Halloween Sale Special - 75% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: newyear

PMI PMP - Project Management Professional (PMP) July 2026 Update

Page: 5 / 6
Total 187 questions

A project team is in the process of selecting a module for the upcoming iteration. They have identified three potential modules as candidates. Despite several rounds

of review, the team remains undecided on which module to select.

What should the project manager do?

A.

Aska colleague to select the module and inform the team of their decision.

B.

Evaluate the options with the team and assess the workable option based on consensus.

C.

Select the simplest module to develop since complex ones will require more iterations.

D.

Select the most appropriate module to be placed in next iteration.

During the planning phase of a project, the local project team presents a task to the project manager. This task will require several months to complete, and the

duration will affect the expected timeline.

What should the project manager do first?

A.

Communicate to stakeholders the updated schedule after considering how long each task will take.

B.

Add more resources during the task execution phase to complete the project on time.

C.

Meet with the project team to assess the task and any possible improvement to reduce its duration.

D.

Procure services to execute the task so the local project team can progress with other project activities.

During a daily coordination meeting, the team reports that due to considerable challenges with the infrastructure, the planned tasks are now blocked and cannot move

forward. What should the project manager do?

A.

Ask the product owner to suggest issue resolution.

B.

Escalate the issue and its impact to the project sponsor.

C.

Determine and apply a suitable strategy to remove or minimize the issues.

D.

Ask the team members to explore trainings while waiting for issue resolution.

The project manager could not get the estimated initial budget for an infrastructure project, leaving the team uncertain about which part of the project should be

‘started. What should the project manager do?

A.

Use the budget defined by the organization and proceed according to the scope.

B.

Ask the sponsor if the project can be started without the budget defined.

C.

Start the work immediately with the given budget.

D.

Calculate a detailed budget to determine a solution.

During the execution of an Al project, the different teams responsible for developing deliverables are consistently delayed. The teams do not have access to shared

resources or are dependent on other teams to complete tasks.

What should the project manager do first?

A.

Use project management tools to identify bottlenecks.

B.

Update communication processes to avoid roadblocks.

C.

Meet with the teams involved to identify the root cause.

D.

Meet with the team to prioritize goals to avoid impediments.

A logistics project is anticipating significant delays in the next few months. The project manager makes a list of the causes of the delays before thinking about how to minimize them.

How should the project manager prioritize which delays to take action on? (Select each box from the Items list and drag and drop it into either the Risk Register or Issue Log box.)

A project manager is engaged in a process improvement project. The business analyst working with the team has been instructed to interact with line production team

members in an efficient manner. Since process duplication would affect their reaction time, line production team members have a significant interest in process

improvement to improve quality.

How should the project manager advise the business analyst to improve interaction with the line production team?

A.

Consult a subject matter expert (SME) who can provide insight into the major gaps that frequently impact line production operations.

B.

Reference the lessons learned of the line production that were used for the process improvements for the last 10 company projects.

C.

Conduct workshops for the line production team members so they actively contribute to the design of process improvements.

D.

Distribute a survey to those who have worked with line production team members in the last 2 months and ask for their recommendations.

Health Records Modernization at Hospital Case Study

A project manager led a health records modernization project at a hospital with a project budget of $US5 million and an 18-month timeline. The project involved multiple stakeholder groups including medical, administrative, and IT staff; board members; patients; insurance companies; external vendors; regulatory bodies; and union representatives.

Stakeholder management was complex and a major undertaking for the project manager, but it was critical to achieve a positive project outcome. When the project started, the project manager conducted stakeholder analysis, using the information to create both a power/interest and an influence/impact matrix. The analysis showed that while the hospital board members and regulatory bodies had high power but moderate interest, the medical staff (doctors and nurses) had both high influence and high impact on the project. Administrative staff showed high interest but lower power, while patients and insurance companies had moderate interest and varying levels of influence. Based on the analysis, the project manager created a stakeholder engagement strategy that documented expectations, communication preferences, and influence levels in a stakeholder register. The project manager also made a RACI (responsible, accountable, consulted, informed) chart to show roles and responsibilities; and created communication channels and frequency for each stakeholder group, an issue escalation system, and a feedback system for continuous stakeholder input.

To execute the modernization process of health records, the project manager realized that medical staff members would need to change their daily workflows. To facilitate change management for these stakeholders, the project manager created a clinical advisory committee, appointed department-specific “champions,” created focus groups for requirements gathering, started a training program, and developed key performance indicators (KPIs) to measure satisfaction.

During project execution, several challenges emerged. The doctors expressed concerns about the system’s impact on patient care, the nurses’ union raised workload concerns, the IT department faced resource constraints, the insurance companies requested additional features, and the administrative staff worried about data security. The project manager responded to these challenges by increasing the frequency of stakeholder meetings, implementing a change management program, creating a beta system for stakeholder testing, developing contingency plans for various stakeholder scenarios, and establishing an issue resolution process.

Despite these mitigation efforts, the medical staff required additional training, leading to a change request for a 2-month extension and a 10% budget increase. The board of directors approved this to help ensure high adoption and satisfaction rates among staff members. The project helped establish new good practices in future programs for stakeholder management in the organization’s project management office (PMO). The documented lessons learned became a reference for future projects of similar scope and complexity.

How should the project manager handle the IT department’s resource constraints while at the same time maintaining project momentum?

(Refer to the Health Records Modernization at Hospital Case Study exhibit.)

A.

Add the requested features to the system to address the resource requests.

B.

Proceed with the implementation, document the situation, and notify the board.

C.

Conduct a requirements analysis and then implement the essential features.

D.

Assess the impact, reprioritize tasks, and present resource options to the board.

An agile project manager is responsible for keeping the project vision updated and in line with the business stakeholders’ goals to continue creating value for the

project. How should the project manager achieve this?

A.

Use the Scrum of Scrums (SoS) meeting to discuss project goals with the product owners and scrum masters.

B.

Include relevant stakeholders in the retrospectives to discuss the progress and achievements of the project.

C.

Discuss the project goals with relevant stakeholders at review meetings to maintain a common perspective.

D.

Use the sprint planning meetings to align with product owners on the backlog of the project streams.

A project manager is leading an ongoing project for a highly reputable international client. A few hours before the final review meeting, during which the client is expected to accept the project and authorize a substantial payment, the project manager’s company suffers a cyberattack. The client is very strict and maintains that any missed deadlines will result in a considerable penalty.

What should the project manager do?

A.

Call an internal meeting with senior leadership to define the next actions.

B.

Follow the business continuity strategy to keep the project in operation.

C.

Find an alternative communication platform on which to conduct the review meeting.

D.

Consult the client to determine potential courses of action.