate the reason and add it as an issue in the issue log

C.

Direct the sales team to speak with accounting to resolve the issue

D.

Escalate the issue to the functional manager

An established project team with a good track record has been working on a project for one year The project manager trusts the team and the work they produce. Which term describes the project manager ' s management approach?

A.

Laissez-faire

B.

Transactional

C.

Transformational

D.

Charismatic

An important project to build a new airport was suddenly stopped because of complaints from residents in the surrounding communities. The residents stated they were not consulted and that the project would cause ecological and pollution damage.

What should the project manager have done first to avoid this situation?

A.

Identified the stakeholders and their expectations

B.

Presented the project to the community

C.

Added this situation to the risk register

D.

Added these requests to the project scope statement

A project manager Is transitioning from a predictive We cycle project to a new agile project How should the project manager manage and control the scope for the new project?

A.

Create a scope baseline and put the rest as backlog activities.

B.

Estimate the work the team can complete and define story sizes to keep the project under control.

C.

Develop a plan to complete more work In less time.

D.

Spend a short amount of time defining the scope and building prototypes to refine the requirements.

According to the project contract the delivery date is approaching However one important material is still not on site The construction work will have to stop and wait for this special material, delaying the project.

What should the project manager do?

A.

Record it in the risk register

B.

Ask the client to help solve the problem

C.

Start procuring this material from another supplier.

D.

Engage the project team to look for alternatives to find a solution

A project manager prepared the base budget model to deliver a highly

customizable software solution. The solution will be delivered in multiple countries with

significantly different cultures and will be staged over phases.

What should the project manager do next?

A.

Review the base model with the team leaders in each country to establish anindependent budget for each phase.

B.

Overestimate costs and underestimate revenues to include the impacts of differentcultural elements.

C.

Apply the company ' s operational budgeting model.

D.

Ask the project management office (PMO) to review the draft budget.

A project manager has noticed that the performance of a new team member has increased dramatically over the past few months The project manager has been measuring this team member ' s performance through the cost performance index (CPl) and schedule performance index (SPl) of work packages. The project manager has also assigned new. unrelated work packages to this team member The project manager wants to formally record the team member ' s success in the project documentation

What should the project manager do?

A.

Attach a note to the project management plan about the team member

B.

Hold a project team meeting about the team member ' s contribution and take minutes

C.

Record the team member ' s contribution in the responsibility assignment matrix (RAM)

D.

Send a communication to management recognizing the team member ' s contributions

A project manager scheduled a session to identify risks on the current project. Most of the stakeholders did not attend the meeting, although they previously confirmed their attendance.

How should the project manager proceed in order to complete the risk register?

A.

Cancel the meeting and create the risk register using the project documents.

B.

Continue the meeting and send the updated risk register to all stakeholders.

C.

Run the meeting and follow up with each one of the absent stakeholders to get their input.

D.

Escalate the issue of stakeholders not attending the meeting to the project sponsor.

An intern is replacing a critical resource midway through a sprint To help the intern get up to speed, the project manager assigns a senior engineer in the team as the intern ' s mentor Two months later, the project goes into critical status, delaying the release milestone by a month.

What should the project manager have done to avoid this scenario?

A.

Convinced the critical resource to remain on the project.

B.

Requested an experienced resource as a replacement

C.

Allocated additional time for mentoring

D.

Negotiated additional time to complete the project

At the end of a project, the project manager is asked to submit project documentation for an internal audit in response to regulatory requirements. What should the project manager have done at the beginning of the project to ensure that project documentation would

fulfill these requirements?

A.

Conducted a document review

B.

Confirmed documentation requirements with stakeholders

C.

Updated the project templates

D.

Implemented a new change control policy

A project manager is hired by a global company. The project manager is an agile specialist and is tasked with supporting the project team to reduce rework and dissatisfaction.

How should the project manager address these objectives?

A.

Decrease the scope of the portfolio and send new solutions to the customer.

B.

Deliver a schedule with the portfolio timeline and delivery to the customer.

C.

Adopt an incremental cycle of delivering value to the customer.

D.

Prepare deliveries with more details to satisfy the customer.

A global company hired a project manager for a new implementation at all of its sites After reviewing the business case and project charter, the project manager notes that the project team has different locations and regions to consider.

What should the project manager do to address this situation?

A.

Inform the steering committee of the situation and request additional resources.

B.

Coordinate virtual and face-to-face meetings at each site to improve communication

C.

Coordinate virtual meetings to assess the project team ' s communication needs

D.

Inform the project sponsor of this situation and request cultural orientation training.

A project manager has just taken over a project that is halfway through its schedule. In a brief meeting with the client’s key project team, the project manager receives several requests from a specific client team member who was not at the project team meeting. The requests for information seem to be for trivial information that was previously submitted in project documents.

What should the project manager do first?

A.

Send an email to the client team member explaining that they have the information already.

B.

Review the stakeholder register to gain insight into the expectations of that team member.

C.

Inform the client project manager that they are sending too many trivial requests.

D.

Update the project risk register to include potential delays in answering these requests.

An agile team is working on a product deliverable in an organization that is transforming itself to quickly respond to change. The finance

team is requesting a project budget for the new product.

What should the team do to address this request?

A.

Work with the finance team to transition to incremental budgeting.

B.

Request the finance team to allocate a budget based on historical data.

C.

Provide the budget to the finance team for only the planned increments.

D.

Extrapolate the budget based on the current cost performance index (CPI).

In the past, the project manager and the project team performed well using

predictive methodology. However, the organization recently decided to adopt agile

approaches, and the project sponsor wants to use an agile approach in an upcoming project.

Before initiating the project, what should the project manager do?

A.

Prepare a risk report that captures the probability and impact of risks, and then shareit with the project sponsor.

B.

Share the organization ' s decision with the team and make plans to adopt an agileapproach in the upcoming project.

C.

Make a request to human resources for new team members who have agileexperience.

D.

Ask the project sponsor to change the approach back to predictive as that is theteam’s strength.

A project manager is working on a major construction project. Part of the

agreed-upon plan was to use a cloud-based system with a server that runs on high-speed

internet service since most of the team members work virtually. The company needs to

reduce operating costs as much as possible and management insists that the project will

now use a system running on a conventional dial-up service.

What should the project manager do next?

A.

Evaluate the impact of this decision and communicate with management.

B.

Agree with management and continue working the project management plan.

C.

Meet with management about their decision and ask them to get another project manager.

D.

Replace some of the team members that work virtually to help the company save money.

A project manager is leading a virtual team that is geographically dispersed. What

should the project manager do to avoid uncertainty in the project due to different cultures?

A.

Start the project and add any uncertainty that arises to the risk register.

B.

Dissolve the virtual team and build a colocated team.

C.

Gather relevant cultural data and engage members in discussions covering their work ethics.

D.

Build a culturally neutral team that will not be affected by cultural differences.

A new team member inquires about how much they need to learn about the organizational process assets (OPAs) residing on the company intranet. Another team member states they only need to know the basics. However, the project manager believes the team member should know everything regarding the OPAs.

What should the project manager do?

A.

Create a training schedule for the new team member to follow over the next few weeks.

B.

Escalate the inquiry to the team member ' s functional manager.

C.

Clarify the relevance of reviewing the documentation on the intranet.

D.

Ask a senior team member to help the new team member navigate through all the documentation.

A project team ' s performance has declined for the last three iterations Some of the team members are disappointed, and raise their concerns during the retrospective meeting What should the project manager do?

A.

Focus on remediation not merely on correcting symptoms

B.

Compare the team ' s performance against other project teams

C.

Identify potential failure points based on the iteration workload

D.

Motivate the team to perform better

A project learn member identified a defect in the initial solution design for a project The stakeholders are not sure whether to deploy the system or not. What should the project manager do?

A.

Propose a solution redesign for the project

B.

Perform risk analysis against the issue.

C.

Revise the project ' s quality control measurements

D.

Develop a mitigation based on the solution design

A product owner has provided the team with a prioritized backlog for the initial

launch of a new product. After analysis, the team concludes that some work is missing to

support the initial launch and provides this information to the product owner. The product

owner acknowledges the missing work and adds it to the bottom of the backlog. The team is

not happy with the prioritization that the missing work received.

What should the project manager do in this situation?

A.

Let the project team pull the recommended work from the bottom of the backlog tomaximize value creation.

B.

Analyze and reprioritize the backlog and provide the decision to the product ownerand team.

C.

Recommend the product owner prioritize the missing work higher because it isneeded for the minimum viable product (MVP).

D.

Empower the product owner by supporting the decision and instructing the team to follow the prioritization as provided.

When trying to track project benefits, a project manager realizes that some key performance indicators (KPIs) are not yet defined. What should the project manager do?

A.

Work with the business analysts to track and collect the missing data and build the KPIs.

B.

Coordinate with the benefit owner to track and collect the missing data and build the KPIs.

C.

Forward the issue to the benefit owner and ask them to collect the missing data and build the KPIs.

D.

Ask the program manager to track and collect the missing data and work to build the KPIs.

A major project is unable to access the US$12 million funding allocated for the project. This prevents the start of the procurement process and is already leading to costly delays.

What should the project manager do?

A.

Escalate to the project steering committee.

B.

Invite the finance department to the next project demo.

C.

Review the project requirements.

D.

Use the currently available resources.

A project team member complained to the project manager that they are not sure f on the latest requirements document because it was emailed to them about one week ago. They mentioned that, in the past they worked on a document tor more than 20 hours only to find out later that another team member had already updated that same document but did not send them the latest revisions.

What should the project manager do to avoid this situation in the future?

A.

Encourage better team communication by positioning team members closer together.

B.

Implement a project management information system (PMIS)

C.

Update the communications management plan to ensure correct delivery of the latest version

D.

Restrict team members from sending the requirements documents via email

An agile project is starting and the assigned team is new to agile During the first daily meetings, the project manager observes that the team is having problems meeting goals What should the project manager do?

A.

Plan an outdoor activity tor the team to get to know each other

B.

Ask the team to review agile protect management approaches.

C.

Ask the human resources department for an experienced agile team

D.

Conduct a meeting to help the team define the team charter

A project manager has just been assigned to a team that is developing a new design product. The work breakdown structure (VW/BS) has been created and the activities have been assigned to the team members. The project manager finds that there are activities that could be completed sooner by other team members. If the current assignments are left as is, the project could be delayed 2 weeks.

What should the project manager do in this situation?

A.

Review the work allocation and reassign some tasks to shorten the critical path.

B.

Maintain the task assignments as planned and compress the other tasks to keep the project on schedule.

C.

Ask the team members to work overtime to finish the tasks on time according to the schedule.

D.

Keep the task assignments unchanged since the project management plan has been approved.

A project manager is tasked with managing a customer relationship management (CRM) implementation project. The project charter is approved, and the project is now in the planning phase. The project manager meets with the stakeholders several times to gather the initial requirements. However, each time they meet, the stakeholders provide additional information that is different from what they provided earlier. The stakeholders are becoming frustrated, and the sponsor is now unresponsive.

What should the project manager have done to avoid this situation?

A.

Initiated requirements planning to analyze, document, and manage requirements

B.

Applied requirements elicitation to involve engaging stakeholders consistently in the requirements process

C.

Implemented the change request process to harness change to the stakeholders’ advantage

D.

Used progressive elaboration to enhance the scope management plan with additional details

Drag the technical practices on the left to the scenario on the right.

In a construction project for a new building, the project manager decides to apply agile principles for the building foundation phase While evaluating the project schedule with the team, the project manager believes that the estimates are inaccurate. How should the project manager address this issue?

A.

Create a product backlog

B.

Perform sprint reviews with the team

C.

Assess the previous project velocity

D.

Reduce the story size by splitting stories

A project is being initiated, and almost every resource available on the project team is a recent university graduate. What should the project manager do to ensure their engagement with the project?

A.

Provide clear direction on the work to be done and its alignment to the major objectives of the organization, using technology to communicate.

B.

Establish a clear hierarchical environment and allow them to navigate through the project faster using social networks.

C.

Foster proactive decision making and develop a hierarchy to approve decisions based on different levels of complexity.

D.

Create an environment that encourages leadership, translates ambitions into growth opportunities, and rewards overtime workers.

A project manager is managing a project that is halfway through its execution phase and the quality standards of the deliverables were formally accepted However, a government agency has recently Introduced new standards that may significantly impact the project The deliverables must be changed to align with the new quality standards

What should the project manager do?

A.

Set up a structured, independent processes to determine if project activities followed the standards.

B.

Schedule training for the project team on the new regulations introduced by the government agency

C.

Evaluate the impact the new regulations will have on the project and submit a change request

D.

Update the lessons learned register and inform senior management of the new standards

The project manager has recently received funding approval for a training program

for the entire project team but has not yet defined the most effective training course. One

team member submitted a request for specialized training that is required for the project.

How should the project manager handle this request?

A.

Send this change request to the change control board (CCB) for approval.

B.

Approve the request for the specialized training.

C.

Reject the request as it does not impact the project deliverables.

D.

Validate if the training is within scope and budget.

A project leader of an agile team realizes that one team member is unmotivated, which is affecting the whole team. What should the project leader do to improve the situation?

A.

Invest in developing the team ' s emotional intelligence.

B.

Ask the unmotivated team member to take a short leave.

C.

Reduce the number of daily and retrospective meetings.

D.

Send the unmotivated team member to another team.

In a functional organization, a product analyst is assigned to a short-duration application development effort The analyst expresses concerns about the task and asks the project manager to provide the support of a peer with expertise in this domain

What should the project manager do?

A.

Make sure the analyst has regular pairing meetings with the other team member throughout task execution

B.

Ask the analyst to use skills to develop the tool, then move development to another team member

C.

Enroll the analyst in a capacity-building program and keep this analyst assigned to the task

D.

Recognize the analyst ' s concerns and reassign the task to another team member

An agile team has completed an iteration and delivered the agreed features to the customer. In a surprise to the team, the features are not accepted by the customer. The project team conducts a root cause analysis.

What should the project manager do to avoid this situation in the future?

A.

Ensure that customer requirements do not change from the start of the project.

B.

Ensure that the definition of done (DoD) is well defined and complete for future iterations.

C.

Ensure that the development and quality assurance team members implement the feature correctly.

D.

Ensure that the team facilitator allocates tasks correctly to team members.

In a weak matrix environment, two key team members are falling behind with their tasks, which will affect the success of the project.

Further investigation by the project manager reveals that they have unresolved issues with each other. The project manager asks them to find a way to resolve the issues, but this is unsuccessful. The project manager then holds a meeting with them to work outa permanent solution to the issues, but this is also unsuccessful.

What should the project manager do next?

A.

Escalate the issue to a higher authority.

B.

Suspend the two key team members immediately.

C.

Put the issue on the agenda for the next team meeting.

D.

Reassign one of the key team members to a different task.

A self-organizing team was delivering as committed. The team accepted a development task with new technology and the iterations started to have reduced velocity. What management decision is suited for this situation?

A.

Provide opportunity for team members to learn and adjust to the technology.

B.

Move team members who are not performing from the team.

C.

Add new members to the team and increase the velocity

D.

Re-assign the project to a team that has worked with this technology

A project manager is leading a new agile project. The requirements for the first sprint have been defined and the work is about to start.

What should the project manager do next?

A.

Assign the tasks to the resources based on their expertise.

B.

Ensure that the priority of each task is clear to the team.

C.

Ask the team to self-organize and manage the work assigned.

D.

Tell the team which task to focus on at the next daily standup.

A project manager decided to incorporate the latest technological advancement with the client ' s devices at no additional cost to the project.

Upon completion and submission of the project deliverables, the client rejected the devices, despite having the latest features.

What should the project manager have done?

A.

Incorporated the change within the scope of the project

B.

Reviewed the quality inspections

C.

Complied with the customer specifications

D.

Documented the technical reviews with the new change