PMI PMP - Project Management Professional (2025 Version)
An agile team has completed 9 out of 10 stones tor the sprint. During the retrospective a few team members pointed out that they finished a of their stories However one team member tailed to finish a story
What should the agile leader do1?
A project manager is implementing an enterprise-wide software project The project has a great business impact and is fully supported by senior management However, the project manager is facing difficulties gelling the support of several key departments.
What should the project manager do?
A new solution is being deployed in countries A B and C. This solution will allow the countries to propose new services to their customers Country A has asked for a change in the solution m order to comply with its own customer market
What should the project manager in charge of the deployment in country A do?
A servant leader is about to start a confidential agile research project. A high risk has been identified related to a team member disclosing details of the project with external people.
What should the servant leader do to address this risk?
One phase of a project took much longer than initially anticipated The key stakeholders expressed their concern regarding a potential project delay. What should the project manager do?
A project manager wants to make sure that similar projects in the future use the project's performance data as a reference. However, the project manager is not sure how to accomplish this.
What should the project manager do?
A predictive project team come across a scenario where they need to use some agile tools and methods. However, they did not feel this was appropriate since their organizational project management processes did not mention this.
What should the project manager do in this scenario?
An agile project team is tasked with a new project After multiple discussions with me customer it appears that there is a lack of clarity on the requirements which resulted in delays in the architecture and design phase
What should the team do next?
A company strictly uses an agile approach, and the backlogs are continuously updated. A new project lead is hired and feels uncomfortable sharing some of the product's vital information with the team and the product owner.
What does the project lead need to do to prevent a risky situation in the next iterations?
A company has undertaken a large transformation project using agile practices. The project sponsor has asked the project manager to promote the new values identified in the intended transformation to the project team
What should the project manager do?
A project manager is working on a software product that will be installed across all levels of the client's organization. The client's executive sponsor insists that only stakeholders at the highest level of the company will be involved in the planning phase.
What should the project manager do?
A procurement team lead has been reported as getting into conflicts with other project team members on a weekly basis, The project manager engages with the team lead and discovers that other team members do not believe the team lead is right for this position.
What should the project manager do to resolve these recurring conflicts between the team lead and the other team members?
Due to a tight schedule, a project team member suggests skipping the quality check of a minor deliverable. What should the project manager do?
An agile team completes a deliverable that is to be certified by another expert team The second team does not take the deliverable for many months What should the servant leader do?
In the middle of an iteration, the product owner tells the agile team that the
government has updated legal requirements. This will result in some changes in the product
definition.
How should the project manager handle this situation?
A complex project is m its execution phase. The project is set up to produce both predictive and incremental deliverables. The agile team is running late on their tasks There is a resource on the agile team who is responsible for producing progress reports for the project manager This resource has the required skills to help other team members with their workload
What should the project manager do to optimize the time of the resource who produces the progress reports?
A project manager is about to start a large-scale project with unclear requirements, a fixed deadline, and a fixed budget. The client is unable to provide a product owner, as they do not have enough capacity and they want to be involved only a few times during the project.
How should the project manager plan and manage the project?
A sales learn working on an IT deployment project approached the project manager on several occasions and complained about nonpayment of their overtime pay The project manager realized that other team members are receiving their overtime pay
What should the project manager do next?
A key challenge that a project manager is facing is the lack of discipline by various team members and their inability to harness energy to achieve the project objectives. What should the project manager do to overcome this challenge?
A key stakeholder has recently started in a company and has been assigned to a hybrid project. Although very experienced in their domain, the stakeholder has only been exposed to predictive project approaches.
What should the project manager do?
A project manager at a plant with continuous operations needs to deliver a project urgently to meet a market opportunity. What should the project manager do to meet the time-to-market need?
A project is coming to a close, and the experienced project team members will be moving on to the next project. Who is responsible for ensuring that the appropriate knowledge transfer is done prior to project closure?
An agile project is in its early iterations, but the project manager already realizes that
more resources will be needed to achieve the expected time lines. There are no internal
resources. available.
What vendor strategy should the project manager use to maximize project delivery?
A project manager received the project charter for a new product. The project is expected to have two main deliveries: the hardware part that has detailed specifications already defined, including a sample machine, and the user interface software that has only a basic specification and a
requirement for a user experience design approach.
Which project management approach should the project manager use?
A project manager is involved with a project to remodel a long-used product. There are no proper records for the original design and execution of the original product. The stakeholders doubt that the remodel can be accomplished without this information and are hesitant to provide support for the project.
What should the project manager do?
A company is transitioning their projects to utilize hybrid project management approaches While putting together their project team, the project manager discovers the requirements from the customer are unclear and also realizes that the team members are lacking critical technical stalls needed for project success. However the customer will not accept any changes to the requirements
What should the project manager do to resolve this issue?
A project manager became aware of misunderstandings between a key stakeholder
and a team member with regard to some of the features defined in the project scope. What
should the project manager do?
An agile team recently started working on a project for a financial institution. The
project sponsor is concerned that an agile approach will not provide enough support for the
organization's compliance standards.
In order to mitigate this risk and avoid problems, what should the project manager do?
A bank has decided to initiate a project to transition from serving small businesses and entrepreneurs to mid- and large-scale businesses The country's economy is struggling, and some stakeholders cannot agree on this transformation need
What should the project manager do'?
A project manager is managing an internal software development project that is on schedule to complete in 1 month. The project should begin seeing value once the system is online,
yet some stakeholders lack an understanding of how it will provide value to the organization.
What should the project manager do next?
A technical lead has complained to the project manager about a team member's performance. The team member has repeatedly missed tasks that have put sprint commitments at, What should the project manager do?
A company is transitioning its projects from a predictive to an iterative approach. The protect team is complaining because they are unsure of what needs to be done due to all of the changes requested by the product owner for features already developed since the beginning of the project.
How should the project manager handle this situation?
A project requires the installation of a call center to support operations. It is estimated that the call center will need 100 people working on
weekdays from 8:00 a.m. to 5:00 p.m. and weekends from 8:00 a.m. to 12:00 p.m.
What should the project manager do?
One of the risks identified during project planning activities is related to a component from a preferred vendor. The component utilizes new technology, and there is a possibility of incompatibility with other parts of the system that are being developed.
What should the project manager do?
One deliverable for a project is to translate and print materials for students every 2 weeks Printing services are available but without guaranteed time lines because other projects make a significantly higher profit and have a higher priority
What should the project manager do to mitigate the risk of not having the materials printed on time?
A project manager was recently assigned to a new project that is about to start. The
organization has already signed a fixed-cost contract with the customer detailing the scope and final delivery date, but the project manager has identified several internal constraints and conditions that will certainly prevent the project from being completed in the number of iterations initially planned.
What should the project manager do next?
A new project manager has been assigned to a project that is in its second phase The product created in the first phase was transferred to operations During a meeting, the project sponsor complained that some of the reports contain conflicting data on the product value
What should the new project manager do next?
A project manager is leading a project with a predictive approach for a governmental body with strictly defined requirements. In the middle of the project, the sponsor requires a significant new feature to be included. This feature was not in the original plan, nor was it part of the planning process,
What should the project manager do?
A project is delayed. The project manager added extra resources to some activities and approved overtime for several team members.
What technique is the project manager applying?
During project execution for an innovative product, a project team has been working hard to meet the deadlines. However, one of the team members will be leaving in 3 weeks and will be replaced with a new team member.
How should the team share tacit knowledge?
A project learn member is having difficulty delivering assigned tasks for a project that is at risk of being delayed. The main issue is that the team member does not understand a new system that was recently implemented.
What should the project manager do?
A lead project manager for an agile project needs to prioritize requirements define the scope of the initial product and deliver the approved scope in a series of multiple versions. What should the project manager do next?
What is the correct way to put an organization on the proper path to changing their mindset to an agile approach?
A project has issues arising where the data integration team and the data migration team have areas that overlap It is not clear who would be responsible for delivery on these areas What should the project manager do next?
A project manager is leading a project that involves on-site and remote team members One task that was assigned to a team member in another country appears to be behind schedule When the project manager inquires about this, the team member claims that the task was completed and that this was reported to the team lead via a telephone conversation
What should the project manager do?
During a kick-off meeting at the start of project execution, the vendor presents a
migration plan to client stakeholders. The director of the business unit that owns the solution being migrated demands the ability to make the final go/no-go decision about whether the systems go live.
What should the project manager do?
A project manager Is leading an agile software development project with strict deadlines The client complained that the last deployment did not meet the acceptance criteria The development team lead is arguing that the deployment met all specifications and has provided evidence of the client's specifications
What should the project manager do?
A new product is designed for a certain market. This product needs to adhere to the health and safety regulations for that region. What should the project manager do to ensure that the product complies with the regulations?
A healthcare company requires all new employees to attend mandatory computer-based training courses, Because some of the employees work with highly sensitive patient data, the training covers various aspects of data security. In spite of this training, data breaches continue to occur in
one of the project teams.
What should the project manager do?
An operations manager continuously raises concerns about a project's benefits to the company While some concerns are valid most of the time these concerns have caused delays in project meetings
How should the project manager handle this'?