New Year Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmas50

AACE International PSP - Planning & Scheduling Professional (PSP) Exam

Page: 7 / 7
Total 216 questions

Which of the following will always describe the critical path? The path with

A.

The longest duration through the network.

B.

Zero float.

C.

Negative float.

D.

The shortest duration and negative float.

Activity 2003 started during the current reporting period and proceeded as planned with the normal schedule. If the remaining duration at the end of this period is ten workdays, then what is the earned value assignable to Activity 2003 in the pay estimate for this reporting period?

A.

$6,000

B.

$10.000

C.

$5,000

D.

$8,000

Which of the following parties is NOT a stakeholder of the Spring Highway project?

A.

ALPHA

B.

GOUGE

C.

BILCO

D.

DEVCO

The Scope of Work divides the major deliverables into smaller more manageable components for all of the following EXCEPT to:

A.

improve the accuracy of cost, time, and resource estimates

B.

facilitate clear responsibility assignments

C.

define a baseline for performance measurement and control

D.

establish the Performance Measurement Baseline values