PRINCE2 PRINCE2-7-Practitioner - PRINCE2 Project Management Practitioner (Version 7)
During stage 3, several BuildyBrick subcontractors are working on different work packages. The project manager is concerned that lessons identified by one team will not reach the others and could lead to rework, delay or additional cost. The project manager therefore holds a fortnightly cross-team ‘lunch and learn’ session.
Is this an appropriate application of the ‘learn from experience’ principle, and why?
Before the end of stage 2, the project board authorizes a change that adds more trees and seating to the external landscaping. The change can be delivered in stage 3 without any forecast breach of project tolerance. While preparing the next stage plan, the project manager incorporates the additional products and work, updates the relevant product descriptions and product register entries, and reviews whether the project initiation documentation needs to be updated.
Is this an appropriate application of ‘prepare the next stage plan’, and why?
While the project mandate is being prepared, the Mayor asks the LOB Portfolio Director, acting at the business layer, to select and appoint a suitable project executive for LouisShopping.
Is this an appropriate application of the organization practice, and why?
PROCESSES
During the ‘starting up a project’ process, the Head of the Portfolio Office explains to the prospective project executive that LouisShopping is strategically important to the LOB portfolio, must support increased business opportunities and is expected to open by the end of financial year three.
During which activity should this clarification of the mandate and business expectations take place?
During the ‘initiating a project’ process, the team expects local heritage-protection groups to oppose the proposal. The Heritage Director suggests waiting until the groups contact the project. Instead, the project manager asks the Heritage Manager to identify groups known from previous work, and the manager supplies a list.
Is this an appropriate approach to leading successful change, and why?
During stage 2, the design team is developing measures to minimize disruption to residents and local businesses. To build a relationship with this large external stakeholder group, the Sustainability Manager arranges a monthly newspaper article explaining the measures and inviting feedback.
Which PRINCE2 Project Management principle is MOST directly demonstrated, and why?