Theoretically construct a summary activity for activities 2001 through 2004. Using the "normal" schedule, what is the cost of the hammock?

A.

$271,000

B.

$299,000

C.

$139,000

D.

$289,000

How could the structural steel drawing delay have been prevented?

A.

Add a time buffer at the end of structural steel activities.

B.

Allow adequate time for review and resubmittal in the baseline schedule.

C.

Release the structural steel for fabrication concurrent with review of structural steel shop drawings.

D.

Switch to post-tensioned concrete construction.

Management has determined the need to release the product 20 days earlier than planned. What tasks need to be expedited?

A.

Drafting and Proofing the Manual.

B.

Packaging only.

C.

Printing the Manual.

D.

Testing, Manufacturing and Packaging.

What is the actual duration as of the status date or data date of Activity B?

A.

7.

B.

3.

C.

0.

D.

4.

Which of the following will NOT affect the total float calculation of a non-resource leveled schedule?

A.

Multiple calendars.

B.

Start and finish constraints.

C.

Preferential logic.

D.

Front end loading.

What owner action could have mitigated the late completion of the project?

A.

Hire a more senior project manager.

B.

Self-perform more of the work.

C.

Use a procurement agent to monitor and expedite equipment deliveries.

D.

Prepare better structural steel drawings.

Determine the correct formula and date for the late finish for Activity 6002.

A.

LS of 6003 plus 1 day equaling 09 Mar 2023

B.

LS of 6003 less 1 day equaling 09 Mar 2022

C.

LS of 6003 less 1 day equaling 09 Mar 2023

D.

LS of 6003 plus 1 day equaling 09 Mar 2022

Which of these letters, symbols or words best approximates the graphical shape of a project's cumulative BCWS?

A.

/

B.

Bell curve

C.

S

D.

_

When reconstructing a CPM schedule electronically from a hardcopy, which of the following is NOT required to determine the critical path?

A.

Detailed listing of working days for each calendar used

B.

Predecessor and successor listing with logic type and lag duration, preferably sorted by activity ID

C.

Assigned party responsibility for each work task

D.

Tabular listing of activities showing duration, calendar ID, early and late dates

In order for a claimant to be entitled to an extension of contract time for a delay event (and further to be considered compensable):

A.

The delay must affect the critical path.

B.

The delay must be concurrent with the delay attributable to both parties.

C.

The delay must not cause monetary harm to the defendant.

D.

The delay must affect the contractor's planned construction schedule.