PRINCE2 PRINCE2-7-Practitioner - PRINCE2 Project Management Practitioner (Version 7)
At the end of the initiation stage, the Regeneration Manager submits the project plan and business case for review. The Portfolio Director releases funding for both stages 2 and 3 and instructs the project manager to provide only a progress report at the end of stage 2, without a project board decision before stage 3 begins.
Is this an appropriate application of the ‘manage by stages’ principle, and why?
The Chief Technology Officer is an influential stakeholder who strongly supports several unproven technologies for the shopping centre. Concerned about delivery risk and reputation, the project executive asks the project manager to limit the CTO’s contact with the project team and other stakeholders.
Is this an appropriate approach to leading successful change, and why?
During initiation, the project team holds a product-based planning workshop to break the site-preparation and foundation products into greater detail. The analysis identifies the need for a more comprehensive and costly environmental impact assessment because of Louistown’s ‘green town’ status.
During which ‘initiating a project’ activity should this workshop take place?
Near the end of stage 2, the supplier planned for the utilities and systems work becomes financially unstable and a replacement subcontractor is selected for stage 3. The project manager recommends that the replacement subcontractor’s account manager should represent the supplier interest as senior supplier.
During which ‘managing a stage boundary’ activity should this recommendation be developed?
During initiation, the project executive asks the project manager to evaluate a credible business option that omits the underground car park. The project manager includes an investment appraisal of that option in the full business case, despite the main contractor’s objection.
Is this an appropriate application of the business case practice, and why?
During the ‘starting up a project’ process, the project team decides that the complex LouisShopping infrastructure project will use a traditional, linear-sequential delivery method.
Which role is accountable for selecting the project approach?
At the stage 2 boundary, the project manager recommends adding the replacement subcontractor’s account manager to the project board to represent supplier interests during stage 3.
Which practice is being applied in ‘managing a stage boundary’?
While preparing the project plan, the project manager and BuildyBrick’s planning specialist use the product flow and data from previous projects to determine that the utilities and systems can be delivered in parallel as separate work packages.
Is this an appropriate application of the ‘plans’ practice, and why?
The City Council asks the portfolio office, independently of the LouisShopping project team, to provide confidence that the design and build will preserve the historic setting while incorporating the required technology.
Is this an appropriate application of the quality practice, and why?
In stage 4, the Heritage Director delegates a review of the inspection arrangements to the Heritage Manager. The Heritage Manager will work with the BuildyBrick CEO and the project manager, then report whether the planned inspections will provide adequate assurance about impacts on historic buildings.
Is this an appropriate application of the ‘define roles, responsibilities and relationships’ principle, and why?
