AACE International PSP - Planning & Scheduling Professional (PSP) Exam

Page: 1 / 7
Total 216 questions

If a contractor has robust planning and scheduling processes, should those company processes supersede client contract specifications?

A.

Proceed with company processes even if they conflict with the client

B.

The client contract specifications always have priority

C.

Review any differences and negotiate workable specifications

D.

Suggest that the client issue a change order, accepting the contractor's processes

When using a detailed estimate as the basis for work package/activity durations, which element does NOT need to be identified before the activity durations can be calculated?

A.

Projected crew size

B.

Estimated labor hours

C.

Hours in a standard work day

D.

Estimated cost

If drafting of the product manual overruns its planned duration by 5 days, how many days may the manufacturing be delayed without affecting release of the product?

A.

15 days.

B.

10 days.

C.

0 days.

D.

5 days.

What is a key first step in developing a critical path method schedule?

A.

Drawing a bar chart of the key phrases of the work.

B.

Defining the execution plan to meet the required scope of work.

C.

Setting out the resource to be used and its limitations.

D.

Drawing the logic diagram.

What owner action could have mitigated the late completion of the project?

A.

Hire a more senior project manager.

B.

Self-perform more of the work.

C.

Use a procurement agent to monitor and expedite equipment deliveries.

D.

Prepare better structural steel drawings.

Which of the following procedures is generally recognized as acceptable when updating a schedule?

A.

Report an actual date when the activity is on a non-work calendar for that date

B.

Change a previously reported actual date

C.

Change the WBS assignment for an activity

D.

Change a calculated date in the future

What is the cycle time?

A.

5 minutes

B.

17 minutes

C.

14 minutes

D.

6 minutes

Using the normal schedule, given Activity 3001 and the relationship with Activity 4001. what is indicated?

A.

The activities are independent, with Activity 4001 starting 15 days earlier than the start

of Activity 5001

B.

These activities are partially concurrent, with Activity 4001 starting 15 days after the

start of Activity 3001

C.

These activities are sequential, with Activity 4001 starting 15 days earlier than the start of Activity 3001.

Which of the following is NOT a tool or technique used to perform scope planning?

A.

Benefit cost analysis.

B.

Schedule performance indexing.

C.

Expert Judgment.

D.

Alternatives identification.

Identify the minimum project duration.

A.

20 months.

B.

16 months.

C.

19 months.

D.

21 months.