Summer Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: ecus65

AACE International PSP - Planning & Scheduling Professional (PSP) Exam

Page: 1 / 5
Total 163 questions

Using the "normal" schedule, if you start Activity 7001 on April 1, 2002, and using a 5-day workweek, what the finish date for Activity 7001?

A.

06-11-02.

B.

06-04-02.

C.

06-18-02.

D.

06-05-02.

Determine the correct formula and date for the late finish for Activity 9004.

A.

LS.10002 + 1 day -> 11-29-03.

B.

LS.10002^ Lag.7 + i day -> 11-20-03.

C.

LS.10002 - 1 day -> 11-27-03.

D.

LS.10002 - Lag.7 - l day -> 11-20-03.

Using the normal schedule, given Activity 3001 and the relationship with Activity 4001. what is indicated?

A.

The activities are independent, with Activity 4001 starting 15 days earlier than the start

of Activity 5001

B.

These activities are partially concurrent, with Activity 4001 starting 15 days after the

start of Activity 3001

C.

These activities are sequential, with Activity 4001 starting 15 days earlier than the start of Activity 3001.

Which of the following options is NOT a feasible method to reduce the overall completion time of the toll road program?

A.

Subcontract outside forces to accelerate the Phase A Schedule

B.

Allocating forces from other BILCO contracts to the toll road project

C.

Proceeding with the work in advance of the environmental studies

D.

Reduce the phasing from 5 phases to 3 phases

Which of the following documents is most likely to be of the LEAST value to a planner/scheduler when planning a contractor's baseline critical path schedule for the construction of a large high-clearance bridge located very near an airport? The contractor has been awarded the contract.

A.

The project plans and specifications

B.

The project geotechnical report

C.

The regulations published by the government aviation agency

D.

The government's report on future high-clearance bridge projects

Select the most appropriate explanation for use of a winter/wet weather seasonal calendar for use in this project?

A.

to highlight a time when there are more holidays and work therefore will be slower and there will be more absenteeism

B.

to denote a time during which work may not progress as fast as planned and cost and risk may be elevated

C.

to provide a key to co-a weather for safety meetings

D.

to show a difference in the calendar year

The linear scheduling velocity diagram has the following two-axis:

A.

Location and crew size

B.

Time and location

C.

Time and rate of progress

D.

Time and crew size

A good change management plan___________.

A.

is provided to stakeholders after it is created

B.

is detailed during the planning phase

C.

tracks minor decisions

D.

involves only the project controls team

Which statement is true?

A.

Where compensability cannot be established, excusability is assumed.

B.

Where compensability can be established, excusabltity cannot be assumed.

C.

Where compensability cannot be established, excusability is a given.

D.

Where compensability can be established, excusability is assumed.

Which of the following will always describe the critical path? The path with

A.

The longest duration through the network.

B.

Zero float.

C.

Negative float.

D.

The shortest duration and negative float.