Summer Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: ecus65

AACE International PSP - Planning & Scheduling Professional (PSP) Exam

Page: 5 / 5
Total 163 questions

Using the "normal" schedule, what is the early finish date of activity 10002 and its total float?

A.

12-27-03 and 24 days of float

B.

12-18-03 and 4 days of float

C.

12-17-03 and 4 days of float

D.

12-18-03 and 25 days of float

In the "normal" schedule, excluding Activity 1000, what activity(s) are concurrent with Activity 3001?

A.

2003 and 7001.

B.

2004.

C.

4001, 5001 and 6001.

D.

4001 and 5001.

An earned value-based project control system can use either of which two budgets as the basis of its calculations?

A.

Labor hours or dollars.

B.

Direct or indirect cost.

C.

Earned or budgeted cost yearly.

D.

Linear feet or dollars.

What activities are concurrent to Activity 2001 in the "normal" schedule?

A.

7001.

B.

1001.

C.

1000.

D.

2003.

Theoretically construct a summary activity for activities 6001 through 6003. Identify the governing predecessor and successor activities for the hammock:

A.

Predecessor is activity 5001, successor is activity 8001

B.

Predecessor is activity 4001, successor is activity 8001

C.

Predecessor is activity 9001, successor is activity 9002

D.

Predecessor is activity 5001, successor is activity 8002

During proofing of the product manual, a problem was discovered requiring 15 days additional time to affect a correction. How can the date of availability be maintained?

A.

Expedite Draft Product Manual by 5 days

B.

Delay Release for Manufacture by 5 days

C.

Delay Manufacture Product by 5 days

D.

Expedite Package Product by 5 days

In a "crashed" schedule, which is a chain of activities that precede activity 2004?

A.

1001, 2001, 2002, 2003

B.

2001, 2002, 2003, 2007

C.

1001, 2002, 2003

D.

1001, 2002, 2002, 2003, 3001

Using the crashed schedule, if you start Activity 2002 on 12 August 2021. what is the finish date for Activity 2002?

A.

19 Sep 2021

B.

08 Sep 2021

C.

09 Sep 2021

D.

27 Aug 2021