Total 56 questions

At the end of the initiation stage, the Regeneration Manager submits the project plan and business case for review. The Portfolio Director releases funding for both stages 2 and 3 and instructs the project manager to provide only a progress report at the end of stage 2, without a project board decision before stage 3 begins.

Is this an appropriate application of the ‘manage by stages’ principle, and why?

A.

Yes, because the project manager is authorized to manage the project on a day-to-day basis within set tolerances throughout each stage, without requiring additional project board decisions

B.

Yes, because the Portfolio Director, as the commissioning authority, has the right to determine the reporting frequency and format that best suit portfolio-level oversight

C.

No, because it is the City Council, rather than the Portfolio Director, that should hold the authority to commit funding across multiple stages of the project

D.

No, because the project board must review the continued viability of the business case and authorize the next stage at each stage boundary, rather than approving multiple stages in advance

The Chief Technology Officer is an influential stakeholder who strongly supports several unproven technologies for the shopping centre. Concerned about delivery risk and reputation, the project executive asks the project manager to limit the CTO’s contact with the project team and other stakeholders.

Is this an appropriate approach to leading successful change, and why?

A.

Yes, because restricting the CTO’s involvement would protect the project’s reputation from untested proposals

B.

Yes, because influential stakeholders should be excluded when their preferred solutions create delivery uncertainty

C.

No, because the project manager should record the technological concerns only as risks requiring formal responses

D.

No, because the CTO should remain engaged so that their influence can support adoption across the organizational ecosystem

During initiation, the project team holds a product-based planning workshop to break the site-preparation and foundation products into greater detail. The analysis identifies the need for a more comprehensive and costly environmental impact assessment because of Louistown’s ‘green town’ status.

During which ‘initiating a project’ activity should this workshop take place?

A.

Agree the tailoring requirements

B.

Agree the management approaches

C.

Prepare the project plan

D.

Prepare the full business case

Near the end of stage 2, the supplier planned for the utilities and systems work becomes financially unstable and a replacement subcontractor is selected for stage 3. The project manager recommends that the replacement subcontractor’s account manager should represent the supplier interest as senior supplier.

During which ‘managing a stage boundary’ activity should this recommendation be developed?

A.

Update the project plan

B.

Prepare the next stage plan

C.

Evaluate the stage

D.

Request the next stage

During initiation, the project executive asks the project manager to evaluate a credible business option that omits the underground car park. The project manager includes an investment appraisal of that option in the full business case, despite the main contractor’s objection.

Is this an appropriate application of the business case practice, and why?

A.

Yes, because developing the business case includes comparing credible business options to select the most appropriate investment

B.

Yes, because customer and supplier organizations must always maintain completely separate project business cases regardless of the given investment

C.

No, because a requirement in the initial scope may never be tested as part of an alternative option

D.

No, because anticipated parking income means that no alternative should be assessed

During the ‘starting up a project’ process, the project team decides that the complex LouisShopping infrastructure project will use a traditional, linear-sequential delivery method.

Which role is accountable for selecting the project approach?

A.

Business layer

B.

Project executive

C.

Project manager

D.

Senior supplier

At the stage 2 boundary, the project manager recommends adding the replacement subcontractor’s account manager to the project board to represent supplier interests during stage 3.

Which practice is being applied in ‘managing a stage boundary’?

A.

Plans

B.

Organization

C.

Quality

D.

Progress

While preparing the project plan, the project manager and BuildyBrick’s planning specialist use the product flow and data from previous projects to determine that the utilities and systems can be delivered in parallel as separate work packages.

Is this an appropriate application of the ‘plans’ practice, and why?

A.

Yes, because data from previous projects should determine the schedule without reviewing the dependencies between the products

B.

Yes, because product dependencies determine sequence, and independent work packages may be planned to run in parallel

C.

No, because work delivered by the same supplier must be scheduled sequentially and should avoid running in parallel

D.

No, because setting work-package tolerances determines the order in which products must be produced

The City Council asks the portfolio office, independently of the LouisShopping project team, to provide confidence that the design and build will preserve the historic setting while incorporating the required technology.

Is this an appropriate application of the quality practice, and why?

A.

Yes, because the portfolio office should manage the project’s quality-control activities on behalf of the project manager

B.

Yes, because the business layer may use the portfolio office to perform independent quality-assurance activity on its behalf

C.

No, because assurance information may be provided to the project board and not to the business layer

D.

No, because a portfolio office may assess strategy but may not review the delivery of individual projects

In stage 4, the Heritage Director delegates a review of the inspection arrangements to the Heritage Manager. The Heritage Manager will work with the BuildyBrick CEO and the project manager, then report whether the planned inspections will provide adequate assurance about impacts on historic buildings.

Is this an appropriate application of the ‘define roles, responsibilities and relationships’ principle, and why?

A.

Yes, because the principle requires that communication channels between all internal and external project team members remain open and transparent at all times

B.

Yes, because the Heritage Manager needs a clear understanding of what the Heritage Director requires of them and of what they may reasonably expect from the other parties involved

C.

No, because it is the project manager’s responsibility to specify how inspections of historically significant buildings should be planned and executed

D.

No, because the Heritage Director, as senior user, should personally conduct the assurance review of the inspection plans rather than delegating to the Heritage Manager