Which of the following is not an internal stakeholder?

A.

Owner

B.

installer

C.

Subcontractor

D.

Prime Contractor

Determine the correct formula and date for the late finish for Activity 2002.

A.

LS.2003 - 1 day -> 11.06.01.

B.

LS.2003 - 1 day -> 10-06-01.

C.

LS.2003 + 1 day -> 10-07-01.

D.

LS.2003 - 1 day -> 10-05-01.

Each column must be poured in one day. Each column requires 2,000 cubic feet of concrete. The lift bucket has a capacity of 40 cubic feet. How many lifts will be required per column pour?

A.

80 lifts

B.

50 lifts

C.

5 lifts

D.

20 lifts

What is the result of a forward pass calculation?

A.

Value of total float for individual activities

B.

Early start and early finish date for individual activities

C.

Value of free float for individual activities

D.

Critical path

When reconstructing a CPM schedule electronically from a hardcopy, which of the following is NOT required to determine the critical path?

A.

Detailed listing of working days for each calendar used

B.

Predecessor and successor listing with logic type and lag duration, preferably sorted by activity ID

C.

Assigned party responsibility for each work task

D.

Tabular listing of activities showing duration, calendar ID, early and late dates

What project cost elements would NOT normally be reflected in the Activity 1000?

A.

Home office expenses

B.

CPM processing and updating

C.

Materials used in the construction

D.

Job site quality control

Which of the following is NOT true?

A.

Remaining durations can exceed original durations.

B.

Constraints can interfere with the longest path calculation.

C.

Multiple calendars can affect the total float calculation.

D.

A network must contain only one Critical Path.

Schedules are periodically updated to reflect progress. What step should NOT occur before the update is considered complete?

A.

All managers should be encouraged to review contiguous activity status

B.

The process of each activity should be indicated by the responsible manager

C.

The critical path should not be revisited to ensure all the downstream logic and durations are still accurate

D.

The project team should be asked to review status for accuracy

What is accurate about Activity 7001 in the precedence diagram?

A.

The successor FF lag from 7001 to 11001 is not shown

B.

The LF is correct

C.

The TF is not calculated correctly

D.

The LF is not correct

Which of the following documents is most likely to be of the LEAST value to a planner/scheduler when planning a contractor's baseline critical path schedule for the construction of a large high-clearance bridge located very near an airport? The contractor has been awarded the contract.

A.

The project plans and specifications

B.

The project geotechnical report

C.

The regulations published by the government aviation agency

D.

The government's report on future high-clearance bridge projects